html5-img
1 / 7

EMGT 501 HW #4 Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17

EMGT 501 HW #4 Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17 Due Day: Oct 10. EMGT 501 HW #4 Solutions Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17 . Ch. 11 – 3. a. r = dm = 20(5) = 100

braith
Download Presentation

EMGT 501 HW #4 Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMGT 501 HW #4 Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17 Due Day: Oct 10

  2. EMGT 501 HW #4 Solutions Chapter 11 - SELF TEST 3 Chapter 11 - SELF TEST 7 Chapter 11 - SELF TEST 17

  3. Ch. 11 – 3 a. r = dm = 20(5) = 100 Since , both inventory position and inventory on hand equal 100. b. r = dm = 20(15) = 300 Since , both inventory position and inventory on hand equal 300.

  4. c. r = dm = 20(25) = 500 Inventory position reorder point = 500. One order of Q* = 400 is outstanding. The on-hand inventory reorder point is 500 - 400 = 100. d. r = dm = 20(45) = 900 Inventory position reorder point = 900. Two orders of Q* = 400 are outstanding. The on-hand inventory reorder point is 900 - 2(400) = 100.

  5. Ch. 11 – 7 Where is the revised order quantity for the new carrying charge . Thus

  6. Ch. 11 – 17 EOQ Model Total Cost Planned Shortage Model

  7. Total Cost • Cost Reduction with Backorders allowed • $848.53 - 791.25 = $57.28 (6.75%) • Both constraints are satisfied: • 1. S / Q = 39.56 / 303.32 = 0.13 • Only 13% of units will be backordered. • Length of backorder period = S / d = 39.56 / (800/250) • = 12.4 days