An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A&D High Tech Project Team 2: Yusuf Akkoca Tom Bloom Karen DeltonShweta Hire Eric Johnson David Mahzonni

  2. Project Priority • Main priority is completion time • May until Mid November to complete; about 6 months

  3. Projected Completion Time • 322 Days to Complete • With Deployment at 11/14/2003 and 100% resource usage.

  4. Costs – Labor & Capital • Total costs $3,846,782 • Hardware costs $98,500 • Labor costs $3,748,282

  5. Critical Path

  6. Potential of on Time Completion • High potential for Failure

  7. Risks & Mitigation • Hardware Compatibility Issues • Software Compatibility Issues – ERP • Availability of Resources • Scope Creep & Last Minute Changes • Enforce a strict change control process

  8. Scope Changes / Change Control • Develop a Strict Change control Process. • Only approve changes deemed critical, other will be added to a “Phase 2”.