The NPDES Permit Program and its applications on a local industry

The NPDES Permit Program and its applications on a local industry. What is NPDES? . Part of the Clean Water Act (CWA) National Pollution Discharge Elimination System 40 CFR 122 The Program’s purpose is to help prevent and remove pollutants from our Nation’s rivers, lakes, and costal waters.

berke
Download Presentation

The NPDES Permit Program and its applications on a local industry

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The NPDES Permit Program and its applications on a local industry

  2. What is NPDES? • Part of the Clean Water Act (CWA) • National Pollution Discharge Elimination System 40 CFR 122 • The Program’s purpose is to help prevent and remove pollutants from our Nation’s rivers, lakes, and costal waters.

  3. Why NPDES? • Complex piece of legislation to understand • Required to complete a Storm Water Pollution Prevention Plan (SWP3) for a Genzyme site in Framingham

  4. Evolution of NPDES • 1970 Refuse Act Permit Program (RAPP) • Developed form the Rivers and Harbors Act of 1899 • Under the direction of the Army Corps of Engineers • Recodified in 1972 to the Federal Water Pollution Control Act (FWPCA) • Water quality based and technology based control strategies • First goals and principles were set regarding clean waters

  5. Evolution of NPDES • From 1973-1976 the first NPDES permits were issued • Focus was on • Best Available Technology (BAT) • Best Practical Control Technology (BPT) • Best Management Practices (BMP) • 1977 – Amendments to the FWPCA provided the framework for the CWA • CWA was amended in 1987 to meet water quality standards set by states

  6. Evolution of NPDES • CWA highlights • Priority pollutants • Schedules and Programs for industrial and municipal stormwater discharges • Toxics • Conventional • Toxic • Non-conventional • Vectors • Point – Discharge directly into water bodies • Non-point – Goes through POTW

  7. NPDES Permitting • Two Types of permits • Individual – Tailor to the facility • General – Cover multiple facilities in a particular group (Multi-Sector General Permit) • All permitted facilities are required to create and maintain a Storm Water Pollution Prevention Plan • MA is a non-delegated NPDES permit state • EPA and DEP jointly issue and enforce the permit

  8. Applicability for the Genzyme Framingham site • Genzyme is required to have a permit because: • Manufacturing designation under the Standard Industrial Codes (SIC) • Discharges stormwater from the site to surface waters (Foss Reservoir)

  9. Genzyme Framingham Site

  10. Stormwater Pollution Prevention Plan Overview • Genzyme has a Multi-Sector General Permit (MSGP) • Blanket permit issued to facilities that don’t require an individual permit. • Issued Oct. 30th 2000 – Exp. Oct 30th 2005

  11. Stormwater Pollution Prevention Plan Requirements • Requirements include: • Prohibited discharges of point source pollution • Best Management Practices (BMP’s) - PM’s etc. • Risk assessments of pollutant sources • Quarterly inspections • Annual site inspection

  12. Stormwater Pollution Prevention Plan Requirements • Annual Training • Review and revise plan every three years or as needed. • Pollution Prevention Team

  13. Pollution Prevention Team • Must implement the following • All general permit and pollution prevention plan requirements • Defining and agreeing on goals for the program • Being aware of any changes that could impact stormwater discharge

  14. Inspection Schedule • Quarterly • Wet weather inspections - 2nd & 3rd quarters • Sample taken from each drainage area • Visual monitoring record • Dry weather inspections - 1st and 4th quarters • Emergency Generators & Fire Pump • Site Drainage Ditches/Swales

  15. Inspection Schedule • Semi-Annually • Catch Basins & Storm Drain Manholes • Annually • Site Assessment • Training

  16. QUESTIONS?