Gulf Coast Construction Users Council Conference

Loading in 2 Seconds...

play fullscreen
1 / 16

Gulf Coast Construction Users Council Conference - PowerPoint PPT Presentation


  • 111 Views
  • Uploaded on

Gulf Coast Construction Users Council Conference. June 24, 2008. Five Key Project Success Factors. Safety Quality Schedule Cost Local, Minority, Women-Owned Initiative. Project Premises. Best-in-class safety, environmental, reliability and cost performance

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Gulf Coast Construction Users Council Conference' - aubrey-phillips


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
five key project success factors
Five Key Project Success Factors
  • Safety
  • Quality
  • Schedule
  • Cost
  • Local, Minority, Women-Owned Initiative
project premises
Project Premises
  • Best-in-class safety, environmental, reliability and cost performance
  • Lower production cost by taking advantage of economies of scale
  • Provide flexibility on product and crude slate
  • Eliminate or reduce current imports and exports of unfinished feed stocks; fill conversion units
  • Leverage existing refinery and logistics infrastructure; third party crude and product terminals
  • Utilizes proven technology
project description
Project Description
  • 325 MBD Heavy/Sour Full-Conversion Crude Unit Expansion
  • 95 MBD 6-Drum Coker
  • 75 MBD Integrated Hydrocracker/Diesel Hydrocracker
  • Naphtha Complex
    • 85 MBD Continuous Reformer
    • 50 MBD C5/C6 Isom Unit
  • 50 MBD Cat Feed Hydrotreater
  • New Sulfur Recovery Unit
  • 146MW Power Generation
project schedule summary
Project Schedule Summary
  • May 2006 Bechtel-Jacobs Joint Venture – Selected as EPC Contractor
  • September 2007 Final Investment Decision - Project Approved
  • August 2008 Design Complete
  • September 2008 Module Delivery Begins
  • September 2010 Commissioning and Startup Complete –
          • Units Online
  • July 2010
  • Construction Complete
project challenges
Project Challenges
  • Skilled Workforce Availability – 5000 to 6000 workers required
  • Material Delivery Timing
  • Labor and Material Cost Escalation
  • Construction in an Operating Facility
  • Traffic/Security
slide10

SETX Industrial / Commercial Workforce Demand 2007-2009

30000

Existing Workforce – approx 12-15,000 workers

25000

20000

15000

10000

5000

0

Jul-08

Jul-09

Oct-07

Apr-08

Oct-08

Apr-09

Oct-09

Jan-08

Jun-08

Jan-09

Jun-09

Feb-08

Mar-08

Feb-09

Mar-09

Aug-07

Sep-07

Nov-07

Dec-07

Aug-08

Sep-08

Nov-08

Dec-08

Aug-09

Sep-09

Nov-09

Dec-09

May-08

May-09

Area Continuing Work

Electricians

Insulator

Laborer

Millwright

Op Engineer

Pipefitter

Plate Welder

Rebar Ironworker

Str Ironworker

Boilermaker

Carpenter

Cement Mason

Pipe Welder

Turnarounds

slide11

Workforce Challenges

  • Lack of Skills
  • Aging Workforce – Baby Boomers
  • Drug Screening / Fitness For Duty
  • Youth Flight from Southeast Texas – Jefferson County
  • High School Dropouts
  • Housing
  • Transportation
workforce development solution options
Workforce Development Solution Options
  • Training programs through partnerships with Texas Workforce Solutions, Lamar State College Port Arthur, City of Port Arthur, BECON
  • Introduced nationally recognized NCCER curriculum training
  • Recruitment from non-traditional sources - military
  • Extensive community outreach
  • Utilization of quality local contractors
  • Training of construction new-comers - high schools
  • Workforce Alliance Initiative
  • BECON Employment Office
  • Recruitment of 1300+ trainees through strategy execution
  • Training of unemployed, under-employed – disengaged workforce
disengaged workforce initiative
Disengaged Workforce Initiative
  • Initiative partners - Motiva PAR, Motiva CEP, CONEX, Digital Workforce Academy, Becon, and Texas Workforce Solutions
  • Pilot started in 3rd Qtr 07
  • Initiative incorporates
    • Assessment Test
    • Life Skills Training
    • Drug Screening – Rehab/Counseling
    • Industrial Skills Training
    • Job Placement
    • Mentorship / Tracking System
disengaged workforce initiative1
Disengaged Workforce Initiative
  • Provides human development and self-confidence in economically challenged communities in Port Arthur.
  • Provide services to address the social and developmental needs of low performing and disadvantaged populations.
  • Build and sustain relationships with the communities with a high percentage of disengaged and disadvantaged populations.
  • Empower these individuals to become participants instead of victims.
recruiting model

Military Candidate

Craftsmen

Contractors

Targeted

Non-Traditional

Groups

Advertisement

Responders

Trainees

Recruiting Model

PROJECT

OPENINGS

EXTERNAL

WEBSITE/HIRING

OFFICE

CANDIDATE

FILTERING

APPLICANT

POOL

CANDIDATE MANAGEMENT SYSTEM

summary
Summary
  • Project will result in the Port Arthur Refinery becoming

the Largest Refinery in the United States

  • First new refinery in the U.S. in more than 30 years
  • Some interesting facts on the project:
          • Drive more than 50,000 piles
          • Pour over 260,000 cubic yards of concrete (Batch Plant on site)
          • Erect 27,000 tons of structural steel
          • Install over 450 miles of pipe and 1000 miles of cable
          • Install over 725 pumps, 19 compressors, 500 exchangers, and 4 gas turbines