1 / 19

Somalia Road Map Plan to achieve 100% coverage of malaria control by Dec. 2010 Sept. 2010

Somalia Road Map Plan to achieve 100% coverage of malaria control by Dec. 2010 Sept. 2010. General Context.

bernadette
Download Presentation

Somalia Road Map Plan to achieve 100% coverage of malaria control by Dec. 2010 Sept. 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Somalia Road Map Plan to achieve 100% coverage of malaria control by Dec. 2010 Sept. 2010

  2. General Context 3 distinct areas:Somaliland, Puntland, Central/South SomaliaHealth indicators- UMR: 225 (per 1,000)- MMR: 1100 (per 100,000)- Malaria prevalence 1 – 10%Political / SocialPopulation – approx 9.3 M. InsecurityPopulation displacementFew health workerHealth system is fragmented & under financed

  3. Malaria Program • Currently funded under the GF Rd 6 from Nov 2007 to Oct 2012. • Phase 1: Sept 2007 to Oct 2009 - 13million • Phase 2: Nov 2009 to Oct 2012 - 14million • Implementation of activities guided by the National Malaria Strategy 2005 to 2010 • Updated NMS / M&E Plan (2010 to 2015) revised, approved and endorsed by health authorities in the three zones. • Courtesy of the EARN/RBM support to finalize and endorse (March 31, 2010)

  4. Situation Analysis • Case Management • Introduction of ACT/RDT started in 2006, covering all Hospital & MCH • Guidelines in place BUT need revision • Just introduced ACT/RDT at the lower Health post levels (2009) • No funding Gap • Malaria prevention • 715,000 distributed: 50,000 procured and planned for distribution • 76,480 received at Mombasa and earmarked for distribution in Lower Shabelle and Lower Juba/ Sept/Oct • So far coverage is estimated above 65% (except L.Sh)

  5. Situation Analysis • IEC • Implementation guided by Malaria communication strategy (2006/2010) • Malaria Communication strategy needs to be updated • Activities – Trained 30% of HWs on communication techniques: Community dialogue: Conducting malaria field days and annual World Malaria Day • Malaria in pregnancy • Implemented only in the CSZ of Somalia • SP is procured by UNICEF: No funding gap • LLINs distributed as part of mass coverage (No ANC distribution)

  6. Situation Analysis ctd • Health system strengthening • 60% of labs undergoing QC • 30% of laboratory technicians trained • 8 senior lab tech to be trained in lab QC • Epidemic Preparedness and response • 7% of health staff trained on epidemic preparedness & response • No clear EP&R strategy except Somaliland (mapping not done, estimate not done) – TA required • HMIS • On-going under Rd 6: All districts covered in Somaliland & Puntland is on-going • Data has started flowing • IDSR – Functioning by the end of 2010 • Strengthening of Malaria Control Program • Established in all three zones. • NMCP Managers trained and supported

  7. Road map Sept 2010 Evaluation - LLIN

  8. Road Map Sept 2010 Evaluation-ACT RDT

  9. Road Map Sept 2010 Evaluation-ACT RDT

  10. Supervision & Capacity building 1 * post pond-Jan11

  11. Road Map Sept 2010 Supervision & Capacity building valuation-

  12. Supervision & Capacity building 2

  13. Road map Sept 2010 Evaluation- Limiting Factors (Mitigation)

  14. Technical Assistance needs over 3 months (Oct – Dec 2010) • Updating communication strategy for malaria (Oct 2010) • GF Rd 10 proposal (NSP and M&E costing on going) • Development of Epidemic Preparedness & Response Strategy (Oct 2010) • Establishment of 3 Ent Units (1/Zone - on going) – TA not needed • Health Facility mapping (especially Health post) • Participation request for support Nationals to attend the 29th Dec meeting in Cairo on PRM • AMD policy update/Work Shop – Oct/Nov 2010 • SMS intruduction in Surveillance weekly data collection

  15. Road Map Sept 2010 Evaluation- TA needs

  16. Road Map Sept 2010 Evaluation- TA needs cont…

  17. MMRT for 18 lab tech (8/NWZ, 10/NEZ) • Ent Unit Equipments procured and will be distributed in Oct 2010 • IRS campaigns implemented (in all zones) • Successful and effective participation in 9th inter-country meeting/ Marrakesh/Morocco • Quarterly supervision of HF and distribution of lab supplies, ACTs and RDTs Latest activities Sept. 2010

  18. Way forward – Oct – Dec 2010 • PR/UNICEF: • 1.2 Million LLINs planned for distribution under Rd 6 ending Nov 2012 • 250,000 LLINs expected to arrive end of September : Gap of 1.2 million • Support NMCP offices (MW & NE only) • WHO • Ent Units establishment – Oct 2010 – Procurements - done • MMRT – for CSZ 10 participants 16th – 30th Oct - DONE • Vector susceptibility tests – 10th Oct - Done • Amend the MOU with PR/UNICEF for Yr 4 (Nov 2010 – Oct 11) • Other SR: ?? (HAVOYOCO, CCM/Italy, MENTOR) • CARITUS – IRS activities

More Related