This document outlines the agenda for the Regional Technical Forum (RTF) Meeting held on July 17, 2012, focused on the Standard Protocol for Non-Residential Lighting Efficiency Measures. It reviews project status, addresses subcommittee issues, and discusses key components such as source data for wattage, hours of operation defaults, control impacts, and HVAC interactions. The meeting aims to refine guidelines, share findings from previous discussions, and seek consensus on updating protocols vital for enhancing lighting efficiency in non-residential settings.

billie
Download Presentation

Standard Protocol for Non-Residential Lighting Efficiency Measures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Standard Protocol for Non-Residential Lighting Efficiency Measures Regional Technical Forum Meeting July 17, 2012

  2. Agenda • Introduction • Project status • Subcommittee Issues Addressed • Source data for wattage, existing and efficient case • Hours of operation defaults • Controls impacts • HVAC Interaction effects • Standard Protocol guidelines • Discussion

  3. Introduction • RTF staff & consultants • Lighting subcommittee members

  4. Project Status Review • Kick off meeting held - March 9th • Work plan developed – March 21st • Review memo distributed – April 20th • Draft protocols posted for review May 10th • Subcommittee discussion on Draft – May 16th • Revised Protocol posted – June 27nd • Lighting subcommittee review – July 3rd • Protocol update for Subcommittee – July 17th • Protocol to RTF for decision – August 21st

  5. Project Participation

  6. Project Participation

  7. System Power • Fixture rated wattage from manufacturer spec sheets • Program administrator maintains a list of fixture wattages, based on: • Manufacturer spec sheets • DesignLights Consortium – solid state lighting • Energy Star • Efficient case wattage from manufacturer spec sheets • No provisional data collection required

  8. Hours of Operation • Information collected to estimate lighting operating hours by space use type • Control schedules • Occupancy schedules, interviews • Alternative approach – prescribed list of operating hours by building type and space occupancy type • Provisional data collection required (trend logging of lighting and current)

  9. Controls • Prescribed list of control savings by space & control type • Primary source – LBNL study • Secondary sources to fill study gaps • Programs with savings partially based on measured data • Provisional data collection required (trend logging of lighting and current)

  10. HVAC Interactive Effects • Prescribed list • Source – regional resource planning factors used for Sixth Power Plan • Based on DOE2 simulations of proto-type buildings by climate zone and fuel • No provisional data collection required

  11. Provisional Data Collection • Specific to operating hours and control impacts • Required until sufficient data collected to demonstrate reliability of savings estimates • Trend data collected • Lighting/current loggers • Sampling allowed within sites • Program sampling as per independent impact evaluation design

  12. Protocol Calculator • Demonstrates protocol calculation methodology • Fixture wattage inputs • LPA inputs for code-impacted measures • Operating hour input from provisional data (hours of use and/or controls) or default operating hours • Default list of control savings

  13. July 3 Subcommittee Issues • Define baselines clearly as per the Guidelines language of current practice and pre-conditions • Add custom measure language for defining baselines • Add lighting fixture data table to calculator (BPA list determined to be from mfg’s. data) • Provide RTF HVAC interaction by climate zone by building type and fuel