Montana Truss Rehabilitation Projects. Lozeau Bridge over the Clark Fork Dearborn River High Bridge Van Buren Street over the Clark Fork. Lozeau Bridge Over the Clark Fork. Constructed 1924 Near Thompson Falls, MT Moved & Reconstructed During WWII in 1944

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Montana Truss Rehabilitation Projects' - dakota


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
montana truss rehabilitation projects

MontanaTruss Rehabilitation Projects

Lozeau Bridge over the Clark Fork

Dearborn River High Bridge

Van Buren Street over the Clark Fork

lozeau bridge over the clark fork
Lozeau Bridge Over the Clark Fork
  • Constructed 1924 Near Thompson Falls, MT
  • Moved & Reconstructed During WWII in 1944
  • USFS With Permission From the War Department
  • Used POW Labor, Local Aggregate
  • Reconstructed in 1998 by MDT

Lozeau Bridge Near Superior, Montana

challenges and solutions
Challenges and Solutions
  • Column Encasement or Replacement
  • Existing columns had been patched in places
  • Original intent was to repair spalled/unsound areas
  • During construction, discovered some areas that were far worse than expected.

Lozeau Bridge

challenges and solutions4
Challenges and Solutions
  • Need to Raise and Support Truss
  • To Repair or Replace Substructure Units and Bearings
  • No End Floor Beams
  • Can’t Jack Against Bottom Chord
  • Solution – Use Jacking Frame
  • Lift Truss From Above Using Cradle under Truss Pins
  • Supports Stringers From Jacking Frame Easily

Lozeau Bridge

challenges and solutions5
Column Encasement or ReplacementChallenges and Solutions
  • Superstructure was temporarily supported by a jacking frame
  • Columns and cap were completely replaced at the end piers
  • Columns were jacketed with a reinforced concrete shell at the center pier

Lozeau Bridge

challenges and solutions6
Challenges and Solutions
  • Attach New Railing to Lightweight Truss or Deck
  • Attach Truss Rail Posts to Steel Stringers and Curbs
  • Railing Independent of Truss
  • Approach Spans Rail Posts Bolted to Curbs and Stringers

Lozeau Bridge

challenges and solutions7
Challenges and Solutions
  • Timber Decks - Maintain Historic Deck Material Type and Minimize Dead Load
  • Pentachlorophenol
  • Running Planks
  • 5 1/8” Glued-Lam Deck
  • Nail Lam Deck at End Spans
  • BMP for Use of Treated Wood in Aquatic Environments

Lozeau Bridge

dearborn river high bridge
Dearborn River High Bridge
  • Built 1897 by the King Bridge Co. Cleveland, OH
  • Lewis and Clark County, Before Highway Dept.
  • Unusual Mid-Deck Truss, Only One Remaining?
  • Reconstructed in 2003 by MDT
  • Venetian Red

Dearborn River High Bridge Near Augusta, MT

challenges and solutions9
Rock Embankment StabilizationChallenges and Solutions
  • Existing Abutment was founded on an unstable rock outcropping
  • Unstable rock mass was threatening existing columns

Dearborn River High Bridge

challenges and solutions10
Rock Embankment StabilizationChallenges and Solutions

Unstable rock mass

Caisson knocked partially

out from under bearing

Dearborn River High Bridge

challenges and solutions11
Challenges and Solutions
  • Need to Raise and Support Truss
  • Stabilize Rock Slope at End
  • Replace all Substructure Units and Bearings
  • Can’t Jack Against Bottom Chord
  • Solution – Deck is to be Removed and Replaced, Remove Lightweight Truss to Bank
  • Use Special Bolted Lifting Points and Spreader Beams

Dearborn River High Bridge

challenges and solutions12
Challenges and Solutions
  • Abutment Replacement & Rock Stabilization
  • Remove unstable rock mass by controlled blasting
  • Stabilize slope by rock bolting
  • Socket the new abutment into competent rock
  • Stabilize approach with gabion baskets

Dearborn River High Bridge

challenges and solutions14
Abutment No. 5 Challenges and Solutions

Dearborn River High Bridge

challenges and solutions17
Substructure ReplacementChallenges and Solutions
  • Reusing the existing stone in the new abutment

Dearborn River High Bridge

challenges and solutions18
Substructure ReplacementChallenges and Solutions

Reusing the existing stone in the new approach span footings

Dearborn River High Bridge

challenges and solutions19
Challenges and Solutions
  • Replace / Repair Old Bearings

New Elastomeric Bearings

New Expansion Bearing Sole Plate

Dearborn River High Bridge

challenges and solutions20
Challenges and Solutions
  • Timber Deck - Maintain Historic Deck Material Type and Minimize Dead Load
  • Creosote
  • 3 1/8” Glued-Lam Deck
  • Transverse & Longitudinal
  • BMP for Use of Treated Wood in Aquatic Environments
  • Most Agencies Do Not Use Creosote Now

Dearborn River High Bridge

challenges and solutions21
Challenges and Solutions
  • Attach New Railing to Lightweight Truss or Deck
  • Longitudinal Decking - Attach Posts to Floor Beams for Approach Spans
  • Transverse Decking - Attach Posts to Structural Tubes in Plane of Deck Between Deck Panels
  • Rail Posts Independent of Truss

Dearborn River High Bridge

challenges and solutions22
Challenges and Solutions
  • OVERCOAT PAINT SYSTEM

Dearborn River High Bridge

  • Restored original color of bridge – “Venetian Red”
  • High pressure water blast and mechanical cleaning
  • Moisture cure urethane overcoat system
  • Make sure paint system is compatible with existing paint
van buren st over the clark fork
Van Buren St. Over the Clark Fork
  • Built 1892-3 on Higgins Avenue
  • Washed out in Flood 1908
  • Salvaged & Moved Upstream to Van Buren Street
  • Sidewalks Outside Truss Removed
  • Converted to Pedestrian Use in 1975
  • Reconstructed by Missoula County in 2004

Van Buren Street Bridge - Missoula, MT

challenges and solutions24
Challenges and Solutions
  • Miscellaneous Truss Repairs – Eyebar Hanger

Van Buren Street Pedestrian Bridge

challenges and solutions25
Challenges and Solutions
  • Miscellaneous Truss Repairs - Verticals

Van Buren Street Pedestrian Bridge

challenges and solutions26
Challenges and Solutions
  • Miscellaneous Truss Repairs – Top Flange Repair
  • All of the top flanges on the built-up floor beams were severely rusted and needed replacement.
  • The existing flange angles were removed and used as a template to drill holes in the new angles

Van Buren Street Pedestrian Bridge

challenges and solutions27
Challenges and Solutions
  • End Frame Replacement

Van Buren Street Pedestrian Bridge

challenges and solutions28
Challenges and Solutions
  • Heat Straightening & Heat Shortening

Van Buren Street Pedestrian Bridge

  • The existing eye bars elongated over the years
  • Performed heat shortening to remove slack
  • Left cables in place
challenges and solutions29
Challenges and Solutions
  • Timber Decks - Maintain Historic Deck Material Type and Minimize Dead Load
  • Penta in Light Oil for Pedestrian Usage
  • 3 1/8” Glued-Lam Deck
  • Re-sawn for Traction
  • BMP for Use of Treated Wood in Aquatic Environments

Van Buren Street Pedestrian Bridge

challenges and solutions30
Challenges and Solutions
  • Attach New Railing to Lightweight Truss or Deck
  • Attach to Steel Stringers
  • Independent of Deck or Truss
  • Allows Easy Future Deck Replacement
  • Note Attachment of Decorative Light-posts at
  • Floor-beam Locations.

Van Buren Street Pedestrian Bridge

construction costs
Construction Costs
  • Lozeau Bridge – 1998 Total Cost $1,500,000 $190 / Sq. Ft.
  • Dearborn R. High Br. – 2003 Total Cost $1,000,000 $250 / Sq. Ft.
  • Van Buren Br. – 2004 Total Cost $350,000 $60 / Sq. Ft.
design resources
Design Resources
  • Heat Straightening - Holt
  • Heat Shortening Details and Specs – AREMA and Old DOT Standards
  • Old Steel Sections - Old Books
  • AASHTO
pictures
Pictures

Lozeau Bridge

pictures35
Pictures

Lozeau Bridge

pictures36
Pictures

Dearborn River High Bridge

pictures37
Pictures

Dearborn River High Bridge

pictures38
Pictures

Dearborn River High Bridge

pictures39
Pictures

Dearborn River High Bridge

pictures40
Pictures

Dearborn River High Bridge

pictures41
Pictures

Dearborn River High Bridge

pictures42
Pictures

Van Buren Street Bridge

pictures43
Pictures

Van Buren Street Bridge

pictures44
Pictures

Van Buren Street Bridge

pictures45
Pictures

Van Buren Street Bridge