Coupling Coil Status S. Gourlay August 1, 2012 PowerPoint Presentation
Download Presentation
Coupling Coil Status S. Gourlay August 1, 2012

Loading in 2 Seconds...

play fullscreen
1 / 3

Coupling Coil Status S. Gourlay August 1, 2012 - PowerPoint PPT Presentation


  • 131 Views
  • Uploaded on

Coupling Coil Status S. Gourlay August 1, 2012. Coupling Coil Test Prep. Cooling tube welding Pressure test Horizontal and vertical milling operations Lead, Quench Protection mounts Coil vacuum epoxy impregnation Gap between cover plate and coil Seal gap (no leaks!)

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Coupling Coil Status S. Gourlay August 1, 2012' - ardice


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Coupling Coil Status

S. Gourlay

August 1, 2012

coupling coil test prep
Coupling Coil Test Prep
  • Cooling tube welding
    • Pressure test
  • Horizontal and vertical milling operations
    • Lead, Quench Protection mounts
  • Coil vacuum epoxy impregnation
    • Gap between cover plate and coil
    • Seal gap (no leaks!)
  • Design/fab holding fixture for potting
  • Manufacture QP and lead support parts
  • Install temp sensors, strain gauges
coupling coil status activities
Coupling Coil Status/Activities
  • Pressure test complete
    • Documentation in progress
  • QP hardware installed
  • Thermal test with fixture complete
  • Should start potting today
    • Out by tomorrow
  • Install strain gauges (six) in strategic areas
  • Assemble lead stabilizers
  • Shipping crate will arrive this week