780 likes | 810 Views
Explore the successful road protection project implemented on Route 248 at Chenunda Creek, showcasing fluvial geomorphology analysis, hydraulic engineering, and construction oversight. Witness the transformation and stabilization of the streambed through innovative methods and vegetation. Experience the before-and-after journey captured in captivating photos.
E N D
NYS-DOT REGION 6ROAD PROTECTION FOR ROUTE 248CHENUNDA CREEK,SOUTH OF WELLSVILLE, NY.CONSTRUCTED AS A HANDS-ON WORKSHOP SEPTEMBER 2006
POC: Sandra Rapp, New York State DOT work 607-324- 8527 srapp@dot.state.ny.us RRD/Derrick Tasks: * Performed a fluvial geomorphology analysis * Developed alternative designs, developed the final design * Reviewed Plans & Specs, many discussions with DOT hydraulic engineers!! * Provided construction oversight & taught a hands-on workshop to 88 of NYS DOT’s finest
Stream Project Functions: Fully functioning both hydraulically & environmentally. Multiple protection redundancy. LPSTP provides direct armor protection. Bendway Weirs Locked Logs, & J-Hook move scour & thalweg away from attacked bank, with velocities reduced on outer bank. Vegetation roughness reduces near-bank flow velocities & provides a functioning riparian corridor. Roots strengthen bank & bind soil. Grade Control structure stops upstream headcut migration.
Planview-Looking US at Reach 1 FROM DAN SABOL, NYS-DOT
Chenunda Creek @ Rt. 248. Pre-project condition Mar 22, 2006. Looking US at the eroding bend. Pix from Joe Galati
Chenunda Creek @ Rt. 248. Pre-project conditions 7/25/2006. Looking DS at the eroding left bank Pix by Derrick
Construction 9/19/2006. Looking US. Hoe placing big stone (DOT heavy) in US keyway Pix by Derrick
Construction 9/20/2006. Looking DS at angle of key to stream flow Pix by Derrick Flow Key angle
STREAM BED & BANK STABILIZATION METHODS USED • Choked & vegetated LPSTP with vegetated keys, & curved US & DS keys • J-Hook Vane • Short Bendway Weirs • Pre-dug & Over-dug pool with Locked Logs and Instant Shade • Joint Plantings, Live Siltation, Pole Plantings, Slit Trench Plantings, Instant Shade, RPM Trees & Shrubs • Hydraulic Cover Stones • Traffic Control Stones (Upstream) • Thalweg Control Stones • Engineered Rocked Riffle Grade Control Structure (all stones in compression) with an integrated fish ladder on the downstream face
Construction 9/20/2006. A dump truck load level full of Sandbar & Streamco Willow, & Ruby Redosier dogwood, (1,500 total) from the NRCS Plant Material Center, Big Flats, NY. Now that is a truckload!!! Pix by Derrick
Construction 9/21/2006. Looking US at trench stone & bundled willows Pix by Derrick
Construction 9/21/2006. Looking US @ toe-down stone toe & short Bendway Weir (2 people standing on Weir) Pix by Sandra Rapp
Construction 9/20/2006. Looking US @ short Bendway Weir & pre-dug thalweg Pix by Martin Vandergrinten NRCS Plant Material Center
Construction 9/19/2006. Digging a key into bank. Some willow poles in place Pix by Derrick
Construction 9/19/2006. Looking at key Pix by Derrick
Construction 9/21/2006. Workshop participants adding more veg to soil-choked key Pix by Derrick
Construction 9/21/2006. Looking DS, digging the J-Hook Vane pool Pix by Derrick
Construction 9/2006. Looking US at Locked Logs in J-Hook pool. Pix by Martin Vandergrinten NRCS Plant Material Center
Construction 9/2006. Looking US at Locked Logs & Instant Shade Pix by Martin Vandergrinten NRCS Plant Material Center
Construction 9/21/2006. The Root Production Method (RPM) Plants Pix by Derrick
Post Construction 9/30/2006. Looking US. All plants, including the RPM plants in place Pix by Joe Galati-NYS DEC
THE PROJECT IS COMPLETE, LET’S ROLL A LITTLE WATER THROUGH IT
HIGH FLOW TWO MONTHS AFTER CONSTRUCTIONPhotos by Sandra Rapp, NYS-DOT REGION 6 NOVEMBER 19, 2006
High water 11/19/2006. Looking DS at project bend, note thalweg in center of the channel Pix by Sandra Rapp US key here
WINTER WONDERLAND FOUR MONTHS AFTER CONSTRUCTIONJANUARY 9, 2007
Post Construction 1/9/2007. Looking US at project bend. Note calm water near bank Pix by Derrick
. LOW LOW LOW FLOW 13 MONTHS AFTER CONSTRUCTIONPhotos by Dave Derrick OCTOBER 15, 2007
13 Months LATER-low flow. Veg in key is robust. Pix by Derrick 10/15/2007
13 Months LATER-low flow. Looking DS, upper bank veg is robust. Pix by Derrick 10/15/2007
Looking DS @ project bend, flow in diversion channel to right Pix by Earl Flint DOT - 2/6/2008
Looking DS @ into project bend Pix by Nancy Root - 2/6/2008
Looking US. Flow over J-Hook near tip of arrow Pix by Nancy Root - 2/6/2008
Looking US @ project bend. Everything looks in order. Pix by Nancy Root - 2/6/2008
Looking US @ DS end of project bend. Good transition into DS bend Pix by Earl Flint DOT - 2/6/2008
22 MONTHS AFTER CONSTRUCTIONPhotos by Joe Galati NYSDEC JULY 10, 2008
Looking US @ the US section of the project & the TCS section of the project 22 MONTHS AFTERCONSTRUCTION-CHENUNDA CR.-PIX BY JOE GALATI 7-10-2008
Looking US @ a well vegetated stable bank 22 months after installation 22 MONTHS AFTERCONSTRUCTION-CHENUNDA CR.-PIX BY JOE GALATI 7-10-2008
Looking US @ J-hook, veg growth & stable bank 22 months after installation 22 MONTHS AFTERCONSTRUCTION-CHENUNDA CR.-PIX BY JOE GALATI 7-10-2008
Looking US @ veg & stable bank 22 months after installation. 22 MONTHS AFTERCONSTRUCTION-CHENUNDA CR.-PIX BY JOE GALATI 7-10-2008
From the DS end of the project looking US 22 months after installation 22 MONTHS AFTERCONSTRUCTION-CHENUNDA CR.-PIX BY JOE GALATI 7-10-2008
YEARS AFTER CONSTRUCTIONPhotos by Joe Galati NYS-DEC (retired)AUGUST 25, 2010
4 YEARS LATER-Looking DS into the upper end of the bend. 4 YEARS LATER-CHENUNDA CR.-PIX BY JOE GALATI 8-25-2010
4 YEARS LATER-Looking @ “J” section of the J-Hook. 4 YEARS LATER-CHENUNDA CR.-PIX BY JOE GALATI 8-25-2010
4 YEARS LATER-Looking US @ the J-Hook & DS pool. 4 YEARS LATER-CHENUNDA CR.-PIX BY JOE GALATI 8-25-2010