Join us on an inspiring journey as we revitalize Sierra Hall through tenant improvements. From initial sketches to the final reveal, experience the highs and lows of construction. Witness the transformation of an outdated space into a vibrant classroom ready for learning. Each phase of the project is marked by milestones, challenges, and creative solutions—from building our special room to illuminating the ceiling and laying tiles. With every step, we embrace the spirit of innovation and collaboration, proving that some journeys are truly worth the effort.
E N D
The Metamorphosis of Sierra Hall 180 Tenant Improvements by Tenacity Summer 2003
May 26th – Some Things Are Not Meant to Last…
June 1st - So The Journey Begins…
June 9th – Like a Phoenix Rising…
June 13th – We Are Building Our Special Room …
June 18th – So We Light up the Ceiling…
June 25th – And Tape Up the Walls…
July 10th – And Start Our Stairway to Heaven…
July 11th – Measuring Twice and Sawing Once……
July 14th – But It Takes 21 Days to Cure Cement!!
July 25th – So How Do We Get From Here to There….
July 26th – …In Only 28 More Days?
August 6th – When Suddenly From Within the Room….
August 6th – There Emerges a Form…
August 8th – As The Pace Picks Up……
August 8th – Accelerating Daily...
August 9th – Until It Begins……
August 9th – …to Look Like a Classroom!
August 9th – But Wait! We’ve Run Out of Tile....
August 13th – Ahhh! Saved by a Smart Contractor
August 19th – So Maybe We Will Be Ready After all!
Check in the First Day of Class To See…