An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GIF++ implementation Adrian Fabich, Sylvain Girod, EN-MEF-LE Technical meeting with Supplier of Irradiator, 3rd October 2013

  2. Contents Gamma Irradiation Facility GIF++ • Layout • Technical infrastructure • Operation • Radiation protection • Safety A. Fabich, EN-MEF-LE

  3. The present GIF in the West Area • Present GIF installed in former West Area • Since 2004 secondary (muon) beam de-commissioned • Since then only of limited use for physics • Limited photon yield (137Cs, 650 GBq installed in `90s) • Limited space for increasing number of users • GIF will be decommissioned with the new GIF++ being operational. West Area A. Fabich, EN-MEF-LE

  4. GIF++ location in EHN1 (North Area) H2 beam line GIF++ EHN 1 H4 beam line H6 beam line H8 beam line West Area A. Fabich, EN-MEF-LE

  5. https://edms.cern.ch/nav/SMTI137:ST0428786 A. Fabich, EN-MEF-LE

  6. GIF++ layout (1) PPX (only emergency) dump Irradiation area dump secondary beam PPG gas mixing zone Preparation zone MAD cable trays to control room PPE (entrance) A. Fabich, EN-MEF-LE

  7. GIF++ layout (2) cut view at 2m height shielding PPX shielding shielding shielding g-field 1 g-field 2 ±37° secondary beam ±37° shielding PPG shielding preparation zone gas mixing zone PPE A. Fabich, EN-MEF-LE

  8. Large material access A. Fabich, EN-MEF-LE

  9. Irradiation field (1) A. Fabich, EN-MEF-LE

  10. Irradiation field (2) A. Fabich, EN-MEF-LE

  11. Secondary muon beam From T2 target 99% of beam are within 10 cm x 10 cm, remainder spread over 1 m2 • Main user mode:couple of periods per year with each about two weeks duration • Parasitic mode with muons: as much as possible (based on experience from previous years, one can expect parasitic muon beams for about 30-50% of the beam time, equivalent to about 2-4 months/year). • Few periods per year of approximately two weeks duration in which a beam pipe is installed within the facility and electron beam is taken by CMS ECAL downstream from GIF++ A. Fabich, EN-MEF-LE

  12. General infrastructure • Electricity: 50 kW • light (+emergency) • Ethernet • cabling, cable trays • demineralised water • NO cryogenics • Beam equipment • Beam instrumentation • Gases • Neutral and mixtures (containing flammable gases) • 15 gas supplies from the gas hut (build. 909) • 10 patch panels in bunker/preparation zone • Each for 4 neutral and 4 hazardous gases • Cooling and ventilation • Optional • Supply lines should mainly be installed in the raised floor. Measurements: autumn 2012 – spring 2013 (courtesy: R. Guida) A. Fabich, EN-MEF-LE

  13. FalseFloor: permanent supplies • 40 cm freeheight • Reducingthesourceheight to 2 meter Cable Trays Source Ground - Trigger Dennis Haasler Same concept in preparationarea A. Fabich, EN-MEF-LE

  14. A. Fabich, EN-MEF-LE

  15. Personnel and Material Access • PPG, Roof: If opened, patrol lost • PPE & Turnstile: Access rights of people checked, key released and people counted • PPE2: Key that was taken at turnstile has to be used in key access mode (patrol not lost) • MAD: access for material up to PC size Personal Protection Exit Personal Protection Gate Small material access Pre Zone Personal Protection Entry PPE & Turnstile A. Fabich, EN-MEF-LE

  16. GIF++ control room • HNA 487 GIF++ A. Fabich, EN-MEF-LE

  17. Cables irradiator – using PPE and gallery Irradiator D. Pfeiffer 94 m Cable tray height 2.5 m Roof height 4.8 m Under floor height 0 m HNA 487 A. Fabich, EN-MEF-LE

  18. Cable routing – shortest to control room D. Pfeiffer ca. 70 m Cable tray height 2.5 m Roof height 4.8 m Under floor height 0 m HNA 487 A. Fabich, EN-MEF-LE

  19. Photon yields to muon detectors D. Pfeiffer Downstream beam trigger: average flux 1.8 e4 s^-1 cm^ -2 Average flux 1.0 e5 s^-1 cm^ -2 roof chamber Upstream beam trigger: average flux 5.9 e4 s^-1 cm^ -2 Average flux 5.1 e5 s^-1 cm^ -2 Average flux 1.2 e3 s^-1 cm^ -2 floor chamber fine tracker A. Fabich, EN-MEF-LE

  20. Trapezoid shaped collimator yz D. Pfeiffer Point source Cylindrical source No difference between point and cylindrical source A. Fabich, EN-MEF-LE

  21. Safety responsibility for implementation with SBA (together with CERN expert groups) • Radiation shielding • Flammable gas detection and ODH (in bunker) • Fire detection • Access system/personnel protection • Interlock(s), also with irradiator • Gas zone: ATEX conform (PH) A. Fabich, EN-MEF-LE

  22. GIF++ irradiation zone The irradiation zone hosting the irradiator • is a controlled area (PPE154). • inside a supervised area (EHN1). • No risk of activation due to low intensities of secondary beam • Presence of high intensity photon source requires additional precautions due to the prompt radiation levels: • Extended shielding • Access system • Entrance chicanes A. Fabich, EN-MEF-LE

  23. Radiation levels • Keeping lateral exterior limit well below 3 mSv/h • At least 80 cm concrete • Accordingly adapted chicanes • Roof (no stay area) shielding adjusted for < 15 mSv/h • Final design based on these conceptual shielding studies horizontal cut at source height ( 2m) 160 cm A. Fabich, EN-MEF-LE

  24. Radiation shielding Vertical cut view • Shielding blocks • Double layer closing the block joints • Roof gaps closed with dedicated iron beams • Chicanes for entrances max. 15 mSv/h 160 cm max. 3 mSv/h g-field 2 g-field 1 max. 3 mSv/h Top cut view A. Fabich, EN-MEF-LE

  25. Radiation protection • RP monitoring • Inside the irradiation area • Monitoring of the source operation • Dedicated RP monitoring • 2 redundant ionization chambers connected to RAMSES • Veto to the source operation • In the surrounding EHN1 area • Monitoring by existing beam monitoring (EHN1 standard) Access system • EHN1 standard • Access safety elements compliant with SIL3 • Single Access System (SAS) for counting persons in the area. A. Fabich, EN-MEF-LE

  26. Operational controls • Users’ interface: CESAR • For personnel access and beam control Standard HW/SW integration into SBA controls environment • Access controls • Beam controls • Safety elements • Irradiator provided with its own console. Only link to SBA controls via veto line and status logging. A. Fabich, EN-MEF-LE

  27. Safety conditions foractive irradiator • Exclude direct exposure to g-source • Source out of parking position only possible if • GIF++ access chain is CLOSED • AND (protecting in upstream zone) • Upstream beam dump is IN-BEAM • OR • PPE144 is CLOSED (no access) • AND (protecting in downstream zone) • Downstream beam dump is IN-BEAM • OR • PPE164 is CLOSED (no access) • AND (no alarms) • No fire • No power failure • No emergency stop button • Irradiator controls included in industrial delivery. • Veto from CERN safety chain will force source into parking position. downstream dump upstream dump A. Fabich, EN-MEF-LE

  28. Conclusions • 3D model of GIFF++ is available • Require design documents of irradiator+filter system • Approved status • CERN will study the mechanical integration A. Fabich, EN-MEF-LE