Transmission Lines & Pipelines: Routing-Condemnation-Easements Wednesday , May 28, 2014 Texas Association of Real

Transmission Lines & Pipelines: Routing-Condemnation-Easements Wednesday , May 28, 2014 Texas Association of Realtors. Big Picture. Phase 1: Company study Phase 2: Routing Phase 3: Land acquisition (condemnation) Phase 4: Construction. 2. Phase 2: Routing.

calvin
Download Presentation

Transmission Lines & Pipelines: Routing-Condemnation-Easements Wednesday , May 28, 2014 Texas Association of Real

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission Lines & Pipelines: Routing-Condemnation-Easements Wednesday, May 28, 2014 Texas Association of Realtors
  2. Big Picture Phase 1: Company study Phase 2: Routing Phase 3: Land acquisition (condemnation) Phase 4: Construction 2
  3. Phase 2: Routing
  4. Routing Process Transmission/Pipelines Regulated Formal Process Powerline Company Files CCN Heard by SOAH/PUC Non-transparent Process O&G Company/Railroad Private/Threat of Condemnation
  5. Powerlines in SOAH Intervene or Comment If Intervening, Provide Written Direct Testimony Critical Difference: Protestors are Not Parties and Comments Are Not Evidence
  6. Powerline Critical Fact! “RECOMMENDED ROUTE” DOES NOT MEAN MUCH
  7. Roles and Strategies of the Team Experts: Routing Landowners: Alliances Lawyers: Legal
  8. How Experts Can Help You Analyze Routes and Segments Recommend a Route Support or Rebut Routes Chosen By Routing Agency Provide Testimony at Hearing
  9. Critical Conclusion! “INTERVENORS” INFLUENCE ROUTE SELECTION
  10. Big Picture Phase 1: Company study Phase 2: Routing Phase 3: Land acquisition (condemnation) Phase 4: Construction 12
  11. Phase 1: The Call, Visit or Letters from Landman Phase 2: Negotiating Your Terms and Compensation Phase 3: Special Commissioners’ Hearing Phase 4: District Court/County Court at Law Appeal Steps in Eminent Domain/Condemnation
  12. Phase 1: The Letters “Bona fide offer” required Condemnor’s “initial offer” Generally, includes a 30-day deadline Law requires a written appraisal and 14-day “final offer” before any hearing Critical time to have consulted with an attorney
  13. Company landman makes the written offer First offer typically “low” Offer and terms are negotiable Landman and/or company lawyers discuss price, location, and terms Phase 2: Negotiating Your Terms & Compensation
  14. If no agreement, company files condemnation lawsuit Purpose of Commissioners’ Court is to assess damages and “award” a dollar amount to landowner Braun & Gresham continues to negotiate Company can begin building after award Phase 3: Commissioners’ Court
  15. Objection to award Formal courtroom jury trial Decides price Expensive Should be used as last resort Phase 4: Appeal
  16. Price of land taken Other damages Details of routes Location of structures Temporary agreements e.g., Roads/Easements Permanent easements General Negotiations
  17. Restore/protect land Access points Roads Improvements Fences and gates Liability protections Landowner’s future use Limits on others’ use Easement Negotiations
  18. Non-exclusivity Limitation of number of lines Limitation of diameter of pipe Limitation of easement width Limitation of surface facilities Depth of pipe Surface restoration measures Indemnity protection Termination clause Land/ranch specifics Miscellaneous provisions No warranty, dispute resolution, etc. Pipeline Specific Negotiations
  19. QUESTIONS? Do transmission lines/pipelines negatively affect property values?
  20. QUESTIONS? Do transmission lines/pipelines negatively affect property values? Should the seller tell the buyer an electric utility company has notified the seller the property may be impacted by the routing of a new transmission line?
  21. QUESTIONS? Do transmission lines/pipelines negatively affect property values? Should the seller tell the buyer an electric utility company has notified the seller the property may be impacted by the routing of a new transmission line? Should the seller tell the buyer a pipeline company has notified seller about the possible routing of a new pipeline across the seller’s property?
  22. QUESTIONS? Do transmission lines/pipelines negatively affect property values? Should the seller tell the buyer an electric utility company has notified the seller the property may be impacted by the routing of a new transmission line? Should the seller tell the buyer a pipeline company has notified seller about the possible routing of a new pipeline across the seller’s property? Should the seller disclose whether the property is under the threat of potential condemnation?
  23. Bad Old Easements Blanket easements by past failure to negotiate Undefined ingress and egress locations Undefined width of permanent easement Undefined number and sizes of pipelines Undefined number of transmission line circuits, etc Undefined use of additional temporary work space Payment for new lines at 1930’s prices -- or worse!! Example $0.25/rod for each additional line (1 rod = 16.5 feet)
  24. Harrington v. Magellan Pipeline Co., L.P. (2011 Waco Court of Appeals) An easement agreement in 1919 that grants the pipeline company the right to lay multiple pipelines “over and through [Grantor’s] lands” is ambiguous as to whether it means multiple pipelines in the same ditch as the first pipeline, or multiple pipelines at different locations and in different directions on Grantor’s lands.
  25. Natural Resources Code Sec. 111.0194 Applies to easements prior to January 1, 1994 Applies to pipelines laid under threat of Condemnation or Eminent Domain If width of easement is undefined in old easement then “extends only a width of 50 feet as to each pipeline laid” Company may rebut with evidence it needs more Statute is unfortunately ambiguous
  26. Exceptions to Title Policy Buyer should request the documents and carefully review the language before closing Without a careful review by buyer and his/her attorney, the buyer man not realize the extent of the burden of a bad old easement` Company may decide to “maintain” an old easement and remove all trees/growth in a 50-100 foot strip of land -- or lay additional lines anywhere on the property
  27. Q & A
  28. Stay informed and connected…Join the: Stay informed on issues affecting landowners and their land. This free e-mail service comes out once every two weeks and gives subscribers exclusive access to alerts on transmission lines, announcements about important changes in the law, and upcoming educational seminars. Anyone interested in land will benefit from a subscription.
  29. Stay Informed and Connected Join our Landowner Alert System http://www.braungresham.com/contact-us/#contact Like us on Facebook www.facebook.com/BraunGresham Follow us on Twitter twitter.com/BraunGreshamLaw
  30. Patrick L. Reznik 512-894-5426 preznik@braungresham.com www.braungresham.com