Load shedding in Pakistan Reasons & Remedies. February 9, 2009 By Muhammad Ziauddin. Organization. Historical Background Load duration curve Capacity, capability & availability Shortage Reasons Remedies / Suggestions. Historical Background. Pre 1994 era Sever load shedding

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Load shedding in Pakistan Reasons & Remedies' - cicada


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
load shedding in pakistan reasons remedies

Load shedding in PakistanReasons & Remedies

February 9, 2009

By

Muhammad Ziauddin

organization
Organization
  • Historical Background
  • Load duration curve
  • Capacity, capability & availability
  • Shortage
  • Reasons
  • Remedies / Suggestions
historical background
Historical Background
  • Pre 1994 era
    • Sever load shedding
  • Post 1994 era
    • Surplus power in the system
  • 2002 Power Policy
    • Lengthy procedure
      • Approval of feasibility
      • Tariff negotiation & approval
      • Security packages
  • High load growth
current situation
Current Situation
  • Supply / Demand Balance
  • Load duration curve
    • Capacity, Capability and Availability
    • Demand
    • Supply
reasons
Reasons
  • Late finalization of 2002 power policy
  • Late initiation of new projects
  • Long processing time
  • Not soliciting new power plants
  • Reliance of unsolicited proposal
  • WAPDA was not allowed to install thermal power plants
  • Private sector started taking advantages
  • Availability of machines in the international market
reasons contd
Reasons (contd)
  • No serious efforts on effeciency improvement and energy conservation
  • Time of day metering system is not up to its strength
  • Hydropower not comming up
  • Small hydro power plants are not being taken up by WAPDA
  • Closure of some IPP & WAPDA‘s power plants
  • Not payment of fuel bills to fuel suppliers
reasons contd1
Reasons (contd)
  • International investors are not comming with enthusiasm
    • International recession
    • Governace issue
  • No serious efforts to exploit alternative energy resources
  • Huge reserve of coal is not being used
issues
Issues
  • Most of the new thermal power plants are based on fuel oil
  • Cost of electricity generations
  • Fuel imports – major implecations on forx reseve
  • Volatility of crude oil prices
  • Fuel transporation and import infrastructure
    • Road / railway network
    • Port facilities
issues contd
Issues (contd)
  • Gas is not available for new power plants
  • Un efficient energy useage
  • No incentive from the government to develop alternative energy resources
  • Rental power plant is sucidal
remedies suggestions
Remedies / Suggestions
  • Development of alternative energy
  • The Regulator should be linient in tariff for wind and solar power plants
  • Manufacturing facility for wind and solar power plants be encouraged by the government
  • Coal should be used for power generation including imported Coal
  • Thermal power plants should be installed by WAPDA in parllel to IPPs
  • More emphasis should be on energy conservation and efficiency improvement
remedies suggestions contd
Remedies / Suggestions (contd)
  • Time of day tariff should be implemented in all catagories of consumers
  • A digonostic study should be conducted for oil transporatation infrastructure and port facilities
  • Captive power plant should brougt on bar
  • Industrial sector should be encouraged to install their own power plants and surplus should be purchased by WAPDA at a competitive price