Summary • Overview of EE • Scope of project in TD • Team members • Project status • List of tasks to completion in outline • List of tasks in detail • Effort required: PPESP request, mid-term review, current plan • Effort for each task, by year, and by team member • Summary comments 2002
The CMS calorimeter BARREL The 53 degree crack LOCATION OF HE Preshower ENDCAP 2002
HE EE SE 2002
Supercrystal parts Arrangement of a few Super Crystal Parts 2002
SC - Concept Super Crystal with Positional Spacer 2002
TD Project scope - included • Supercrystals • Manufacture of 50% of full supercrystals (alveolars and crystals supplied by others) • Handover of parts and expertise to others for the other 50% • Major mechanics • Design of backplate, ring flange, positional spacers, environmental shield, moderators, other internal components • Procurement and supply of above • Electronics • Participation in ECAL joint VFE design • Customisation to suit EE. Design & supply housings, cooling, etc. • Project co-ordination • Many interfaces to other work areas including assembly & installation • Ensure ECAL is aware of what needs to be done outside our scope 2002
TD project scope - excluded • Supercrystals • Supply of crystals (ETH); alveolars (Russia); VPTs (PPD) • Electronic test eqpt for regional centre (PPD) • Partial supercrystals (Russia) • Major mechanics • Some support with design and analysis from Russia • Dee assembly (IC/CERN) • Electronics • Support with completion of HV design from PPD • VFE cards (ECAL) • Other areas • Slow controls (ECAL); services outside EE (ECAL) • Installation (ECAL) • Radiation testing and TIS clearance (PPD) 2002
Team members in TD • Justin Greenhalgh • Management of TD resources and activities in other areas • Thermal and structural performance oversight • Brian Smith • Supercrystals • John Hill • Major mechanics, mechanical integration issues • Tony Lodge • Electronics • Others - Design and technician support 2002
Project status - overview • Supercrystals • Design OK, parts mostly on order, gearing up for production in summer 2003 but subject to confirmation of external funding • Major mechanics • Design passed review, production drawings in hand, due to carry out tender action spring/summer 2003 • Electronics • CMS critical path item • EE working as part of ECAL effort to make a joint design for the VFE “mechatronics” • tests hoped in test beam summer 2003, production electronics required March 2005 2002
Project status - supercrystals • Successful review November 2000 • Mechanical components tendered, companies shortlisted, contract to be placed before end 2002 • Production facility about 50% kitted out • Production due to start summer 2003 • BUT • crystals still not ordered, • HV cards design still not fixed, • other details to finalise 2002
Project status - major mechanics • EDR succesful in Sept 2002 • Production drawings being made • Ring flange almost complete • Backplate in hand • Pos spacers next • Agreed to freeze backplate and ring flange and treat those as design constraints for the mechatronics 2002
Project status - Electronics • Strategy is to work with the ECAL community to ensure that the agreed design is EE-compatible • Two promising potential designs for housing the electronics • Fundamental principle is that it must be possible to install and test the cooling before the electronics is fitted • After many delays on the FPPA chip design, a second, more promising, design is now being pursued in parallel (using 0.25 micron technology) • TD staff member Tony Lodge is now working about 50% at CERN, the arrangements being under continuous review • CERN mechanical designer is due to start work on EE-specific design issues 2002
Outline list of tasks from now to completion in TD • procure mechanical parts for supercrystals, • produce about 300 supercrystals, transfer expertise to other regional centres • complete design of major mechanical items, procure them • participate in completion of ECAL “mechatronics” design • (level of input negotiable) • complete EE-specific mechatronics design • (level of input depends upon how applicable the ECAL design is to EE) • See Project Specification paper - latest version was superseded by developments in the mechatronics area. 2002
Tasks from now to completion - supercrystals • Oversee production of SC mechanics • Complete preparation of regional centre at RAL • Resolve remaining details: temperature sensors, support bracket for fibres. • Resolve HV card and umbilical design, procure. 2002
Tasks from now to completion - major mechanics • Completion of production drawings for backplate, ring flange, positional spacers, moderators • Oversee completion of drawings for environmental shield by Russian colleagues • Tender action - documents, company visits, etc • Oversee manufacture • Interface with assembly and installation teams 2002
Tasks from now to completion - mechatronics • Work with ECAL to arrive at a mechatronics design which can be applied (perhaps in two variants) to the barrel and the endcaps. • Currently effort is being used to look at the services external to EE, because they influence the design inside. • Future: • Install the “new” electronics in the test bench “E zero prime” model. Includes making any required mods to suit EE • Test beam runs to establish noise performance • Fix noise problems • Make engineering model of final design, produce drawings • Oversee production 2002
Effort requirements - midterm review vs current situation 2002
Summary • The scope of project includes making significant parts but we (TD/PPD) cannot afford to assemble or install the Dees. • There have been significant delays - to the VFE electronics and the crystal delivery, eg. • A major exercise was undertaken in early 2001 to fully re-cost activities to completion. • Some work was passed to PPD and a significant increase in TD resources was sought at the mid-term review. • Since then there have been yet further delays but we have • Minimised effort usage where design work was blocked • Sought to use “ECAL-wide” resources as far as possible, by collaborating on the joint mechatronics design (just starting to pay off) • replanned to live within the mid-term-review effort budget 2002