An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. [23/1-19/2] MOM report Zisman Apollonio 23/1/09 19/2/09 12/2/09 • Relevant Issues: • NO target since december accident •  no data taking •  we have 80 days (to ISIS startup) • Try to turn a failure into an opportunity? Hogdson MICE VC 12/2/2009

  2. A pretty dense schedule! • target re-design (J. Tarrant, this VC) • fixing the solenoid (M. Courthold et al., this VC) • levelling the floor downstream Q9 • minor issues MICE VC 12/2/2009

  3. Pump vacuum Cool down 10xMLI sheets on DS end placed 12/2/09 • DKsol vacuum done • Cooling down now DKsol ready NB: only 4 days from ISIS startup! DSA Accessible! 11/2/09 MLI sheets on US end: need Beam shield removal! (see M.C. talk for further details) MICE VC 12/2/2009

  4. Floor levelling • floor DS of Q9 is not sufficiently flat • unevenness up to 2cm reported (T. Hayler) • a complete survey + levelling of the area is needed prior to laying down the floor aluminium plate • this (unfortunately) requires TOF1/KL to be temporarily moved • TOF1/KL planned to be back on time for the next Data Taking • Complete plan for un-cabling/move has been discussed with detector responsibles (M.Bonesini/L.Tortora) • Experts from Milan/Rome on their way (18/2) to assist with operations (in particular KL horizontalisation) • At the moment KL/TOF cables have been properly marked and de-cabled MICE VC 12/2/2009

  5. Two minor issues Small leak noticed on Q7: mirror plates removed & being investigated (Spensley) M. Bonesini requested some PMTs (from TOF0) back to Milan for test/repair. Cosmic Bar to be removed Should be easier now (DSA free access) MICE VC 12/2/2009