Interactive Session 4. Tuesday, July 17 7pm to 10pm Build a sqa plan for the dental office software Assume a 3-person, development team, a separate 2-person, test team, and a project manager above the dev team’s manager

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Interactive Session 4' - bian


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
interactive session 4
Interactive Session 4
  • Tuesday, July 17 7pm to 10pm
  • Build a sqa plan for the dental office software
  • Assume a 3-person, development team, a separate 2-person, test team, and a project manager above the dev team’s manager
  • Assume a reasonable set of company standards and a reasonable set of project documents
sqa plan
SQA Plan
  • This is a example of an SQA plan.
  • See lecture page for link
final exam preview

Final Exam Preview

Final Exam, Thursday, July 26

earned value analysis

Earned Value Analysis

Basing Progress on Percentage of Estimated Effort

basic measures 1
Basic Measures (1)
  • Budgeted Cost of Work(BCW): the estimated effort for each work task.
  • Budget at Completion (BAC): the sum of each BCW and thus the estimate of the total effort for the project
  • Planned Value (PV): the percentage of the total estimated effort that is assigned to a particular work task. PV = BCW/BAC
basic measures 2
Basic Measures (2)
  • Budgeted Cost of Work Scheduled (BCWS): the sum of the estimated effort for each work task that was scheduled to be competed by the specified time.
  • Budgeted Cost of Work Performed (BCWP): the sum of the estimated efforts for the work tasks that have been completed by the specified time.
basic measures 3
Basic Measures (3)
  • Actual Cost of Work Performed (ACWP): the sum of the actual efforts for the work tasks that have been completed.
progress indicators 1
Progress Indicators (1)
  • Earned Value(EV) = BCWP/BAC = the sum of the PV’s for all completed work tasks
  • Schedule Performance Index (SPI) = BCWP/BCWS
  • Schedule Variance (SV) = BCWP – BCWS
progress indicators 2
Progress Indicators (2)
  • Percent Complete (PC) = BCWP/BAC
  • Cost Performance Index (CPI) = BCWP/ACWP
  • Cost Variance (CV) = BCWP – ACWP
l14as12 ind asg due 7 24
L14aS12 – Ind Asg due 7/24

Plot all the progress indicators for the time 1/1 to 9/1

Plot at .5 month intervals and use .5 month units