New Medical Facility Building

New Medical Facility Building. By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 494 - Senior Design II. introduction. Our senior project involved completing the development of a theoretical medical building.

aronald
Download Presentation

New Medical Facility Building

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Medical Facility Building By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET 494 - Senior Design II

  2. introduction • Our senior project involved completing the development of a theoretical medical building. • We have completed the working drawings using AutoCAD. • Completed a project schedule using Primavera software. • Determined the building and fire codes. • Determined the site location. • Conducted an elevation survey of the site. • Made a quantity take-off, also known as an estimate.

  3. Working Drawings

  4. WORKING DRAWINGS

  5. WORKING DRAWINGS

  6. Working drawings

  7. Working drawings

  8. Working drawings

  9. WORKING DRAWINGS

  10. Exterior finishes • Roof • “S” tile roof • Wall Finish • Stucco (Decorative wall finish) • Owner will select color • Trim Pieces • 2x8 Fascia • 2x2 Window Trim • Owner will select color

  11. Project schedule • We used the Primavera software in order to create a bar chart. • It is basically a flowchart of each task needed to complete this building.

  12. Building codes • The building codes come from the Hammond Zoning Ordinance booklet. • Part 1: Principles and Objectives • Section 1.3 - Commercial • 1.306 • Part 3: Schedule of District Regulations Adopted • Section 3.8 – C-1 Commercial District • 3.805 • 3.806 • 3.807 • Part 5: Off-Street Parking and Loading Requirements • Section 5.3 – Commercial • 5.301 • Section 5.6 – Off-Street Loading Requirements • 5.601

  13. Fire codes • The fire codes came from the NFPA 101 Life Safety Code booklet. • Chapter 26: New Building Occupancies • Section 26-1: General Requirements • 26-1.7 • Section 26-2: Means of Egress Requirements • 26-2.1.1 • 26-2.3.2 • 26-2.4 • 26-2.6 • 26-2.8 • Section 26-3: Protection • 26-3.3.1 • 26-3.5

  14. Location • The location is on Professional Plaza • Near downtown Hammond and I-12 interstate • Two adjacent lots • 0.5 acres for $99,000 • 0.75 acres for $125,000 • Total lot size and price • 1.25 acres • $224,000

  15. Elevation survey of location A survey was taken of the location using elevation points. These points are on a 40’ grid pattern across the whole property.

  16. Building materials Estimate • Preliminary estimate cost: $261,580 - $297,250 • $110 - $125 per square foot • Actual Estimate: $284,460.87

  17. Building materials Estimate

  18. Timeline/Deliverables Last Semester This Semester

  19. ANY QUESTIONS?