1 / 85

AMS Superconducting Magnet progress over the last 2½ months January 2007

AMS Superconducting Magnet progress over the last 2½ months January 2007 Steve Harrison Scientific Magnetics. Magnet STA Magnet manufacture Valve qualification CGSE dewar update Helium vessel.

chadf
Download Presentation

AMS Superconducting Magnet progress over the last 2½ months January 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AMS Superconducting Magnet • progress over the last 2½ months • January 2007 • Steve HarrisonScientific Magnetics

  2. Magnet STA • Magnet manufacture • Valve qualification • CGSE dewar update • Helium vessel

  3. In October 2006 the CMR had been mounted in the STA vacuum vessel, and the 16 straps had been tensioned and adjusted.

  4. The vacuum vessel weld fixture had been installed at Culham.

  5. A wiring loom has been installed inside the vacuum vessel

  6. … to take signals from the accelerometers mounted on the cold mass replica …

  7. … to instrumentation feedthroughs.

  8. Accelerometers in position.

  9. The bore tube has been inserted …

  10. … and the conical flanges fitted.

  11. The next task was to fit the temporary seals, but the sealing surface had been badly scratched.

  12. With care, it was possible to make seals good enough for leak testing the small number of components which were not already tested.

  13. Vacuum covers have been fitted over the 16 straps …

  14. … and over the unused ports.

  15. Then the entire assembly was lifted out of the frame ...

  16. Port cover Strap cover Turbomolecular pump Vacuum valve Mass spectrometer … for leak testing.

  17. The assembly was leaktight, so the temporary seals were taken out from the bore.

  18. The welding fixture now had to be dismantled to mount the STA.

  19. Next the STA was carefully lowered into the ring …

  20. … and transferred to the ring lifting beam for rotation and installation in the weld fixture.

  21. The vacuum vessel installed ready for welding.

  22. After welding, and a prolonged weld examination process, the alodining was completed …

  23. … and the STA was installed in the shipping fixture. It finally left Culham on 2 January 2007.

  24. In October the magnet was mechanically complete, but had no cryogenic plumbing, and no electrical joints between the dipoles and racetrack coils.

  25. Dipole heat shunt Racetrack heat shunt Cool down loop Conductor stabiliser Superfluid cooling loop Steel Cool down loop Copper

  26. Inter-coil conductors have to be mechanically, thermally, and electrically stabilised over complicated geometries using ultra-high purity aluminium.

  27. Conductor stabiliser Quench heater terminal The stabilisers have to be hand-crafted to fit the magnet geometry precisely. They are made from precision-bent, copper-plated aluminium.

  28. Coil ends Unsupported length (max 30 mm) Copper plating allows the conductor to be soldered to the stabiliser.

  29. The geometry of the flight cooling loops is not suitable for use in the test cryostat, so simplified loops are required.

  30. Trial fit-up of one of the cooling loops for the magnet test.

  31. Both loops mechanically attached to the magnet.

  32. “Corner” section with Cu/Fe/Cu transition.

  33. Pure aluminium shunts for transferring heat from the coils to the cooling loops. All these components have to be tinned with solder.

  34. Pre-tinning the cooling loop for connection to the heat shunts.

  35. Re-fitting the cooling loop ready to solder up the heat shunts.

  36. In October 2006, a test facility for acceptance testing (of up to 5 valves at a time) had been designed and manufacturing was just starting.

More Related