An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALMA Operations ASAC Meeting Sept 16-17 2006 J. Hibbard, NRAO (NA ARC Manager), on behalf of the Operations Working Group

  2. Guidelines for ALMA Operations • ALMA is a service observing facility, for which the scientific demand will be very high. The astronomer is not normally required to be present when his/her observations are executed. • ALMA operational activities in Chile are limited to what is required to acquire, certify and archive the scientific data of the scientific teams proposing observations; this includes certain business functions and other activities requiring proximity to the array. For safety reasons, the number of ALMA staff working at the array site at 5000 meters elevation must be kept to an absolute minimum. • The main interface between the user communities and ALMA is through the Regional Centers (ARCs), including proposal handling and support for data reduction and archival research. • Maintenance, Repair and Development work on hardware and software is contracted to the Executives.

  3. Baseline plan for the relation of Operations to Construction From the ALMA Project Plan • Hardware delivered will be integrated, verified, and commissioned subsystem module-by-subsystem module. Once commissioned, each subsystem module will be placed into service in the operating array. • The initial complement of the ALMA operations team must be in place at the OSF and on the array site at the time the first array subsystem modules are commissioned.. • The details of the scientific operations plan need to be refined and implemented at the time the first few antennas arrive on site.

  4. ALMA Operations Staffing—by Employer • International Staff Who are employed by ESO, NRAO or NAOJ and seconded to ALMA operations in Chile. (35 in 2013) • Local Staff Who are employed through AUI/NRAO under Chilean labor laws in a manner decided by the ALMA Board. (191 in 2013) • Contract Services Staff Individuals performing services under service contracts with ALMA. These people are not employed directly by ALMA or the Executives. (144 in 2013) • ARC Operations Support Staff Staff at ALMA Regional Centers providing operations and community support (51 in 3 ARCs in 2013)

  5. Plan for Overlap in Time with the Construction Project • The plan for ALMA operations needs to be made consistent with the plans assumed for it in the ALMA construction plan. That is, the ramp-up with time of the ALMA operations staff needs to be planned consistent with the assumptions being made in the construction project. • This process has been started, but needs to be planned in more detail when main JAO operations staff (Head of Technical Services, Head of Science Operations, Project Scientist) are in place. • A plan for staffing of the commissioning effort needs to be melded with the construction and operations plans. • Plan presented by R. Laing was developed to be consistent with current operations plan. • There will be a time when all three staff—construction, commissioning and interim operations—will be on site at the same time. Their collective space requirements will exceed that needed for full ALMA operations.

  6. Operations Group: I • Origins • Created by JAO, reports to JAO • May 2003: Guilloteau, Sramek • August 2003: Emerson

  7. Other ALMA contributors Brian Glendenning Debra Shephard Eduardo Hardy Bill Porter External reviewers (Draft F) Willem Baan (Westerbork) Paul Ho (SMA) Roberto Neri (IRAM) Peggy Perley (NRAO) David Woody (OVRO) Melvyn Wright (BIMA) Operations Group: II

  8. Operations Group: III • First meeting December 2005 • Concentrate on Operations staffing plan, budget, outstanding issues identified by Board in Ops Plan ver. A. • Participants: • JAO (Tarenghi, Beasley, Murowinski) • Project Managers (Russell, Rykaczewski, Hasegawa) • Project Scientists (Wootten, Wilson, Kawabe) • ARC Managers (Hibbard, Adreani, Kawabe) • Legacy (Emerson)

  9. ALMA Operations Plan Update • Modifications: • Includes entry of ALMA-J (ACA, bands 4 & 8 and possibly 10) • Technical positions staffed with local hires wherever possible • Recruitment of operations staff tied to construction milestones

  10. Operations Staffing Ramp-up now tied to Construction Milestones

  11. Identified positions added for trilateral project (orange) Identified positions filled by transfer from Construction (blue; AIV staff in this case) All positions tied to construction milestones (3 months before Early Science in this case)

  12. ALMA Operations Plan Update • Modifications: • Includes entry of ALMA-J (ACA, bands 4 & 8 and possibly 10) • Technical positions staffed with local hires wherever possible • Recruitment of operations staff tied to construction milestones • Adopt ASAC recommendation that CSV be extended, moving Early Science Decision Point back ~ 9months. • Early Science starts Sept 2010

  13. Current Staffing plan assumes ASAC recommendation to extend CSV

  14. ALMA Operations Plan Update • Modifications: • Includes entry of ALMA-J (ACA, bands 4 & 8 and possibly 10) • Technical positions staffed with local hires wherever possible • Recruitment of operations staff tied to construction milestones • Adopt ASAC recommendation that CSV be extended, moving Early Science Decision Point back ~ 9months. • Early Science starts Sept 2010 • Planning baseline is for a single international Proposal Review Committee (none in Silva Plan) • Meets once per year for first 3 cycles, then 2/year

  15. ALMA Operations Plan Update • Modifications: • Includes entry of ALMA-J (ACA, bands 4 & 8 and possibly 10) • Technical positions staffed with local hires wherever possible • Recruitment of operations staff tied to construction milestones • Adopt ASAC recommendation that CSV be extended, moving Early Science Decision Point back ~ 9months. • Early Science starts Sept 2010 • Planning baseline is for a single international Proposal Review Committee (none in Silva Plan) • Meets once per year for first 3 cycles, then 2/year • “Contingency Line” replaced with smaller budget for Directors Emergency Fund.

  16. ALMA Operations Plan Update • Modifications: • Includes entry of ALMA-J (ACA, bands 4 & 8 and possibly 10) • Technical positions staffed with local hires wherever possible • Recruitment of operations staff tied to construction milestones • Adopt ASAC recommendation that CSV be extended, moving Early Science Decision Point back ~ 9months. • Early Science starts Sept 2010 • Planning baseline is for a single international Proposal Review Committee (none in Silva Plan) • Meets once per year for first 3 cycles, then 2/year • “Contingency Line” replaced with smaller budget for Directors Emergency Fund. • Development Plan…

  17. ALMA Development Plan • Long-range development plan • 2008 solicit community input • Future ALMA science drivers (“2020 vision”) • What new capabilities does ALMA need to address these science drivers? • ALMA-wide plan 2009 • executives and JAO work together to estimate initial costs • Board, with input from ASAC, reviews the plan, provides policy guidance to generate scientific vision with both long-term and short-term projects • Funding agencies sign-up to approved plan via ALMA Board

  18. Board Decisions on Operations • Automatic generation of images: • At the start of early science, there may not be enough data to make a full pipeline analysis possible. Also, the ALMA staff needs to check the correctness of the pipeline results. After 1 to 2 years of early science operation the pipeline should be a reliably working system. • Director’s Discretionary Time • No Director’s Discretionary Time is foreseen. All of the ALMA time belongs to the executives. • Data proprietary period • This will be 1 year starting with the end of the program. Special cases could be considered in exceptional circumstances.

  19. Joint ALMA Observatory

  20. ALMA Observatory Top-Level

  21. Division of Science Operations (DSO)

  22. ALMA Operations: Division of Science Operations (DSO): Full Operations Head of Science Operations Both/ISM/2006.4 Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 AG Manager2 - OSF/LSM/2010.2 Sci. Prog. Manager OSF/ISM/2008.1 Web Developer - NA/RSM/2009.4 Data Manager 1 -SCO/ISM/2009.1 Data Manager 2 -SCO/ISM/2010.3 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 OSF Archive Appears in 2006.4, run by AIV Better archive in 2008.4, run by Ops ARCs start mirroring 2011.4 SCO Archive/Pipeline Starts out in 2009 at OSF SCO Archive mirrors OSF 2011 Pipeline starts 2011.4 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Array Operator6 - OSF/LSM/2010.2 Array Operator7 - OSF/LSM/2010.2 Array Operator8 - OSF/LSM/2010.2 Archive Operator1 - OSF/LSM/2009.1 Archive Operator2 - OSF/LSM/2009.1 Archive Operator3 - OSF/LSM/2009.1 Archive Operator1 - Both/LSM/2009.2 Archive Operator2 - Both/LSM/2009.2 Archive Operator3 - SCO/LSM/2011.4 PDM Astr5 - OSF/ISM/2009.1 PDM Astr6 - OSF/ISM/2009.1 PDM Astr7 - OSF/ISM/2009.1 PDM Astr8 - OSF/ISM/2009.1 Array Operator9 - OSF/LSM/2010.2 Array Operator10 - OSF/LSM/2010.2 Array Operator11 - OSF/LSM/2010.2 Array Operator12 - OSF/LSM/2010.2 Content Manager1 - OSF/LSM/2009.1 Content Manager2 - OSF/LSM/2010.1 Content Manager3 - OSF/LSM/2010.1 DB Content Mangr1 - SCO/LSM/2011.4 DB Content Mangr2 - SCO/LSM/2011.4 DB Content Mangr3 - SCO/LSM/2012.2 PDM Astr9 - OSF/ISM/2010.2 PDM Astr10 - OSF/ISM/2010.2 PDM Astr11 - OSF/ISM/2010.2 PDM Astr12 - OSF/ISM/2010.2 PDM Astr13 - OSF/ISM/2010.2 PDM Fellow1 - OSF/ISM/2011.1 PDM Fellow2 - OSF/ISM/2011.1 PDM Fellow3 - OSF/ISM/2011.1 PDM Fellow4 - OSF/ISM/2012.1 PDM Fellow5 - OSF/ISM/2012.1 PDM Fellow6 - OSF/ISM/2012.1 PDM Fellow7 - OSF/ISM/2013.1 PDM Fellow8 - OSF/ISM/2013.1 Blue=Transfer from construction Red=added for ACA

  23. ALMA Operations: Division of Science Operations (DSO): 2007.4 Head of Science Operations Both/ISM/2006.4 2007 Milestones: Apr-07 Ant 1 AIV Receive at OSF Antenna Operations Group (AOG) Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 Blue=Transfer from construction Red=added for ACA

  24. ALMA Operations: Division of Science Operations (DSO): 2008.4 Head of Science Operations Both/ISM/2006.4 2008 Milestones: Apr-07 Ant 1 AIV Receive at OSF Jun-08 Ant 1&2 OSF Interferometer Start Aug-08 Ant 1 AOS Checkout Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 Sci. Prog. Manager OSF/ISM/2008.1 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Blue=Transfer from construction Red=added for ACA

  25. ALMA Operations: Division of Science Operations (DSO): 2009.4 Head of Science Operations Both/ISM/2006.4 2009 Milestones: Apr-07 Ant 1 AIV Receive at OSF Jun-08 Ant 1&2 OSF Interferometer Start Aug-08 Ant 1 AOS Checkout Jan-09 3-element Interferometr AOS Jan-09 Start of CSV Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 Sci. Prog. Manager OSF/ISM/2008.1 Web Developer - NA/RSM/2009.4 Data Manager 1 - SCO/ISM/2009.1 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 OSF Archive Appears in 2006.4, run by AIV Better archive in 2008.4, run by Ops ARCs start mirroring 2011.4 SCO Archive/Pipeline Starts out in 2009 at OSF SCO Archive mirrors OSF 2011 Pipeline starts 2011.4 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Archive Operator1 - OSF/LSM/2009.1 Archive Operator2 - OSF/LSM/2009.1 Archive Operator3 - OSF/LSM/2009.1 Archive Operator1 - Both/LSM/2009.2 Archive Operator2 - Both/LSM/2009.2 PDM Astr5 - OSF/ISM/2009.1 PDM Astr6 - OSF/ISM/2009.1 PDM Astr7 - OSF/ISM/2009.1 PDM Astr8 - OSF/ISM/2009.1 Content Manager1 - OSF/LSM/2009.1 Blue=Transfer from construction Red=added for ACA

  26. ALMA Operations: Division of Science Operations (DSO): 2010.4 Head of Science Operations Both/ISM/2006.4 2010 Milestones: Apr-07 Ant 1 AIV Receive at OSF Jun-08 Ant 1&2 OSF Interferometer Start Aug-08 Ant 1 AOS Checkout Jan-09 3-element Interferometr AOS Jan-09 Start of CSV Jan-10 Early Science Decision Point/CfP Apr-10 End SV 15 element Array Sep-10 Start Early Science Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 AG Manager2 - OSF/LSM/2010.2 Sci. Prog. Manager OSF/ISM/2008.1 Web Developer - NA/RSM/2009.4 Data Manager 1 -SCO/ISM/2009.1 Data Manager 2 - SCO/ISM/2010.3 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 OSF Archive Appears in 2006.4, run by AIV Better archive in 2008.4, run by Ops ARCs start mirroring 2011.4 SCO Archive/Pipeline Starts out in 2009 at OSF SCO Archive mirrors OSF 2011 Pipeline starts 2011.4 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Array Operator6 - OSF/LSM/2010.2 Array Operator7 - OSF/LSM/2010.2 Array Operator8 - OSF/LSM/2010.2 Archive Operator1 - OSF/LSM/2009.1 Archive Operator2 - OSF/LSM/2009.1 Archive Operator3 - OSF/LSM/2009.1 Archive Operator1 - Both/LSM/2009.2 Archive Operator2 - Both/LSM/2009.2 PDM Astr5 - OSF/ISM/2009.1 PDM Astr6 - OSF/ISM/2009.1 PDM Astr7 - OSF/ISM/2009.1 PDM Astr8 - OSF/ISM/2009.1 Array Operator9 - OSF/LSM/2010.2 Array Operator10 - OSF/LSM/2010.2 Array Operator11 - OSF/LSM/2010.2 Array Operator12 - OSF/LSM/2010.2 Content Manager1 - OSF/LSM/2009.1 Content Manager2 - OSF/LSM/2010.1 Content Manager3 - OSF/LSM/2010.1 PDM Astr9 - OSF/ISM/2010.2 PDM Astr10 - OSF/ISM/2010.2 PDM Astr11 - OSF/ISM/2010.2 PDM Astr12 - OSF/ISM/2010.2 PDM Astr13 - OSF/ISM/2010.2 Blue=Transfer from construction Red=added for ACA

  27. ALMA Operations: Division of Science Operations (DSO): 2011.4 Head of Science Operations Both/ISM/2006.4 2011 Milestones: Apr-07 Ant 1 AIV Receive at OSF Jun-08 Ant 1&2 OSF Interferometer Start Aug-08 Ant 1 AOS Checkout Jan-09 3-element Interferometr AOS Jan-09 Start of CSV Jan-10 Early Science Decision Point/CfP Apr-10 End SV 15 element Array Sep-10 Start Early Science Oct-11 Pipeline commissioned at SCO Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 AG Manager2 - OSF/LSM/2010.2 Sci. Prog. Manager OSF/ISM/2008.1 Web Developer - NA/RSM/2009.4 Data Manager 1 -SCO/ISM/2009.1 Data Manager 2 -SCO/ISM/2010.3 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 OSF Archive Appears in 2006.4, run by AIV Better archive in 2008.4, run by Ops ARCs start mirroring 2011.4 SCO Archive/Pipeline Starts out in 2009 at OSF SCO Archive mirrors OSF 2011 Pipeline starts 2011.4 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Array Operator6 - OSF/LSM/2010.2 Array Operator7 - OSF/LSM/2010.2 Array Operator8 - OSF/LSM/2010.2 Archive Operator1 - OSF/LSM/2009.1 Archive Operator2 - OSF/LSM/2009.1 Archive Operator3 - OSF/LSM/2009.1 Archive Operator1 - Both/LSM/2009.2 Archive Operator2 - Both/LSM/2009.2 Archive Operator3 - SCO/LSM/2011.4 PDM Astr5 - OSF/ISM/2009.1 PDM Astr6 - OSF/ISM/2009.1 PDM Astr7 - OSF/ISM/2009.1 PDM Astr8 - OSF/ISM/2009.1 Array Operator9 - OSF/LSM/2010.2 Array Operator10 - OSF/LSM/2010.2 Array Operator11 - OSF/LSM/2010.2 Array Operator12 - OSF/LSM/2010.2 Content Manager1 - OSF/LSM/2009.1 Content Manager2 - OSF/LSM/2010.1 Content Manager3 - OSF/LSM/2010.1 DB Content Mangr1 - SCO/LSM/2011.4 DB Content Mangr2 - SCO/LSM/2011.4 PDM Astr9 - OSF/ISM/2010.2 PDM Astr10 - OSF/ISM/2010.2 PDM Astr11 - OSF/ISM/2010.2 PDM Astr12 - OSF/ISM/2010.2 PDM Astr13 - OSF/ISM/2010.2 PDM Fellow1 - OSF/ISM/2011.1 PDM Fellow2 - OSF/ISM/2011.1 PDM Fellow3 - OSF/ISM/2011.1 Blue=Transfer from construction Red=added for ACA

  28. ALMA Operations: Division of Science Operations (DSO): Full Operations Head of Science Operations Both/ISM/2006.4 Admin Asst1 - OSF/LSM/2008.1 Admin Asst2 - OSF/LSM/2008.1 Antenna Operations Group (AOG) Program and Data Management Group (PDG) AG Manager1 - OSF/LSM/2008.1 AG Manager2 - OSF/LSM/2010.2 Sci. Prog. Manager OSF/ISM/2008.1 Web Developer - NA/RSM/2009.4 Data Manager 1 -SCO/ISM/2009.1 Data Manager 2 -SCO/ISM/2010.3 Array Operator1 - OSF/LSM/2006.4 Array Operator2 - OSF/LSM/2006.4 System Astr1 - OSF/ISM/2008.2 System Astr2 - OSF/ISM/2008.2 System Astr3 - OSF/ISM/2008.2 System Astr4 - OSF/ISM/2008.2 OSF Archive Appears in 2006.4, run by AIV Better archive in 2008.4, run by Ops ARCs start mirroring 2011.4 SCO Archive/Pipeline Starts out in 2009 at OSF SCO Archive mirrors OSF 2011 Pipeline starts 2011.4 Array Operator3 - OSF/LSM/2008.3 Array Operator4 - OSF/LSM/2008.3 Array Operator5 - OSF/LSM/2008.3 PDM Astr1 - OSF/ISM/2008.2 PDM Astr2 - OSF/ISM/2008.2 PDM Astr3 - OSF/ISM/2008.2 PDM Astr4 - OSF/ISM/2008.2 Array Operator6 - OSF/LSM/2010.2 Array Operator7 - OSF/LSM/2010.2 Array Operator8 - OSF/LSM/2010.2 Archive Operator1 - OSF/LSM/2009.1 Archive Operator2 - OSF/LSM/2009.1 Archive Operator3 - OSF/LSM/2009.1 Archive Operator1 - Both/LSM/2009.2 Archive Operator2 - Both/LSM/2009.2 Archive Operator3 - SCO/LSM/2011.4 PDM Astr5 - OSF/ISM/2009.1 PDM Astr6 - OSF/ISM/2009.1 PDM Astr7 - OSF/ISM/2009.1 PDM Astr8 - OSF/ISM/2009.1 Array Operator9 - OSF/LSM/2010.2 Array Operator10 - OSF/LSM/2010.2 Array Operator11 - OSF/LSM/2010.2 Array Operator12 - OSF/LSM/2010.2 Content Manager1 - OSF/LSM/2009.1 Content Manager2 - OSF/LSM/2010.1 Content Manager3 - OSF/LSM/2010.1 DB Content Mangr1 - SCO/LSM/2011.4 DB Content Mangr2 - SCO/LSM/2011.4 DB Content Mangr3 - SCO/LSM/2012.2 PDM Astr9 - OSF/ISM/2010.2 PDM Astr10 - OSF/ISM/2010.2 PDM Astr11 - OSF/ISM/2010.2 PDM Astr12 - OSF/ISM/2010.2 PDM Astr13 - OSF/ISM/2010.2 PDM Fellow1 - OSF/ISM/2011.1 PDM Fellow2 - OSF/ISM/2011.1 PDM Fellow3 - OSF/ISM/2011.1 PDM Fellow4 - OSF/ISM/2012.1 PDM Fellow5 - OSF/ISM/2012.1 PDM Fellow6 - OSF/ISM/2012.1 PDM Fellow7 - OSF/ISM/2013.1 PDM Fellow8 - OSF/ISM/2013.1 Blue=Transfer from construction Red=added for ACA

  29. Divison of Technical Services (DTS)

  30. ALMA Operations: Division of Technical Services (DTS): Full Operations Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 EDMS Admin - SCO/LSM/2010.3 CMMS Admin - SCO/LSM/2010.3 SMO Eng1 - Both/LSM/2008.1 SMO Eng2 - OSF/LSM/2010.1 SMO Eng3 - OSF/LSM/2011.1 Sys.Eng1 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 Ant.Mang2 - OSF/LSM/2009.1 Ant.Mang3 - OSF/LSM/2009.1 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Lead3 - OSF/LSM/2009.1 Lead4 - OSF/LSM/2009.1 Ant.Super1 - OSF/LSM/2008.2 Ant.Super2 - OSF/LSM/2009.1 Ant.Super3 - OSF/LSM/2009.1 Ant.Super4 - OSF/LSM/2010.3 Ant.Super5 - OSF/LSM/2010.3 Ant.Super6 - OSF/LSM/2011.4 (6) Mtech 1-6 - OSF/LSM/2009.1 (3) Mtech 7-9 - OSF/LSM/2009.3 (3) Mtech 10-12 - OSF/LSM/2009.3 (3) MTech13-15 - OSF/LSM/2010.3 (3) MTech16-18 - OSF/LSM/2011.1 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 Corr.Eng3 - OSF/LSM/2009.1 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 (5) IS Tech 6-10 - OSF/CSM/2009.1 (3) IS Tech11-13 - OSF/CSM/2009.3 (3) IS Tech14-16 - OSF/CSM/2010.3 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 CntrlSpec3 - OSF/LSM/2009.1 CntrlSpec4 - OSF/LSM/2010.3 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 E.Eng4 - OSF/LSM/2009.1 E.Eng5 - OSF/LSM/2009.1 (3) E.Eng6-8 - OSF/LSM/2009.3 SW Eng8 - Both/LSM/2011.1 SW Eng9 - Both/LSM/2011.1 SW Eng10 - Both/LSM/2011.1 SW Eng11 - Both/LSM/2011.1 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 (2)TransportDr3-4 - OSF/LSM/2009.1 TransportDr5 - OSF/LSM/2010.3 TransportDr6 - OSF/LSM/2011.4 DB Admin1 - OSF/LSM/2008.4 DB Admin2 - OSF/LSM/2010.1 DB Admin3 - OSF/LSM/2010.1 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ETech7-8 - OSF/LSM/2009.1 (5) ETech9-13 - OSF/LSM/2009.3 (2) ETech14-15 - OSF/LSM/2010.3 (2) ETech16-17 - OSF/LSM/2011.1 (4) ETech18-21 - OSF/LSM/2011.3 (2) ElecTech1,2 - OSF/LSM/2007.4 ElecTech3 - OSF/LSM/2009.1 (2) ElecTech4,5 - OSF/LSM/2010.3 ElecTech6 - OSF/LSM/2011.4 IT Manager - SCO/LSM/2009.1 DB Admin4 - SCO/ISM/2009.3 (2) MechTech1,2-OSF/LSM/2007.4 MechTech3 - OSF/LSM/2009.1 (2) MechTech4,5 - OSF/LSM/2010.3 MechTech6 - OSF/LSM/2011.4 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 IT Supprt7 - OSF/CSM/2010.1 IT Supprt8 - SCO/CSM/2009.3 IT Supprt9 - SCO/CSM/2009.3 IT Spprt10 - SCO/CSM/2009.3 (2) MTech1,2 - OSF/LSM/2008.2 MTech3 - OSF/LSM/2009.1 (2) MTech4,5 - OSF/LSM/2009.3 (2) Helper1,2 - OSF/LSM/2007.4 Helper3 - OSF/LSM/2009.1 (2) Helper4,5 - OSF/LSM/2010.3 Helper6 - OSF/LSM/2011.4 (2) OpMTec1,2 - OSF/LSM/2008.2 OpMTec3 - OSF/LSM/2009.1 (2) OpMTec4,5 - OSF/LSM/2011.1 MIS Spprt1 -SCO/CSM/2009.3 MIS Spprt2 -SCO/CSM/2009.3 (2)Machinist1,2 - OSF/LSM/2007.4 Machinist3 - OSF/LSM/2009.1 (2)Machinist4,5 - OSF/LSM/2010.3 Machinist6 - OSF/LSM/2011.4 Red=added for ACA Blue=Transfer from construction

  31. 2007 milestones: Apr-07 Back End 1 AIV receive at OSF Apr-07 Ant 1 AIV Receive at OSF May-07 1st Quadrant Corr. AIV receive at OSF ALMA Operations: Division of Technical Services (DTS): 2007.4 Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 CG Manager 1 - Both/LSM/2007.3 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 CntrlSpec1 - OSF/LSM/2007.2 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 Transport Super - OSF/LSM/2006.4 IT Computing Group (2) ElecTech1,2 - OSF/LSM/2007.4 (2) MechTech1,2-OSF/LSM/2007.4 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 (2) Helper1,2 - OSF/LSM/2007.4 (2)Machinist1,2 - OSF/LSM/2007.4 Red=added for ACA Blue=Transfer from construction

  32. 2008 milestones: Apr-08 ACA Correlator at AOS Mar-08 Delivery of OSF Facilities Jun-08 1 baseline interferometry at OSF Aug-08 Ant1 AOS Checkout ALMA Operations: Division of Technical Services (DTS): 2008.4 Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 SMO Eng1 - Both/LSM/2008.1 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Ant.Super1 - OSF/LSM/2008.2 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 DB Admin1 - OSF/LSM/2008.4 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ElecTech1,2 - OSF/LSM/2007.4 (2) MechTech1,2-OSF/LSM/2007.4 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 (2) MTech1,2 - OSF/LSM/2008.2 (2) Helper1,2 - OSF/LSM/2007.4 (2) OpMTec1,2 - OSF/LSM/2008.2 (2)Machinist1,2 - OSF/LSM/2007.4 Red=added for ACA Blue=Transfer from construction

  33. 2009 milestones: Jan-09 3 ant of different types at AOS Jan-09 3-element Interferometer at AOS Jan-09 Start of CSV Sep-09 Ship Chilean Archive and Pipeline computer equip ALMA Operations: Division of Technical Services (DTS): 2009.4 Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 SMO Eng1 - Both/LSM/2008.1 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 Ant.Mang2 - OSF/LSM/2009.1 Ant.Mang3 - OSF/LSM/2009.1 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Lead3 - OSF/LSM/2009.1 Lead4 - OSF/LSM/2009.1 (6) Mtech 1-6 - OSF/LSM/2009.1 (3) Mtech 7-9 - OSF/LSM/2009.3 (3) Mtech 10-12 - OSF/LSM/2009.3 Ant.Super1 - OSF/LSM/2008.2 Ant.Super2 - OSF/LSM/2009.1 Ant.Super3 - OSF/LSM/2009.1 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 Corr.Eng3 - OSF/LSM/2009.1 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 (5) IS Tech 6-10 - OSF/CSM/2009.1 (3) IS Tech11-13 - OSF/CSM/2009.3 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 CntrlSpec3 - OSF/LSM/2009.1 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 E.Eng4 - OSF/LSM/2009.1 E.Eng5 - OSF/LSM/2009.1 (3) E.Eng6-8 - OSF/LSM/2009.3 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 (2)TransportDr3-4 - OSF/LSM/2009.1 DB Admin1 - OSF/LSM/2008.4 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ETech7-8 - OSF/LSM/2009.1 (5) ETech9-13 - OSF/LSM/2009.3 (2) ElecTech1,2 - OSF/LSM/2007.4 ElecTech3 - OSF/LSM/2009.1 IT Manager - SCO/LSM/2009.1 DB Admin4 - SCO/ISM/2009.3 (2) MechTech1,2-OSF/LSM/2007.4 MechTech3 - OSF/LSM/2009.1 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 IT Supprt8 - SCO/CSM/2009.3 IT Supprt9 - SCO/CSM/2009.3 IT Spprt10 - SCO/CSM/2009.3 (2) MTech1,2 - OSF/LSM/2008.2 MTech3 - OSF/LSM/2009.1 (2) MTech4,5 - OSF/LSM/2009.3 (2) Helper1,2 - OSF/LSM/2007.4 Helper3 - OSF/LSM/2009.1 (2) OpMTec1,2 - OSF/LSM/2008.2 OpMTec3 - OSF/LSM/2009.1 MIS Spprt1 -SCO/CSM/2009.3 MIS Spprt2 -SCO/CSM/2009.3 (2)Machinist1,2 - OSF/LSM/2007.4 Machinist3 - OSF/LSM/2009.1 Red=added for ACA Blue=Transfer from construction

  34. 2010 milestones: Jan-10 Early Science Decision Point/CfP Apr-10 Start SV Ant 16 Sep-10 Start Early Science ALMA Operations: Division of Technical Services (DTS): 2010.4 Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 EDMS Admin - SCO/LSM/2010.3 CMMS Admin - SCO/LSM/2010.3 SMO Eng1 - Both/LSM/2008.1 SMO Eng2 - OSF/LSM/2010.1 Sys.Eng1 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 Ant.Mang2 - OSF/LSM/2009.1 Ant.Mang3 - OSF/LSM/2009.1 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Lead3 - OSF/LSM/2009.1 Lead4 - OSF/LSM/2009.1 Ant.Super1 - OSF/LSM/2008.2 Ant.Super2 - OSF/LSM/2009.1 Ant.Super3 - OSF/LSM/2009.1 Ant.Super4 - OSF/LSM/2010.3 Ant.Super5 - OSF/LSM/2010.3 (6) Mtech 1-6 - OSF/LSM/2009.1 (3) Mtech 7-9 - OSF/LSM/2009.3 (3) Mtech 10-12 - OSF/LSM/2009.3 (3) MTech13-15 - OSF/LSM/2010.3 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 Corr.Eng3 - OSF/LSM/2009.1 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 (5) IS Tech 6-10 - OSF/CSM/2009.1 (3) IS Tech11-13 - OSF/CSM/2009.3 (3) IS Tech14-16 - OSF/CSM/2010.3 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 CntrlSpec3 - OSF/LSM/2009.1 CntrlSpec4 - OSF/LSM/2010.3 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 E.Eng4 - OSF/LSM/2009.1 E.Eng5 - OSF/LSM/2009.1 (3) E.Eng6-8 - OSF/LSM/2009.3 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 (2)TransportDr3-4 - OSF/LSM/2009.1 TransportDr5 - OSF/LSM/2010.3 DB Admin1 - OSF/LSM/2008.4 DB Admin2 - OSF/LSM/2010.1 DB Admin3 - OSF/LSM/2010.1 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ETech7-8 - OSF/LSM/2009.1 (5) ETech9-13 - OSF/LSM/2009.3 (2) ETech14-15 - OSF/LSM/2010.3 (2) ElecTech1,2 - OSF/LSM/2007.4 ElecTech3 - OSF/LSM/2009.1 (2) ElecTech4,5 - OSF/LSM/2010.3 IT Manager - SCO/LSM/2009.1 DB Admin4 - SCO/ISM/2009.3 (2) MechTech1,2-OSF/LSM/2007.4 MechTech3 - OSF/LSM/2009.1 (2) MechTech4,5 - OSF/LSM/2010.3 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 IT Supprt7 - OSF/CSM/2010.1 IT Supprt8 - SCO/CSM/2009.3 IT Supprt9 - SCO/CSM/2009.3 IT Spprt10 - SCO/CSM/2009.3 (2) MTech1,2 - OSF/LSM/2008.2 MTech3 - OSF/LSM/2009.1 (2) MTech4,5 - OSF/LSM/2009.3 (2) Helper1,2 - OSF/LSM/2007.4 Helper3 - OSF/LSM/2009.1 (2) Helper4,5 - OSF/LSM/2010.3 (2) OpMTec1,2 - OSF/LSM/2008.2 OpMTec3 - OSF/LSM/2009.1 MIS Spprt1 -SCO/CSM/2009.3 MIS Spprt2 -SCO/CSM/2009.3 (2)Machinist1,2 - OSF/LSM/2007.4 Machinist3 - OSF/LSM/2009.1 (2)Machinist4,5 - OSF/LSM/2010.3 Red=added for ACA Blue=Transfer from construction

  35. 2011 milestones: Aug-11 32 Ant SV Oct-11 SCO Archive/pipeline ALMA Operations: Division of Technical Services (DTS): 2011.4 Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 EDMS Admin - SCO/LSM/2010.3 CMMS Admin - SCO/LSM/2010.3 SMO Eng1 - Both/LSM/2008.1 SMO Eng2 - OSF/LSM/2010.1 SMO Eng3 - OSF/LSM/2011.1 Sys.Eng1 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 Ant.Mang2 - OSF/LSM/2009.1 Ant.Mang3 - OSF/LSM/2009.1 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Lead3 - OSF/LSM/2009.1 Lead4 - OSF/LSM/2009.1 Ant.Super1 - OSF/LSM/2008.2 Ant.Super2 - OSF/LSM/2009.1 Ant.Super3 - OSF/LSM/2009.1 Ant.Super4 - OSF/LSM/2010.3 Ant.Super5 - OSF/LSM/2010.3 Ant.Super6 - OSF/LSM/2011.4 (6) Mtech 1-6 - OSF/LSM/2009.1 (3) Mtech 7-9 - OSF/LSM/2009.3 (3) Mtech 10-12 - OSF/LSM/2009.3 (3) MTech13-15 - OSF/LSM/2010.3 (3) MTech16-18 - OSF/LSM/2011.1 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 Corr.Eng3 - OSF/LSM/2009.1 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 (5) IS Tech 6-10 - OSF/CSM/2009.1 (3) IS Tech11-13 - OSF/CSM/2009.3 (3) IS Tech14-16 - OSF/CSM/2010.3 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 CntrlSpec3 - OSF/LSM/2009.1 CntrlSpec4 - OSF/LSM/2010.3 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 E.Eng4 - OSF/LSM/2009.1 E.Eng5 - OSF/LSM/2009.1 (3) E.Eng6-8 - OSF/LSM/2009.3 SW Eng8 - Both/LSM/2011.1 SW Eng9 - Both/LSM/2011.1 SW Eng10 - Both/LSM/2011.1 SW Eng11 - Both/LSM/2011.1 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 (2)TransportDr3-4 - OSF/LSM/2009.1 TransportDr5 - OSF/LSM/2010.3 TransportDr6 - OSF/LSM/2011.4 DB Admin1 - OSF/LSM/2008.4 DB Admin2 - OSF/LSM/2010.1 DB Admin3 - OSF/LSM/2010.1 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ETech7-8 - OSF/LSM/2009.1 (5) ETech9-13 - OSF/LSM/2009.3 (2) ETech14-15 - OSF/LSM/2010.3 (2) ETech16-17 - OSF/LSM/2011.1 (4) ETech18-21 - OSF/LSM/2011.3 (2) ElecTech1,2 - OSF/LSM/2007.4 ElecTech3 - OSF/LSM/2009.1 (2) ElecTech4,5 - OSF/LSM/2010.3 ElecTech6 - OSF/LSM/2011.4 IT Manager - SCO/LSM/2009.1 DB Admin4 - SCO/ISM/2009.3 (2) MechTech1,2-OSF/LSM/2007.4 MechTech3 - OSF/LSM/2009.1 (2) MechTech4,5 - OSF/LSM/2010.3 MechTech6 - OSF/LSM/2011.4 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 IT Supprt7 - OSF/CSM/2010.1 IT Supprt8 - SCO/CSM/2009.3 IT Supprt9 - SCO/CSM/2009.3 IT Spprt10 - SCO/CSM/2009.3 (2) MTech1,2 - OSF/LSM/2008.2 MTech3 - OSF/LSM/2009.1 (2) MTech4,5 - OSF/LSM/2009.3 (2) Helper1,2 - OSF/LSM/2007.4 Helper3 - OSF/LSM/2009.1 (2) Helper4,5 - OSF/LSM/2010.3 Helper6 - OSF/LSM/2011.4 (2) OpMTec1,2 - OSF/LSM/2008.2 OpMTec3 - OSF/LSM/2009.1 (2) OpMTec4,5 - OSF/LSM/2011.1 MIS Spprt1 -SCO/CSM/2009.3 MIS Spprt2 -SCO/CSM/2009.3 (2)Machinist1,2 - OSF/LSM/2007.4 Machinist3 - OSF/LSM/2009.1 (2)Machinist4,5 - OSF/LSM/2010.3 Machinist6 - OSF/LSM/2011.4 Red=added for ACA Blue=Transfer from construction

  36. ALMA Operations: Division of Technical Services (DTS): Full Operations Admin Ass’t 1 - OSF/LSM/2007.4 Admin Ass’t 2 - OSF/LSM/2007.4 Head Tech Services OSF/ISM/2006.3 Spectrum Manager - SCO/ISM/2007.1 EDMS Admin - SCO/LSM/2010.3 CMMS Admin - SCO/LSM/2010.3 SMO Eng1 - Both/LSM/2008.1 SMO Eng2 - OSF/LSM/2010.1 SMO Eng3 - OSF/LSM/2011.1 Sys.Eng1 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Sys.Eng2 - OSF/ISM/2010.3 Antenna Group Electronics Group Maintenance Group Computing Group Ant.Mang1 - OSF/LSM/2007.2 Ant.Mang2 - OSF/LSM/2009.1 Ant.Mang3 - OSF/LSM/2009.1 EG Mangr1 - OSF/LSM/2007.2 EG Mangr2 - OSF/LSM/2007.4 MG Mangr1 - OSF/LSM/2008.1 MG Mangr2 - OSF/LSM/2008.1 CG Manager 1 - Both/LSM/2007.3 CG Manager 2 - Both/LSM/2008.4 Lead1 - OSF/LSM/2007.4 Lead2 - OSF/LSM/2007.4 Lead3 - OSF/LSM/2009.1 Lead4 - OSF/LSM/2009.1 Ant.Super1 - OSF/LSM/2008.2 Ant.Super2 - OSF/LSM/2009.1 Ant.Super3 - OSF/LSM/2009.1 Ant.Super4 - OSF/LSM/2010.3 Ant.Super5 - OSF/LSM/2010.3 Ant.Super6 - OSF/LSM/2011.4 (6) Mtech 1-6 - OSF/LSM/2009.1 (3) Mtech 7-9 - OSF/LSM/2009.3 (3) Mtech 10-12 - OSF/LSM/2009.3 (3) MTech13-15 - OSF/LSM/2010.3 (3) MTech16-18 - OSF/LSM/2011.1 SW Eng1 - Both/LSM/2006.4 SW Eng2 - Both/LSM/2006.4 SW Eng3 - Both/LSM/2006.4 SW Eng4 - Both/LSM/2007.2 Corr.Eng1 - OSF/LSM/2007.2 Corr.Eng2 - OSF/LSM/2007.2 Corr.Eng3 - OSF/LSM/2009.1 SW Eng5 - Both/LSM/2008.2 SW Eng6 - Both/LSM/2008.2 SW Eng7 - Both/LSM/2008.2 (5) IS Tech 1-5 - OSF/CSM/2008.1 (5) IS Tech 6-10 - OSF/CSM/2009.1 (3) IS Tech11-13 - OSF/CSM/2009.3 (3) IS Tech14-16 - OSF/CSM/2010.3 CntrlSpec1 - OSF/LSM/2007.2 CntrlSpec2 - OSF/LSM/2008.2 CntrlSpec3 - OSF/LSM/2009.1 CntrlSpec4 - OSF/LSM/2010.3 E.Eng1 - OSF/LSM/2007.4 E.Eng2 - OSF/LSM/2007.4 E.Eng3 - OSF/LSM/2008.2 E.Eng4 - OSF/LSM/2009.1 E.Eng5 - OSF/LSM/2009.1 (3) E.Eng6-8 - OSF/LSM/2009.3 SW Eng8 - Both/LSM/2011.1 SW Eng9 - Both/LSM/2011.1 SW Eng10 - Both/LSM/2011.1 SW Eng11 - Both/LSM/2011.1 Transport Super - OSF/LSM/2006.4 TransportDr2 - OSF/LSM/2008.2 (2)TransportDr3-4 - OSF/LSM/2009.1 TransportDr5 - OSF/LSM/2010.3 TransportDr6 - OSF/LSM/2011.4 DB Admin1 - OSF/LSM/2008.4 DB Admin2 - OSF/LSM/2010.1 DB Admin3 - OSF/LSM/2010.1 IT Computing Group (3) ETech1-3 - OSF/LSM/2008.2 (3) ETech4-6 - OSF/LSM/2008.4 (2) ETech7-8 - OSF/LSM/2009.1 (5) ETech9-13 - OSF/LSM/2009.3 (2) ETech14-15 - OSF/LSM/2010.3 (2) ETech16-17 - OSF/LSM/2011.1 (4) ETech18-21 - OSF/LSM/2011.3 (2) ElecTech1,2 - OSF/LSM/2007.4 ElecTech3 - OSF/LSM/2009.1 (2) ElecTech4,5 - OSF/LSM/2010.3 ElecTech6 - OSF/LSM/2011.4 IT Manager - SCO/LSM/2009.1 DB Admin4 - SCO/ISM/2009.3 (2) MechTech1,2-OSF/LSM/2007.4 MechTech3 - OSF/LSM/2009.1 (2) MechTech4,5 - OSF/LSM/2010.3 MechTech6 - OSF/LSM/2011.4 IT Supprt1 - OSF/CSM/2007.2 IT Supprt2 - OSF/CSM/2007.2 IT Supprt3 - OSF/CSM/2007.2 IT Supprt4 - OSF/CSM/2008.4 IT Supprt5 - OSF/CSM/2008.4 IT Supprt6 - OSF/CSM/2008.4 IT Supprt7 - OSF/CSM/2010.1 IT Supprt8 - SCO/CSM/2009.3 IT Supprt9 - SCO/CSM/2009.3 IT Spprt10 - SCO/CSM/2009.3 (2) MTech1,2 - OSF/LSM/2008.2 MTech3 - OSF/LSM/2009.1 (2) MTech4,5 - OSF/LSM/2009.3 (2) Helper1,2 - OSF/LSM/2007.4 Helper3 - OSF/LSM/2009.1 (2) Helper4,5 - OSF/LSM/2010.3 Helper6 - OSF/LSM/2011.4 (2) OpMTec1,2 - OSF/LSM/2008.2 OpMTec3 - OSF/LSM/2009.1 (2) OpMTec4,5 - OSF/LSM/2011.1 MIS Spprt1 -SCO/CSM/2009.3 MIS Spprt2 -SCO/CSM/2009.3 (2)Machinist1,2 - OSF/LSM/2007.4 Machinist3 - OSF/LSM/2009.1 (2)Machinist4,5 - OSF/LSM/2010.3 Machinist6 - OSF/LSM/2011.4 Red=added for ACA Blue=Transfer from construction

  37. ALMA Regional Centers (ARCs)

  38. “BeyondARC” User Services ALMA Operations: Three ALMA Regional Centers - ARCs NAASC EU ARC nodes ARCs provide basic user interface, as well as basic archive, software, and hardware maintenance and development EU ARC (ESO) NA ARC Joint ALMA Observatory ARCs are integral part of JAO ALMA Operations J ARC ? NAOJ

  39. Required ARC “Core” tasks • Operations support tasks: • Participate in Commissioning & Science Verification. • Schedule block verification. • Astronomer on Duty. • Data reduction help-desk. • TAC support (technical feasibility assessment) • Coordination meetings between ARCs, JAO. • For each s/w system (offline, PST, ObsTool, pipeline): • Participating in software pre-release tests (~ bi-annual). • “Exercising” s/w: using software to reduce simulated or real data; refine pipeline heuristics. • End-user documentation (hardcopy and web-based). • Support: helpdesk for offline, PST, ObsTool; develop heuristics for pipeline. • ARC Mirror Archive • Complete copy of SCO Science Archive, including raw and calibration data.

  40. ARC pre-Operations Duties ARC staff should be testing/exercising user software (PST, ObsTool, offline, pipeline) prior to its deployment as a means to train for support duties and to write support documentation. • Offline software released 2007.1 • Leaves 2 years for exercising on ALMA-like data (VLA, SMA, etc.) until Early Science Decision Point (ESDP) in 2010.1 • Proposal Submission Tool “more or less done” 2007.2, more fully integrated 2008.1. • Leaves ~2 year for testing/training prior to earliest Call for Proposals in 2010.1. • ObsTool (proposal Phase II): ready for expert users in 2009.1. • Leaves ~18mo for testing/training until first phase II in 2010.3. • Pipeline delivered 2011.3 • ARC staff help develop heuristics; will be involved in e2e tests prior to deployment ARC staff need to test, train, and generate end-user documentation (e.g. cookbooks) by Call for Proposal (PST, 2010.1), Phase II submission (ObsTool, 2010.3) and Early Science (Offline, 2010.3). Must exercise pipeline and refine heuristics with ALMA data prior to delivery in 2011.3.

  41. W W W W W S S S S S Pipeline heuristics =workshop =school TAC Support Sched. Block verification Pre-test exercise support doc Delaying Early Science ObsTool Pipeline Offline PST W 2006.4 NSF proposal due ……………………………………………………………………………………………………… 2007.1 Offline software/level1 ………………………………………………………………………………………………… 2007.2 PST “mostly done” …………………………………………………………………………………………………….. 2007.3 ……………………………………………………………………………………………………………………………… 2007.4 ……………………………………………………………………………………………………………………………… 2008.1 ……………………………………………………………………………………………………………………………… 2008.2 ……………………………………………………………………………………………………………………………… 2008.3 ……………………………………………………………………………………………………………………………… 2008.4 3 element inter/AoD starts …………………………………………………………………………………………… 2009.1 OT ready for “expert users” ……………………………………………………………………………………………. 2009.2 ESDP: CfP/prop. submission …………………………………………………………………………………………. 2009.3 TAC support ……………………………………………………………………………………………………………. 2009.4 phase II submission ……………………………………………………………………………………………………. 2010.1 Start early science ESDP:CfP …..…………………………………………………………………………………… 2010.2 TAC support ……………………….…………………………………………………………………………………… 2010.3 phase II submission …………….……………………………………………………………………………………… 2010.4 Start early science ……………………………………………………………………………………………………… 2011.1 ……………………………………………………………………………………………………………………………… 2011.2 Pipeline at SCO ………………………………………………………………………………………………………… 2011.3 ARC mirror archives …………………………………………………………………………………………………… 2011.4 ……………………………………………………………………………………………………………………………… 2012.1 ……………………………………………………………………………………………………………………………… 2012.2 ……………………………………………………………………………………………………………………………… 2012.3 ……………………………………………………………………………………………………………………………… 2012.4 ……………………………………………………………………………………………………………………………… W CSV Demonstration Science AoD Non-core: splatalogue, Schools, workshops, Calibration surveys Software support Other support Other

  42. ALMA Operations: ALMA Regional Centers: Full Operations EU ARC NA ARC EA ARC ARC Head Office ARC Manager - NA/RSM/2006.3 AdminAsst1 - NA/RSM/2008.1 ARC Head Office ARC Manager - NA/RSM/2006.1 AdminAsst1 - NA/RSM/2008.1 ARC Head Office ARC Manager - NA/RSM/2006.3 AdminAsst1 - NA/RSM/2008.1 User Science Support User Science Support User Science Support ARC Astronomer1 - NA/RSM/2007.1 ARC Astronomer2 - NA/RSM/2008.2 ARC Astronomer3 - NA/RSM/2008.4 ARC Astronomer4 - NA/RSM/2010.2 ARC Astronomer5 - NA/RSM/2010.2 ARC Astronomer6 - NA/RSM/2011.1 ARC Scientist1 - NA/RSM/2007.3 ARC Scientist2 - NA/RSM/2008.4 ARC Scientist3 - NA/RSM/2009.2 ARC Scientist4 - NA/RSM/2010.2 Web Developer - NA/RSM/2009.4 ARC Astronomer1 - NA/RSM/2006.3 ARC Astronomer2 - NA/RSM/2008.2 ARC Astronomer3 - NA/RSM/2008.4 ARC Astronomer4 - NA/RSM/2010.2 ARC Astronomer5 - NA/RSM/2010.2 ARC Astronomer6 - NA/RSM/2011.1 ARC Scientist1 - NA/RSM/2007.3 ARC Scientist2 - NA/RSM/2008.4 ARC Scientist3 - NA/RSM/2009.2 ARC Scientist4 - NA/RSM/2010.2 Web Developer - NA/RSM/2009.4 ARC Astronomer1 - NA/RSM/2007.1 ARC Astronomer2 - NA/RSM/2008.2 ARC Astronomer3 - NA/RSM/2008.4 ARC Astronomer4 - NA/RSM/2010.2 ARC Scientist1 - NA/RSM/2007.3 ARC Scientist2 - NA/RSM/2008.4 ARC Scientist3 - NA/RSM/2010.2 Web Developer - NA/RSM/2009.4 Archive Ops Archive Ops Archive Ops Database Managr1 - NA/RSM/2011.2 Archive Tech1 - NA/RSM/2009.1 Archive Tech2 - NA/RSM/2011.3 Archive Developr1 - NA/RSM/2011.4 Archive Developr2 - NA/RSM/2011.4 Database Managr1 - NA/RSM/2011.2 Archive Tech1 - NA/RSM/2009.1 Archive Tech2 - NA/RSM/2011.3 Archive Developr1 - NA/RSM/2011.4 Archive Developr2 - NA/RSM/2011.4 Database Managr1 - NA/RSM/2011.2 Archive Tech1 - NA/RSM/2009.1 Archive Tech2 - NA/RSM/2011.3 Archive Developr1 - NA/RSM/2011.4 Archive Developr2 - NA/RSM/2011.4

  43. North American ALMA Science Center (NAASC)

  44. NAASC: North America ALMA Science Center, Charlottesville, VA • One-stop shopping for NA astronomers • Proposals • Observing scripts • Data archive and reduction

  45. “BeyondARC” User Services Beyond ARC is needed to provide advanced user support, algorithm development, student programs, EPO, grants ALMA Operations: Three ALMA Regional Centers - ARCs NAASC “Satellite” EU ARCs ARCs provide basic user interface, as well as basic archive, software, and hardware maintenance and development EU ARC (ESO) NA ARC Joint ALMA Observatory J ARC ? NAOJ

  46. NAASC Org. Chart NRAO Directors Office ANASAC NAASC Head Office Science Development Division Chilean Affairs NA ARC Manager Advanced User Support Technical Division Maintenance & Repair of NA hardware deliverables; hardware development for new mm/submm capabilities Data Management Division Maintenance & Repair of NA software deliverables; software development for new operational modes User Science Support Professional Development Archive Operations Postdocs& students NA ALMA EPO = ARC Core support = MR&D support = Enhanced services

  47. Operations Technical Support • Operations running cost include budget to provide technical support for hardware and software delivered to project by each executive • Best to have experts who built hardware or wrote software maintain it. • Managed by Director of Technical Services (hardware) or Director of Science Operations (software). • How managed regionally depends on executive

  48. Operations Core Support NAASC Org. Chart NRAO Directors Office ANASAC NAASC Head Office Science Development Division Chilean Affairs NA ARC Manager Advanced User Support Technical Division Maintenance & Repair of NA hardware deliverables; hardware development for new mm/submm capabilities Data Management Division Maintenance & Repair of NA software deliverables; software development for new operational modes User Science Support Professional Development Archive Operations Postdocs& students NA ALMA EPO = ARC Core support = MR&D support = Enhanced services

  49. “Beyond Core” NAASC Org. Chart NRAO Directors Office ANASAC NAASC Head Office Science Development Division Chilean Affairs NA ARC Manager Advanced User Support Technical Division Maintenance & Repair of NA hardware deliverables; hardware development for new mm/submm capabilities Data Management Division Maintenance & Repair of NA software deliverables; software development for new operational modes User Science Support Professional Development Archive Operations Postdocs& students NA ALMA EPO = ARC Core support = MR&D support = Enhanced services

  50. NAASC ARC Functions • End to end proposal submission, review coordination, scheduling preparation, cookbooks, quality assurance, NA mirror archive • User friendly web-based access • Helpdesk based problem resolution • North America software maintenance and development • Offline system, scheduler, ACS, M&C • North America hardware maintenance and development • Band 3 & 6 Receivers, LO system, DTS system