CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100. Prepared by: Program Management Branch (HGP) 22 September 2004 009/HGP/2004. CTA PLANNING EMBRAER PROGRAM ERJ170-200. ACTIVITIES -Total Number of Reports : 314

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about '' - clementine-giles


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Cta planning main hour m h for embraer programs erj170 200 and erj190 100

CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100

Prepared by: Program Management Branch (HGP)

22 September 2004

009/HGP/2004


Cta planning embraer program erj170 200

CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ170-200

ACTIVITIES

-Total Number of Reports : 314

Reports for CTA review : 104 (67% delegation) (2000 m-h)

Specialists Meetings : 9 weeks (2 m; PF1 availab.) (6000 m-h) -Formal CTA Meetings : 2 (2000 m-h)

Support to FCAA Meetings : -

Published Documents : Revisions of Doc (AFM, MRB, etc.)

Pre TC Activities : 30 calendar days

Coord/Flight Tests : 70 FTH (500 m-h)


Cta planning embraer program erj 170 200
CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ-170-200

SCHEDULE OF MAIN EVENTS

  • Application : May 2001

  • Preliminary TCBM : 5 August 2003

  • 1st Flight : June 2003

  • Pre-flight TCBM : 10 December 2003

  • AIT issuance : 23 December 2003

  • Certification Flight Tests : January – September 2004

  • Last Certification Reports Delivery : 30 Sept 2004

  • CTA Engineering Inspection : 11 October 2004

  • Final TCBM : 25 October 2004

  • TC Issuance : 29 October 2004


Cta planning embraer program erj 170 2001
CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ 170-200

TOTAL REQUESTED HOURS

  • Total Required (CTA) : 10500

    CTA AVAILABLE HOURS

  • Average Month : 7500

  • Peak Month : 9000

  • PF1 (50% availab.) : 3800/4500

    Minimum period at 50% availability : 3 months


Cta planning embraer program erj 190 100
CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ-190-100

ACTIVITIES

  • Number of Reports : 874 (1318)

  • Report for CTA Review : 370 (58 % delegation) (7500m-h)

  • Specialists Meetings : 39 weeks (9 mo (60%); PF1 avail.)

    (26000 m-h)

  • Formal CTA Meetings : 3 (3000 m-h)

  • Support to FCAA Meetings : 2 (1500 m-h)

  • Published Documents : 1000 m-h

  • Pre TC Activities : 30 calendar days (3500 m-h; PF1

    50% avail.)

  • Ground/Flight Tests : 300 FHT (2500 m-h)


Cta planning embraer program erj 190 1001
CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ-190-100

TOTAL REQUESTED HOURS

  • TOTAL REQUIRED (CTA) : 45000

    CTA AVAILABLE HOURS

  • Average Month : 7500

  • Peak Mont : 9000

  • PF1 (50% availab.) : (3800/4500)

    Minimum period at 50% availability : 12 months


Cta planning embraer program erj 190 1002
CTA PLANNING ERJ170-200 AND ERJ190-100EMBRAER PROGRAM ERJ-190-100

SCHEDULE OF MAIN EVENTS

Application : 30 May 2001

Preliminary TCBM : 2 April 2004

1st Flight : 11 February 2004

Pre-Flight TCBM : 11 August 2004 (OCTOBER 2004)

AIT Issuance : 18 August 2004 (NOVEMBER 2004)

Certification Flight Tests : September 24 – March 05

Last Certification Report Delivery : 13 may 2005

CTA Engineering Inspection : 8 June 2005

Final TCBM : 23 June 2005

TC Issuance : 30 June 2005