LHC Collaboration Meeting @ FNAL February 24, 2004 T. Page - Fermilab. Interconnect Status. Piping and bellows Beam tube drift tubes Pipe supports TAS absorber Shields. MLI Vacuum shells Q1 IP end Q3-DFBX Misc. Piping and bellows.

chibale
Download Presentation

LHC Collaboration Meeting @ FNAL February 24, 2004 T. Page - Fermilab

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Collaboration Meeting @ FNALFebruary 24, 2004T. Page - Fermilab

  2. Interconnect Status • Piping and bellows • Beam tube drift tubes • Pipe supports • TAS absorber • Shields • MLI • Vacuum shells • Q1 IP end • Q3-DFBX • Misc. T. Page

  3. Piping and bellows • Q1-Q2 interconnect: All parts in stock; parts need to be sent to weld shop for final assembly. Expected completion date: May 2004. • Q2-Q3 interconnect: Bellows and flanges in stock, pipes are being cut at the machine shop. Once complete, parts will be sent to weld shop for final assembly. Expected completion date: June 2004. T. Page

  4. Drift tubes • 316LN material is on order, due at the end of February. • Material will be sent to vendor after acceptance at FNAL. • Vendor will fabricate flanges and cooling jacket. • Final assemblies to be welded at FNAL weld shop. • Beam tube sections to be cut and swaged at FNAL; still need approximately 13 m of uninsulated beam tube. T. Page

  5. Pipe supports • Pipe supports in stock. • Modifications needed for: • TAS clearance • Holes for beam tube support bracket • Parts will be revised when the TAS design is complete. T. Page

  6. TAS absorber • Conceptual design complete. • Designer (Simmie) will begin work on the TAS design details in March 2004. • Design should take approximately 2 months to complete. • Parts arrive at FNAL by September / October 2004. T. Page

  7. Shields • Shields have been revised but haven’t been ordered. • Orders are being worked on now and should go out by mid March 2004. • Parts expected July 2004. T. Page

  8. MLI • Q1-Q2 and Q2-Q3 interconnect blankets have been ordered. • Blankets are due at the end of February 2004. T. Page

  9. Vacuum shells • Shells have been revised but haven’t been ordered. • Orders are being worked on now and should go out by mid March 2004. • Parts expected July 2004. T. Page

  10. Q1 IP end • Shields are on order. 1st assembly has been received. The remaining are expected in the next two weeks. • Modifications are needed on the shield end plate. This will be done at FNAL. This is to match the interface specification for the Q1 CWT. • Vacuum vessel end domes are in QC. • MLI is being released this week. Will be ordered with the Q3-DFBX MLI. T. Page

  11. Q1 IP end (cont.) • Thermometers, connectors and copper strap details need to be completed. • Helium guard conceptual design has been complete. Designer (Simmie) will start working on the details after the TAS design is complete. • Design completion: September 2004. • Parts arrive at FNAL: January 2005. T. Page

  12. Q1 IP end (cont.) T. Page

  13. Q3-DFBX • Shield design is almost complete, connection to the DFBX needs to be finalized. • MLI design complete, can be released by the end of March. T. Page

  14. Miscellaneous • Q1-Q2 heater and thermometers. • Concept discussed, design work has not started. • Interconnect assembly travelers. T. Page

  15. Summary • Major Items to be completed • TAS absorber • Helium guard • Q1 IP end heaters and thermometers • Q1-Q2 heater and thermometers • Interconnect assembly travelers and associated drawings. T. Page

  16. End T. Page