chung
Uploaded by
6 SLIDES
205 VIEWS
60LIKES

Metropolitan Council

DESCRIPTION

Metropolitan Council. Environmental Services. Info Item : East Bethel Update. Presented to the Environment Committee March 22, 2011. Bryce Pickart, Assistant General Manager, Technical Services. A Clean Water Agency. Questions. Proposed Facilities. Project Timeline.

1 / 6

Download Presentation

Metropolitan Council

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Metropolitan Council Environmental Services Info Item: East Bethel Update Presented to the Environment Committee March 22, 2011 Bryce Pickart, Assistant General Manager, Technical Services A Clean Water Agency

  2. Questions

  3. Proposed Facilities

  4. Project Timeline • 2004 City begins its planning • 2006 City request to Council • 2007 City completes comp plan • 2008-2009 Planning and land acquisition • 2010 a) MPCA issues permit b) Construction cooperation and cost sharing agreement c) Water Service Agreement d) City sells bonds e) City awards construction contracts

  5. Post-2010 Election • Issue: • New mayor and two new City Council members (majority) opposed sewer project due to economy • Actions: • 1/5/11: City Council suspends contracts; fires City Administrator • 1/24/11: City Council hires Landform to evaluate risks of proceeding versus ending project • 2/16/11: Landform submits risk assessment • 2/19/11: City Council decides to proceed with sewer and water lines and to re-evaluate need for water treatment plant

  6. East Bethel Current Status • Construction Cooperation Agreement: • Easements being acquired by City • Construction to start on City portion (within street right-of-way) • Wastewater Treatment and Reuse • Final design underway • Construction bids in fall 2011 • Completion in 2013