CONSTRUCTION MANAGERS MANUAL. Nabil Fahoum February 2013. Construction Manager’s Manual. 1000 Administrative 3000 Procurement 4000 Engineering 5000 Construction 6000 Quality Assurance 7000 Program Controls. Program Management Procedures.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Nabil Fahoum February 2013' - aphrodite-charles


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

CONSTRUCTION MANAGERS MANUAL

Nabil Fahoum February 2013

program management procedures

1000 Administrative

3000 Procurement

4000 Engineering

5000 Construction

6000 Quality Assurance

7000 Program Controls

Program Management Procedures
quality assurance qa quality control qc
Quality Assurance (QA)Quality Control (QC)
  • The Contractor is responsible for the quality control of their Work.
  • The CM verifies compliance with QA/QC requirements to ensure that all components of the Contractor’s work conform to the plans, specifications, applicable standards and other requirements of the contract.

5

daily activity report daily report field book
Daily Activity Report, Daily Report & Field Book

Daily Activity Report

Form A-1B

Daily Report

Form A-1

Field Book

6

punch list
Punch List

A list prepared by the CM of outstanding work items and/or work items not complete in conformance with the contract.

Form A-45 PL Punch List Template.

7

project walkthroughs
Project Walkthroughs

Pre-Final Walkthrough

  • Walkthrough attendees:
  • CM
  • Tollway Maintenance
  • Tollway PM
  • Tollway GEC
  • Tollway User Departments
  • Contractor (Optional)
  • General Project Overview
  • Prior to Substantial Completion
  • Punch List Available to Attendees
  • Contract vs. Extra Work Items

8

project walkthroughs1
Project Walkthroughs

Final Walkthrough

Completed Punch List

9

final punch list
Final Punch List

Punch List Items Which Are Closed

Documentation Provided To Indicate Why No Further Action Was Required By Contractor

Physically

Completed

Form A-45 PL Punch List Template.

10

reference documentation

Tollway Website Documents

Reference Documentation

http://www.illinoistollway.com/doing-business/construction-engineering

questions
Questions ?