Evaluating InSync Performance in Microsimulation

Evaluating InSync Performance in Microsimulation. Aleksandar Stevanovic, PhD, PE Florida Atlantic University. Transpo 2012 Bonita Springs, FL October 29, 2012. Why Simulating InSync ?. Comprehensive evaluation of its performance Controlled experiments Abundance of outputs

baird
Download Presentation

Evaluating InSync Performance in Microsimulation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Evaluating InSync Performance in Microsimulation Aleksandar Stevanovic, PhD, PE Florida Atlantic University Transpo 2012 Bonita Springs, FL October 29, 2012

  2. Why Simulating InSync? • Comprehensive evaluation of its performance • Controlled experiments • Abundance of outputs • Better understanding of pros & cons • Repeatability and comparability

  3. Originality of this Study • No comprehensive evaluation of InSync in microsimulation • Regular operations modeled with no attention to special conditions/situations • Evaluation of InSync for regular operations (AM, MD, and PM) + • Freeway Incident • Rail Preemption • Extra Demand • Inclement Weather

  4. About SR 421 - Dunlawton Ave • 12 signalized intersections (11 analyzed) • Divided 4-6 lane facility • Left turns • RR crossing & school zones • 35-50 mph speed limits

  5. Why SR421 in Volusia County? • A common (sub)urban corridor • Difficult to retime • Seasonal and annual variations in traffic flows • Evacuation route

  6. Data Collection for VISSIM Model • Turning movement counts • Travel times along mainline (GPS & video) • Signal timing sheets & Synchro files • Other data – RR gate timings, school zone hours, etc.

  7. Google Map as Background

  8. NEMA-like Ring-Barrier Controllers

  9. Calibration • Making sure that modeled and simulated volumes are equal • Volume balancing • Sources and sinks • Saturation flow rates • Manual process

  10. Calibration Details – Nova Rd

  11. Calibration Results

  12. Validation • Verifying that segment travel times from model and field are comparable • Speed distributions • Acceleration & deceleration • Offsets & detectors • Understand limitations

  13. Validation Results AM Peak MD Peak PM Peak

  14. TOD Signal Timings

  15. InSync – Controllers Run Free • 1) Disable all coordination (set controller into “free/uncoordinated” mode) • 2) Enable Detector Diagnostic Failure Mode • a. Set On failure to 250 minutes • b. Set Off failure to 5 minutes • i) Diagnostic failure mode on a 170 will allow itself to come out of failure. • 3) Set all “Minimum Green” times to 5 sec., or as client feels comfortable • 4) Leave “Maximum Green” times as before • 5) Set “Passage Gap” or “Observed Gap” to 1 sec. • 6) For protected/permitted left turns, omit the left turn call when the opposing thru • movement is green. • • Notes: • o This will prevent a yellow trap if the controller receives calls on • permitted left turn phases when the opposing thru is green, but may • not bring on the adjacent green thru movement to allow the left turn • a permitted movement. • 7) Enable “Soft Recall” on the mainline phases • 8) Disable “Yellow Lock” and “Red Lock” detector locking • 9) Set all “Detector Delays” to 0 sec. • 10) Disable all recalls: Max, Min, Hard, Vehicle, Phase, etc. • 11) Remove “Extensions” • 12) Disable “Anti-Backup” or “Left Turn Trap” • 13) Enable “Max Recall Inhibit”

  16. InSync Detectors in VISSIM

  17. InSync-VISSIM Interface

  18. Field-like InSync Dialog Box If a picture is used, use this layout. Pics are much preferred over bullets or other text.

  19. Simulations • Four signal timing scenarios - Identical traffic flows and geometric conditions • Field TOD • Optimal TOD – single section • Optimal TOD – multiple sections • InSyncAdaptive – no additional adjustments • 10 random seeds • Three peak periods (AM, MD, and PM) • 2.5 hours (15 min for warm up and 15 min for cool off) for each peak period

  20. Operational Scenarios • Regular operations - 3 peak periods (AM, MD, and PM) • Special operations (only for PM peak) • Freeway Incident - Traffic diversion due to a freeway incident • Rail Preemption - Impact of disruption caused by freight train operations • Extra demand – 20% traffic growth (flat) • Inclement Weather - Reduction in speed and sat. flows due to a heavy rain

  21. Freeway Incident • An 1-hour incident on I-95 freeway between SR 421 and SR 400 • One lane closed – traffic diverts to SR 421 • AADT ~ 50,000 veh/day; k factor ~ 15%; d factor ~ 55%; 4 lanes • 1,000 veh – diverted to SR 421 during one hour

  22. Diversion Routes 300 300 Incident 200 200 1000 vph

  23. Rail Preemption • 4 trains modeled in 2 PM peak hours (every 30 mins) • Anywhere between 20 – 100 cars in a train (modeled 20, 30, 70, and 100) • Train’s speed distributed around 45 mph • Gates take about 7 seconds to go up/down

  24. SR 421 & FEC Railway FEC RR

  25. Extra Demand • Flat increase of 20% for all of the traffic demand generators • Turning movement proportions remain the same • Impact on intersections – almost all intersections worsen LOS by one grade • Oversaturated network (8 ints. at LOS D or worse; 4 ints. at LOS E or worse)

  26. Inclement Weather • Inclement weather conditions (heavy rain) in Florida • PM Peak traffic demand unaltered (worst-case scenario) • Travelling speeds reduced by ~ 15% (from - 20% to -10%) • Saturation flows reduced by ~ 20% (~ ~ 1500 vph)

  27. What was Evaluated? • Intersection performance • Main-corridor travel times • Main street vs. Side street • Network performance

  28. Results Examples

  29. Intersection Performance

  30. AM Peak – Intersection Delay

  31. MD Peak – Number of Stops

  32. PM Peak – Average Queue

  33. ED – Level of Service

  34. Main-Corridor Travel Times

  35. IW Travel Times EB

  36. IW Travel Times WB

  37. IW Travel Times All

  38. IW Travel Times - Summary Percent improvement

  39. Main Street vs. Side Street

  40. RP Main vs. Side Street T & L

  41. RP Main vs. Side Street

  42. Network Performance

  43. FI Total Network Delay

  44. FI Total Number of Stops

  45. FI Total Travel Time

  46. FI Network Summary

  47. Summary of Results

  48. Reduction [%] of Delays & Stops Average improvements: Delay ~ 22%; Stops ~ 15 %

  49. Summary – All Scenarios InSync better than a respective TOD signal timing Results are not definite or TOD is better

  50. Questions, feedback, comments? astevano@fau.edu