Preparing for a Transition

Preparing for a Transition. Sarah Moyns, Assistant Director for Transitions and Building Management Jerry Mann, Senior Associate Director University of North Carolina at Charlotte . A Step-by-Step Guide for Staff and Students. Cone University Center.

cardea
Download Presentation

Preparing for a Transition

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preparing for a Transition Sarah Moyns, Assistant Director for Transitions and Building Management Jerry Mann, Senior Associate Director University of North Carolina at Charlotte A Step-by-Step Guide for Staff and Students

  2. Cone University Center • Built in 1961, first addition in 1966, second in 1976 • Less than 100,000 square feet

  3. Student Union History • The University of North Carolina set out to create a unique building on campus where students and the campus community can gather on a regular basis. • The goal is to have a bustling building with events, meetings, meals, education and entertainment August 22, 2005

  4. Student Union History • 1999 - Budget earmarked to renovate existing University Center (Cone). Sasaki Associates engaged to assist with design • May 2001 – Sasaki recommends building new structure • 2001 to 2003 – Program review • August 2003 – Designer selection awarded to Sasaki and the FWA Group • November 2003 – Sector study completed and location chosen • April 2004 – Program development completed • August 2004 – Schematic design completed • May 2005 – Design development completed • July 2006 – Construction documents completed • April 18, 2007 - Pavement Breaking

  5. Transition: Where to Begin • Determine the goals and challenges you expect to face • Set a timeline • Select who is involved on your teams • Leaders vs. participants • Establish what methods and resources you will use • Create initiatives to keep the momentum going • Mark the milestones • Plan a completion celebration

  6. Goals • Reasonable • Measurable • Attainable

  7. Challenges • Introduce concept of a “Student Union” to the campus • Engage student population to play a more direct role in governance of the building • Plan for migration from career centered employment model to student centered

  8. Transition Timeline • January 2008 – Core Team Assembled • February – Transition Team Proposal presented to staff • March – Topping Out Ceremony • April – Transition Team Kick Off, begin Student Union Advisory Board work, Students vote on Union Logo • Summer ‘08 – Market student union to incoming students • Aug. – Oct. – Retail Survey • October – Grand Opening initial Proposal Submitted • December – Office cleaning day, auxiliary/food services brought onto Core Team

  9. Transition Timeline • January 2009 – Student Union Advisory Board begins work • February – Grand Opening Team begins planning specifics, Homecoming Parade, Grand Opening t-shirt contest announced • March – Union marketing campaign announced, student employment information sessions/interviews, office cleaning day • April – Student employees hired, staff begins to be hired • May – packing begins, final preps for the move, move meeting and timeline in place • June – building complete

  10. Transition Timeline • April – Student employees hired, staff begins to be hired • May – packing begins, final preps for the move, move meeting and timeline in place • June – building complete • Late June/Early July – Move in • August 24, 2009 – GRAND OPENING!!!!!

  11. Milestones • Transition Team Kick Off • Topping Out Ceremony • Cleaning Day • Advisory Board Established • Staffing Finalized • Grand Opening Date Set • Retail Tenants Determined

  12. Teams • Team Leadership • Student Union Transition Core Team • Comprised of Transition Team Leaders • Student Union Advisory Board Committee • The Team Plan • Find people who are interested in the process • Have team leaders recommend outside staff and students to participate on teams (utilize their expertise) • Begin the process at least 12 months prior to final move • Hold a kick off event/meeting where all team members attend, each member receives a team booklet • Be sure Team Leaders contact all team members right away

  13. Purpose of the Teams • Brings University constituents into the project • Generates multiple angles and viewpoints • Encourages employees to take ownership of the project • Increases familiarity of the project and its processes • Successfully moves into, opens, and manages the building

  14. Teams • Mission/Values • Programming • Grand Opening • Policy • Moving • Technology • Budget • Building Operations • Marketing

  15. Team Functionality • Specific to your goals and transition or change • Campus needs will be different • Eastern Michigan University (EMU) vs UNCC • Determine initial direction when developing teams • Work together

  16. Methods/Resources • Focus Groups • Student Body Elections • Project Management Site • Monthly Newsletter • Blog • Facebook • Union Website • Homecoming • Campus Surveys • Student Union Advisory Board • Orientation • Leadership Conferences • Student Government • Career Fairs

  17. Keeping the Momentum • Newsletters • Involve staff in decisions • Be excited • Take teams on tours • Continually inform the campus about the project • Celebrate the milestones!

  18. Team Completion Celebration • Soon after the Transition/move/change • Luncheon • Welcome • Orientation

  19. Lessons Learned • It is personality management as much as project management • Know your staff and who you can go to • Keep dialog open with everyone • Don’t forget the little everyday items

  20. Lessons Learned • There will be changes • Know when to step back and when to keep going for the sake of the project • JUST DO IT!

  21. Team Member Feedback • I liked being a part of the process –EMU • I really liked being involved I thought that as a student we really wouldn’t have much say in the Union…I am loving the fact that my opinions and suggestions matter. –UNCC • Sometimes decisions have to be made without everyone’s input – EMU • Some groups were focused others were not. Some did not have clear direction up front – EMU/UNCC • Groups working on similar tasks can combine at times – EMU • It is difficult to explain that some things we won’t know until we get in the building – EMU/UNCC

  22. Outcomes • EMU • Building was completed and opened on time • Staff functioning well and service has improved • Campus life reports full capacity at every Friday night movie • Art gallery attendance up 3,000 in first 6 weeks • 95 events held in auditorium in first 60 days • Reservations up 15% • UNCC • TBD

  23. Questions?

  24. Contact Information Sarah Moyns smoyns@uncc.edu Jerry Mann jmann30@uncc.edu