1 / 27

6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT. Presented by Eyob Yehayis. 1. Project Area Description. Bililo spate is located at 42.75 N and 9.233E The average altitude is 1450 m. The annual mean rain fall is 757.15 mm. The annual effective RF=579.4mm

cwen
Download Presentation

6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 6.12aDESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT Presented by Eyob Yehayis

  2. 1. Project Area Description Bililo spate is located at 42.75 N and 9.233E • The average altitude is 1450 m. • The annual mean rain fall is 757.15 mm. • The annual effective RF=579.4mm • T max=31.6 and T min=15.6 oc • The Annual mean ETo=1902.77mm

  3. 1. Project Area Description Continued… • The cropping season starts in 15th march dominantly they produce sorghum. • The crop water required during the cropping season 579.14 mm. • The total effective rainfall during the cropping season is 338 mm. • Irrigation required = CWR-ERF = 259.69 mm

  4. 1. Project Area Description Continued… • The watershed Area is 157 km2 of which above 70% of it is covered by forest and scattered bushes, the rest is farmland. • About 25% of the cathment has a slope>28 % • The Project is almost it is a newly designed spate irrigation scheme.

  5. 2 The basic assumptions used for the project. • The system should be easy for farmers to operate and not require the large inputs of labor or other resources to maintain. • The system should prevent large and uncontrolled flood flows from damaging canals and field systems. • The system should Continue to function with high rates of sedimentation on the fields and canal beds.

  6. 3 Structural Component of The System 4.1 Weir (Diversion Head work) 4.2 Canal and Canal Structures

  7. 3.1 Weir (Diversion Head work) • The head work is modified to discharge the excess flood that is expected to come in 50 year return period. • Accordingly , the maximum flood for 50 years Return period is 110 3/s. • Designed to provides the required head to command the Farmland. • The intake canal sill level is 0.3 m above under sluice level.

  8. 3.2 Canal and Canal Structures 3.2.1 Flood Canal (Main canal) The design canal capacity is determined by the following assumptions: • The recession flood stays for 5 days • The farm land is provided with 25 cm flood water on one irrigation. • Farm land have chance of getting 2 flood water irrigation during the growing season. • The resulting design capacity is 3 m3/s for 500ha.

  9. 4.2. Flood Canal cont’ed… • The canal cross section and bed slope is designed on the maximum permissible velocity which satisfy 60% design flow to avoid the silt deposition on canal bed at lower flow. • Some of the canal cross section which passes porous and cliff formation is lined with masonry. • The secondary canal capacity is designed by proportioning the hectare it develops and multiplying by flood duration day ( 5 days).

  10. 4.2.1 Flood Canal cont’ed… Generally The System has: -Earthen canal on main canal 5 km on secondary canal 10.5km, 11 in number -Lined canal on main canal 2.3 km

  11. 4.2.2 Canal Structures • The system is provided with different farm structures which satisfies the hydraulic performance and structural stability depending on the land topography. • Accordingly, on the main canal there are: • 4 vertical drops • 32 inclined drops 7 of which on secondary canal • 1 flume • 5 division box • 4 chute 2 of which on SC1 • 3 Road crossing culverts

  12. 5 Water Management • It is assumed that only 1/5 of the command area is irrigated in one day starting from upstream toward the down stream. This could be changed based on the community interest.

  13. 6 Problem encountered • Estimating the frequency, amount and duration of the flood water in un gauged rivers. • Estimating the sediment yield with the respective runoff.

  14. Head Work

  15. Downstream face of Weir

  16. Downstream of Headwork

  17. Flood water entering the canal

  18. Rejection spillway

  19. Lined canal

  20. Canal running along the cliff

  21. Flume upstream

  22. Division box with drop

  23. Secondary canal under construction

  24. Recession flow

  25. Canal Silting

More Related