1 / 12

Why are we here?

Why are we here?. FPLE is seriously concerned that the upgrades being constructed in the McCamey area are not adequate. Concerns. McCamey Area Plan, as it is currently being implemented, will not meet the existing requirements of 755 MW, much less the 900 MW announced by ERCOT

axel
Download Presentation

Why are we here?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Why are we here? FPLE is seriously concerned that the upgrades being constructed in the McCamey area are not adequate.

  2. Concerns • McCamey Area Plan, as it is currently being implemented, will not meet the existing requirements of 755 MW, much less the 900 MW announced by ERCOT • Findings need to be verified • Generation patterns may result in lower limits • Additional mitigation alternative considerations • Timing • Implementation by ERCOT

  3. Hub and Spoke Implementation

  4. Assumptions • Rio Pecos capacitors in-service • RAPs in the 69 kV system • Big Lake – McCamey 138 @ 149/170/170 • Operations case at 52000 MW load (80%), McCamey area load 144 MW • Outages required for upgrade construction not modeled

  5. AssumptionsRAPs • Shef-Iran 69 kV • Atlt-Humt 69 kV • Odnth-Pegtp 69 kV • Illn-Oznr 69 kV • FtL-Iln 69 kV

  6. Findingsw/o Capacitors Included; RAPs Used

  7. FindingsAll Capacitors Included; RAPs Used

  8. Why is there a difference? • Dispatch outside McCamey was not taken into account when the plan was originally developed • If generating units in the Odessa area are dispatched, a portion of the generation flows through McCamey

  9. Potential Mitigation Alternatives • Accelerate Ft. Lancaster to Friend Ranch 138 kV by an additional 6 months • Install Breakers at North McCamey • Add Tension Monitors in Crucial lines • Implement SPS • Start building 345 kV line • Other

  10. Breaker Addition at McCamey

  11. Maximizing Line Capacity • Limiting lines and tension monitors • Rio Pecos to Crane 138 kV • North McCamey to Big Lake 138 kV • SPS until the 345 kV is completed

  12. McCamey Area Transmission Upgrades 50 MVAR 50 MVAR 25 MVAR 25 MVAR 50 MVAR 25 MVAR 25 MVAR 50 MVAR

More Related