Clean Energy and Regulation in India : Role and Challenges of Civil Society Participation PowerPoint Presentation
Download Presentation
Clean Energy and Regulation in India : Role and Challenges of Civil Society Participation

Loading in 2 Seconds...

play fullscreen
1 / 36

Clean Energy and Regulation in India : Role and Challenges of Civil Society Participation - PowerPoint PPT Presentation


  • 86 Views
  • Uploaded on

Clean Energy and Regulation in India : Role and Challenges of Civil Society Participation. M. Thimma Reddy Shantanu Dixit Prayas (Energy Group) India Electricity Governance Initiative. Agenda. Overview Legal, Policy framework, Regulatory initiatives

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Clean Energy and Regulation in India : Role and Challenges of Civil Society Participation' - dale


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
clean energy and regulation in india role and challenges of civil society participation

Clean Energy and Regulation in India: Role and Challenges of Civil Society Participation

M. Thimma Reddy

Shantanu Dixit

Prayas (Energy Group) India

Electricity Governance Initiative

agenda
Agenda
  • Overview
    • Legal, Policy framework, Regulatory initiatives
  • Current Status of Clean Energy in five Indian states
  • Challenges to maintaining CE momentum
  • Role and importance of civil society participation
  • Barriers to enhanced CSI Participation : Lessons from five Indian states
  • Concluding comments
electricity act 2003 promising provisions for clean energy
Electricity Act 2003 : Promising Provisions for Clean Energy
  • Preamble : Promotion of efficient and environmentally benign policies
  • S. 61, S. 86 : Promotion of co-generation and renewable energy sources (RE)
    • Tariff, Grid Connectivity, Sale to any person, Specify % of RE use
  • S. 61 : Tariff to encourage efficiency, economical use of resources, optimum investments
national policies e p 05 tp 06 napcc 08 strengthened mandate for clean energy
National Policies: (EP 05, TP 06, NAPCC 08)Strengthened mandate for clean energy
  • Full exploitation of feasible RE potential
  • Preferential feed-in tariff
  • High priority to Demand Side Management (DSM)
  • Adoption of load management techniques, Time of Use tariff
  • RE contribution target of 15% by 2020
regulatory initiatives accelerating deployment of clean energy 1
Regulatory Initiatives:Accelerating Deployment of Clean Energy ..1
  • Central Regulatory Commission Initiatives
    • Terms and conditions for RE tariff determination
    • Renewable Energy Certificates
    • Multi-state program for accelerated deployment of efficient appliances
regulatory initiatives accelerating deployment of clean energy 2
Regulatory Initiatives:Accelerating Deployment of Clean Energy ..2
  • Technology specific feed in tariffs (yr 2002 to 2006)
    • Typical tariff preferential of about Rs. 0.80 – 1.20 / kWh
    • Higher rate of return
  • Long term power purchase agreements (13 to 20 years)
    • Connectivity
    • Payment security
regulatory initiatives accelerating deployment of clean energy 3
Regulatory Initiatives:Accelerating Deployment of Clean Energy ..3
  • Renewable portfolio standards / Renewable Purchase Obligations (2006 –2010)
clean energy deployment current status of energy efficiency
Clean Energy Deployment: Current status of energy efficiency
  • Sporadic regulatory efforts to promote EE
    • Maharashtra
      • CFL DSM program - over 10 MW saving
      • Load Management Charge
    • Time of Use tariff, Capacitor programs
clean energy deployment challenges to maintain momentum
Clean Energy Deployment: Challenges to maintain momentum
  • Un-even development across states
  • Emphasis on high positive cost RE options, while low / -ve cost EE getting less attention
  • Increasing tariff impact (MH ~ Rs. 900 Crore/Yr.)
  • Lukewarm, at times, negative response by some utilities and large consumers (Spenser's case)
clean energy deployment challenges to maintain momentum11
Clean Energy Deployment: Challenges to maintain momentum

R E Potential:

Biomass – Andhra Pradesh

NEDCAP Estimate: 627 MW

ASCI Estimate: 225 MW

Projects Sanctioned: 270 MW

Existing Capacity: 220 MW

clean energy deployment challenges to maintain momentum12
Clean Energy Deployment: Challenges to maintain momentum

R E Potential:

Biomass – Maharashtra

Estimated Potential: 781 MW

Present installed capacity is only 12% of the estimated potential. Already availability of biomass fuel has become a problem

“…the price of the biomass is also increasing because of the unavailability of biomass fuels” (para 22, Order Dt. 14-12-2009)

clean energy deployment challenges to maintain momentum13
Clean Energy Deployment: Challenges to maintain momentum

R E Potential:

Biomass – Tamil Nadu

2006 Estimate: 500 MW

2009 Estimate: 868 MW

MNRE Estimate: 967 MW

Exiting Capacity: 272 MW

clean energy deployment challenges to maintain momentum14
Clean Energy Deployment: Challenges to maintain momentum

R E Potential:

Wind – A.P. NEDCAP Estimate: 2110 MW

InWEA Estimate: 8675 MW

Maharashtra: MEDA Estimate: 6500 MW

ABPS Estimate: 4584 MW

Orissa: OREDA Estimate: 1700 MW

WISE Estimate: 2430 MW

clean energy deployment challenges to maintain momentum15
Clean Energy Deployment: Challenges to maintain momentum

R E Potential:

Solar – Orissa

OREDA Estimate: 14,000 MW

WISE Estimate: 5,000 MW

clean energy deployment challenges to maintain momentum16
Clean Energy Deployment: Challenges to maintain momentum

Past Policies:

  • Capital subsidies – Accelerated depreciation
  • The Scheme was misused
  • Generation Based Incentive
  • Who will finance RE intervention?
  • Present attention is to add massive conventional capacities
  • RE is not being looked at as an alternative
clean energy deployment challenges to maintain momentum17
Clean Energy Deployment: Challenges to maintain momentum

Government Intervention:A.P. Wind Tariff:

GoAP Order Dt. 11-04-2008 = Rs.3.10/U

GoAP Order Dt. 09-09-2008 = Rs.3.50/U

APERC Order Dt. 01-05-2009: adopted corresponding tariff

A.P. Biomass:

GoAP Order Dt. 12-11-2008 = Rs.3.79/U

APERC Order Dt. 31-03-2009 = Rs.3.95/U

These Orders were given under S.108 of E. Act 2003

clean energy deployment challenges to maintain momentum18
Clean Energy Deployment: Challenges to maintain momentum

Lack of Coordination:

  • Multiple departments are involved
  • Lack of coordination among these departments
  • Orissa: OREDA, Dept. of Science and Technology, Irrigation Dept., State Technical Committee, GRIDCO
  • Tamil Nadu: TEDA, TNEB, Irrigation Department
clean energy deployment challenges to maintain momentum19
Clean Energy Deployment: Challenges to maintain momentum

Lack of capacity of EDAs:

  • Do not have adequate manpower
  • The existing staff does not have capacity
  • Some times/places All India Service personnel head them, and they consider it as a punishment posting
  • Political interference
clean energy deployment challenges to maintain momentum20
Clean Energy Deployment: Challenges to maintain momentum

Lack of Transparency:

Capital Cost: A.P. – Wind Energy

APERC approved capital cost: Rs. 4.70 Crore/MW

clean energy deployment challenges to maintain momentum21
Clean Energy Deployment: Challenges to maintain momentum

Lack of Transparency:Fuel Price – Maharashtra

Biomass: MERC Order Dt. 14-12-2009: Biomass variable cost increased from Rs. 1.34 per unit to Rs. 3.28. Total cost increased to Rs. 4.98 per unit

“discrepancies and reliability of data was a major issue in arriving at necessary conclusion”. (Para 54)

Same biomass price continued in RE Tariff Regulation 2010 (Para 46.1)

clean energy deployment challenges to maintain momentum22
Clean Energy Deployment: Challenges to maintain momentum

Lack of Transparency:Fuel Price – Maharashtra

Bagasse: MERC Order Dt. 11-01-2010: Cogen power tariff increased from Rs. 3.50 per unit to Rs. 4.79 due to hike in bagasse price

“The Petitioner has neither provided any statistics, computations of cost of generation nor any supporting documents for the operational cogeneration projects” (Para 49)

Same bagasse price continued in RE Tariff Regulation 2010 (Para 55.1)

clean energy deployment challenges to maintain momentum23
Clean Energy Deployment: Challenges to maintain momentum

Lack of Transparency:

Project Cost – Orissa

Project cost decided by State Technical Committee

  • Incase of dispute OERC advises the parties to settle it through discussions
  • Then OERC approve the outcome of the discussions
clean energy deployment challenges to maintain momentum24
Clean Energy Deployment: Challenges to maintain momentum

Lack of Transparency: Solar tariff

What is appropriate tariff for Solar power?

Whether competitive bidding provides solution.

clean energy deployment challenges to maintain momentum25
Clean Energy Deployment: Challenges to maintain momentum

Absence of Performance Monitoring:

  • EDAs
  • Pollution Control Boards
  • ERCs
clean energy deployment challenges to maintain momentum26
Clean Energy Deployment: Challenges to maintain momentum

Environmental and Social Impacts:

Biomass Power Plants: A.P.

Municipal Solid Waste based Plants

Wind Energy Plants

civil society participation critical for addressing emerging challenges
Civil Society Participation: Critical for addressing emerging challenges
  • Support for innovative solutions and managing trade-offs
  • Push for balanced, rational but ambitious deployment of clean energy
  • Make regulators, utilities, project developers and large consumers accountable
civil society participation huge opportunity
Civil Society Participation: Huge opportunity
  • Many spaces for CSI intervention
    • Regulatory commissions required to function in a transparent manner (public notice etc.)
    • CSIs can file petitions
    • Participate in public hearings
    • Large no. of ‘green’ CSIs

 Create ‘demand pull’

civil society participation but limited use
Civil Society Participation: ….. but limited use
  • Civil society intervention in RE cases
barriers to enhanced csi participation lessons from five indian states
Barriers to enhanced CSI ParticipationLessons from five Indian states
  • Awareness amongst CSIs
    • Role and process of regulatory decision making
    • Opportunities / Spaces for CSI intervention
    • Potential and feasibility of CE options
    • Importance of appropriate RC and utility actions
barriers to enhanced csi participation lessons from five indian states 2
Barriers to enhanced CSI ParticipationLessons from five Indian states ..2
  • Resources and capability of CSIs
    • Analytical resources - Technical, financial, legal
    • Financial resources
      • Hire analytical resources
      • Long drawn, sustained interventions needed for success
      • Stakeholder engagement and interactions
barriers to enhanced csi participation lessons from five indian states 3
Barriers to enhanced CSI ParticipationLessons from five Indian states ..3
  • Transparency about RE generation costs
    • In-adequate information about costs and performance norms
    • Significant upward changes in fuel / capital costs
    • Lack of transparency about nature and scale of subsidies, concessions
    • Concerns about excessive tariff and profiteering by developers
    • Consumers’ inputs not taken into account: e.x. AP

 Concerns about ‘Is the premium reasonable ?’

barriers to enhanced csi participation lessons from five indian states 4
Barriers to enhanced CSI ParticipationLessons from five Indian states ..4
  • Effective performance monitoring systems
    • Little monitoring of project performance after clearances and power purchase agreements by authorities

 Concerns about ‘is the premium justified?’

barriers to enhanced csi participation lessons from five indian states 5
Barriers to enhanced CSI ParticipationLessons from five Indian states ..5
  • Consideration of social and environmental impacts of RE generation
    • Biomass projects – De-forestation, un-availability of cooking fuel
    • Wind – Compensation for land, impact on common property rights
  • Recognition of CSIs role
    • ERCs, Utilities, Developers should appreciate and encourage role of CSIs
concluding comments
Concluding comments
  • Enhanced CSI participation in RC is crucial for sustained and ambitious CE program
  • RCs and funding agencies can play a significant role in enhancing CSI role
    • RCs – Ensure better transparency (costs, potential ) and performance monitoring
    • Development organizations and funding agencies – Support Awareness and capacity building of CSIs
    • Government and Project Developers – Transparency about costs and performance, mechanisms to address local social and environmental concerns
slide36
Thank you.

M. Thimma Reddy

Shantanu Dixit

Member, Prayas (Energy Group), India

www.prayaspune.org/peg

shantanu@prayaspune.org

Electricity Governance Initiative

www.electricitygovernance.org