1 / 10

Surface Development ILC Community Task Force September 25, 2007 CFS Global Design Effort V. Kuchler, T. Lackowski G. Van

Surface Development ILC Community Task Force September 25, 2007 CFS Global Design Effort V. Kuchler, T. Lackowski G. Van Zandbergen, R. Walton. So What is the Current Status The CFS Group in General, is in a Very Challenging Situation

chandra
Download Presentation

Surface Development ILC Community Task Force September 25, 2007 CFS Global Design Effort V. Kuchler, T. Lackowski G. Van

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Surface DevelopmentILC Community Task ForceSeptember 25, 2007CFS Global Design EffortV. Kuchler, T. LackowskiG. Van Zandbergen, R. Walton

  2. So What is the Current Status • The CFS Group in General, is in a Very Challenging Situation • The International Linear Collider is not a Federally Recognized or Department of Energy Funded Project • The State of Illinois is not Officially Engaged in the Effort • Funding Levels are Uncertain at this Time, and A Continuing Resolution for FY 08 is a Virtual Certainty • So There will be a Series of Iterations • Investigation, Design and Identification of Further Work Needed • Request for and Approval to Proceed • Repeat as Needed • There are Likely to be a Number of These Cycles or Iterations Before an Illinois/Fermilab Site (or any Other Site) is Officially Declared the United States ILC Candidate Site

  3. What’s Next • In Spite of the Challenges, Work Must Proceed • Refinement of Criteria and Design • Cost Reduction and Value Engineering • Regional Interest Issues • Environmental • Subsurface and Geotechnical Investigation and Characterization • We Also need to Develop a Plan to Complete the Effort • Gain Enough Information to Identify an Alignment • Identify the Surface Presence Needed • Begin to Understand the Acquisition Strategies • Without • Overselling the Project • Unduly Antagonizing Local Communities and Residents • Promising Things we Have No Authority to Promise • Overselling the Project • Getting Too Far Ahead of Actual Project Approval, Much Less Any National or International Site Selection Process

  4. The Plan • First the Environmental Process Must Begin • This Process is Likely to Constitute the Critical Path for US Site Selection • This Process is Outlined in the National Environmental Protection Act • We Can Begin by Identifying Land Use and Ownership Beyond the Fermilab site Boundaries • We Can Also Begin to Characterize General Aspects of the Areas Around Fermilab • We Can Identify Possible Brownfield Sites for Advantages in the LEED Process • A Good Portion of This Can be Accomplished Using Existing Public Information Available Through Information Sharing Agreements with Adjacent Counties • Once the Initial Investigation is Completed, a Potential Alignment can be Identified which will Give Specific Shaft Locations

  5. The Plan cont. • Subsurface Investigation is a Little More Complicated • We Can Begin with Investigation on the Fermilab Site • Soil Borings Can be Completed • Geotechnical Data • Vibration Transfer and Stability Assessments Can be Made • Ground Water Information Can be Verified • While a Good Start, Eventually This Same Investigation Process Will Need to be Conducted along the Entire Alignment Chosen for the ILC Including the Proposed Upgrade to 1 Tev (~4 More Shafts and Extending 10 km in Each Direction)

  6. The Posters • The Posters Presented Reflect Conceptual Ideas Based on the Criteria Developed to Date • No Specific Programming has been Completed for any Surface Buildings • Cryogenic Compressor Buildings are Based on the LHC/CERN Model • Electrical and Cooling Equipment are Representative and will Ultimately be Directly Proportional to the Electrical Needs of the ILC Project • Shaft/Surface Configuration will Require Compromise Between the Project needs and LandAvailabilitly

  7. Topic for Tonight’s Discussion • Given This Background Information, • What is the Best Way to Proceed

More Related