1 / 27

TK3333 Software Management

TK3333 Software Management. Topic 9 : Cost Planning and Performance. Contents. Prepare a baseline budget Cumulate actual costs Determine the earned value of work performed Analyse cost performance Forecast project cost at completion Control project costs Manage cash flow.

belden
Download Presentation

TK3333 Software Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TK3333Software Management Topic 9: Cost Planning and Performance

  2. Contents • Prepare a baseline budget • Cumulate actual costs • Determine the earned value of work performed • Analyse cost performance • Forecast project cost at completion • Control project costs • Manage cash flow

  3. Real World Example • Vignette: eBay • eBay understands the importance of analyzing project data to produce performance indicators. • eBay’s mission is to provide a trading platform for people all over the world. They do this by continually improving the user’s experience on the eBay site. • Decisions for change are based on measurable factors like the number of visitors to the site, length of time customers spend on eBay, busiest day of the week for eBay transactions, etc. • Managers regularly collect data from the site to develop new marketing and merchandising techniques. This mentality has helped eBay to continually improve the buy-sell process for eBay customers. • Project managers should understand the value of measurable factors, and apply them to make responsible decisions about their projects.

  4. Real World Example • Vignette: London Traffic • Ken Livingstone was London’s first directly elected mayor in 2000. He created Transport for London to oversee the city’s road and transport services that were previously managed separately. Mission: to upgrade London’s transportation infrastructure with a toll system project. • Traffic congestion is a major problem for central London. Transport for London developed a plan to install a system that would identify and charge car owners that enter defined congestion zones. • Technological risks were identified, and the project was divided into 5 smaller components (to be managed separately, as opposed to purchasing one large system). • Project team worked together in one location on the five components to the system. • The project was successfully implemented by February 2003. Transport for London reports that traffic in the congestion zone has decreased by 20%, with a 5% increase during travel times.

  5. Project Cost Estimates • Cost planning starts with the proposal. • The cost section may include: • Labor • Materials • Subcontractors and consultants (if used) • Equipment and facilities rental • Travel

  6. Project Budgeting: Two Steps • The project cost estimate is allocated to the various work packages in the project work breakdown structure. • The budget for each work package is distributed over the duration of the work package.

  7. Step 1: Allocating the Total Budgeted Cost • Allocating total project costs for the various elements to the appropriate work packages will establish a total budgeted cost (TBC) for each work package. • There are two approaches to establishing the TBC for each work package: top-down and bottom-up. • When all budgets are summed, they cannot exceed the TBC.

  8. Step 1: Allocating the Total Budgeted Cost Top-down Bottom-up Source: pg. 269

  9. Step 2: Developing the Cumulative Budgeted Cost • The second step is to distribute each TBC over the duration of its work package. • A cost is determined for each period. • The cumulative budgeted cost (CBC) is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time. • One uses the CBC as the standard against which actual cost is compared.

  10. Developing the Cumulative Budgeted Cost Source: pg. 270-271

  11. Determining Actual Cost • Track actual cost by establishing a system to collect data on funds actually expended. • Cost that actually is spent. • Periodically assign a portion of the total committed cost (commitments/encumbered costs) to actual cost. • Cost that is allocated although it has not been totally spent (e.g. salary) • Total actual and committed cost by work package for comparison to the CBC. • Cumulative actual cost (CAC) should be calculated.

  12. Determining Actual Cost CBC CAC Source: pg. 273-274

  13. Determining the Value of Work Performed • Earned value is the value of the work actually performed. • Determine earned value by collecting data on the percent complete for each work package. • Convert this percentage to a dollar amount by multiplying the TBC of the work package by the percent complete. • EV = % complete x TBC

  14. Determining the Value of Work Performed Cumulative % complete CEV Source: pg. 276-277

  15. Cost Performance Analysis Based on 4 measures: • Total Budgeted Cost (TBC) • Cumulative Budgeted Cost (CBC) • Cumulative Actual Cost (CAC) • Cumulative Earned Value (CEV) FCAC General performance CPI; CV

  16. Cost Performance Index (CPI) • A measure of the cost efficiency with which the project is being performed. • The earned value received for every $1 spent. • The index is dimensionless. • Cost performance index (CPI) = F(Cumulative earned value, Cumulative actual cost) = CEV/CAC • Ideally CP1 should be 1.0 (i.e. $1 spent = $1 value). • If CPI < 1.0 or gets smaller, corrective action should be taken.

  17. Cost Variance (CV) • The difference between the cumulative earned value of the work performed and the cumulative actual cost. • Similar as CPI, except that it is expressed in $. • Cost Variance (CV) = Cumulative Earned Value (CEV) – Cumulative Actual Cost (CAC) • Ideally CV should be positive values (i.e. value >= cost). • If CV is negative, corrective action should be taken. • But, don’t be too happy with positive values => maintain that way!

  18. Cost Forecasting • Three methods for determining forecasted cost at completion (FCAC): • FCAC = Total Budgeted Cost /Cost Performance Index • FCAC = Cumulative Actual Cost + (Total Budgeted Cost – Cumulative Earned Value) • FCAC = Cumulative Actual Cost + Re-estimate of remaining work to be performed

  19. Cost Forecasting • FCAC = Total Budgeted Cost /Cost Performance Index • The value is based on the current efficiency rate (i.e. remain the current performance). • FCAC = Cumulative Actual Cost + (Total Budgeted Cost – Cumulative Earned Value) • The value ignores the past/current efficiency rate. Focus on the remaining, which will be performed at an efficiency rate of 1.0 (i.e. maximum performance to meet the budget). • FCAC = Cumulative Actual Cost + Re-estimate of remaining work to be performed • Redo the estimation of the remaining activities. Time consuming. Only use this when the project has deviated far from the actual plan.

  20. Cost Forecasting CEV CAC TBC (1) FCAC = TBC/CPI = TBC/(CEV/CAC) = 100000/(54000/68000) = $126,582 (2) FCAC = CAC + (TBC – CEV) = 68000 + (100000 - 54000) = $114,000 (3) FCAC = CAC + $$$$

  21. Cost Control • The key is to analyse cost performance on a regular and timely basis (e.g. every 30th day of the month). • Identify cost variances and inefficiencies early (i.e. CV negative) . • Involves analysing cost performance to determine which work packages may require corrective action (i.e. CPI < 1.0). • Deciding what corrective action should be taken • Revising the project plan

  22. Cost Control • When a project is offtrack, we can: • Ignore the deviation. • When the deviation is smaller than the tolerance we can hold. If not, do option 2 or 3 below. • Take corrective actions to get back on target. • Revise the plan to reflect the deviation. • Adjust schedule, scope or performance requirements. • Cancel the project altogether. • When the project has slipped too much that it is no longer viable (i.e. too late, too expensive or non-functional).

  23. Cost Control • Taking corrective actions to reduce the costs: • Activities that will be performed in the near future. • Do not procrastinate! The more you wait, the lesser time you have to do anything. • Activities that have a large cost estimate. • Reduce large cost better than eliminate small tasks. • The larger estimated cost, the greater the opportunity for cost reduction.

  24. Ways to Reduce Costs of Activities • Substitute less expensive materials. • But, the quality may be jeopardised. • Assign a person with greater expertise to perform or help with the activity. • But, his/her pay may be higher. • Reduce the scope or requirements. • This will makes customers unhappy. • Increase productivity through improved methods or technology. • Cost may be higher; learning curve etc.

  25. Managing Cash Flow • Make sure that sufficient payments are received from the customer in time for you to cover the costs of performing the project. • The key to managing cash flow is to ensure that cash comes in faster than it goes out. • Some guidelines: • Ask customer to pay early (e.g. downpayment; frequent and equal monthly/weekly payment) • Invest any excess cash and earn interest. • Avoid customer from paying only at the end of the project. • Delay payment to suppliers as possible.

  26. Project Management Software • All costs associated resources can be stored. The software calculates the budget for each work package and for the entire project. • The software allows the user to define different rate structures for each resource and when charges for those resources will be accrued. • Cost tables and graphs are available to help analyse cost performance.

  27. Thank You • Question? • Next (4/5) : • Mid Sem (20%) • Tue 4/5 8.15pm; Topic 1-8

More Related