An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Practicing examples

  2. Mid term • Room: C/9 • Two groups: From 14:00 to 15:00 From 15:15 to 16:15

  3. Productivity • There is firm with a labour costs of 1000, machine costs of 2000 and overhead costs of 1500 per day. Its output rate is 100 pieces per day. The market price is 20 per piece. • On a monthly basis what is the • Labour productivity • Machine productivity • Multifactor productivity

  4. Solution • LP=(100*20)/1000=2 • MP=(100*20)/2000=1 • MFP= =(100*20)/3500=0,57

  5. Calculating capacity • 2 weeks, 5 day per week;  = 0,9; number of shifts = 3; hours per shift = 8; homogenousmachines = 2; maintenancetime = 2hours per week. • Questions: DesignedCapacity, EffectiveCapacity, Resources • Solution: DC = (2*5)*3*8*60*2 = 28,800 mins EC = DC – (2*2*60*2) = 28,320 mins Resource = EC*0,9 = 25,488 mins