1 / 25

LS1 Cabling Progress LS1 Committee (LSC) – 21 June 2013

EDMS 1293605. LS1 Cabling Progress LS1 Committee (LSC) – 21 June 2013. Daniel RICCI on behalf of the Cabling and Optical Fibre Section (EN-EL-CF). Outline. The LS1 challenge for cabling Monitoring of cabling activities & current performance Facing the challenges: where do we stand?

amos-baker
Download Presentation

LS1 Cabling Progress LS1 Committee (LSC) – 21 June 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDMS 1293605 LS1 Cabling ProgressLS1 Committee (LSC) – 21 June 2013 Daniel RICCI on behalf of the Cabling and Optical Fibre Section (EN-EL-CF)

  2. Outline • The LS1 challenge for cabling • Monitoring of cabling activities & current performance • Facing the challenges: where do we stand? • Conclusions Cabling = copper(ctrl & DC) cables AND optical fibres D. RICCI – CERN, LSC meeting – EDMS 1293605

  3. The LS1 challenge:the important numbers • 37 main projects to carry on + day-by-day installation works (Someexamples: R2E, LHC cabling campaigns, WCC hose consolidation, SPS campaigns & irradiated cables TS1+, new SPS fibre infrastructure (BI & others), PSS, LINAC4 & Meyrin campaigns, Computer Centre extension B513, LHC-Experiments fibreupgrade) • Overallestimated budget ~12 MCHF • ~1000 km of copper and opticalcablesbeinginstalledduring LS1 Moreover, activitiesalsoinclude • Managing CERN-wide optical fibreinfrastructure (3,000 km installed optical cables) • Qualification, procurement and standardisation of cabling and optical fibre components (3.5 MCHF/year) • Managing cable park (4200 drums) and cable tray infrastructure (350 km) • Monitor cable aging and put in action the replacement campaigns (~1MCHF/machine point) D. RICCI – CERN, LSC meeting – EDMS 1293605

  4. LS1 challenge:planning and resources Example CF planning (LHC only) • Very « dense » planning • Must copewith machine constraints/priorities • Delay on one activitycanprovoke « domino » effect • ~35 people in CF plus ~100 contractor people • Challenging supervision, training and knowledgetransfer of new workingmethod LS1 New cabling R2E Consolid. D. RICCI – CERN, LSC meeting – EDMS 1293605

  5. The cablingstrategy(in a snapshot)see LSC presentation 15/3/2013 • 1) Enhanced section structure • 2) Anticipatequalification and procurement of material PROJ 1 Variousworks TE/ABT Campaign Booster PROJ 2 LIU Campaign SPS-BA1 PROJ n Variousworks BE/BI + fibres… CampaignLHC-Point1 • 3) Optimizework organisation and resource distribution by working by geographicalcampaigns • 4) Boost training & projectpreparationwithcontractors • 5) Project progress and schedule monitoring Simulation D. RICCI – CERN, LSC meeting – EDMS 1293605

  6. LS1 progress monitoring • Methoddeveloped in agreement with the management requestto be able to follow activity progress in ‘real-time’ • Objectives • Help Project Managers to manage parallel projects and workload • Warn timely on activity delay or anticipation • Prevent resource bottlenecks • Be able to provide detailed status reporting (e.g. for each geographical campaign) • Be a test-bench for LS2 • Costs • Dedicated FTEs to implement/following (1.5 FTEs for 2013) • Enforce new work style with contractors • More commitment (mainly time) requested from the Project Managers D. RICCI – CERN, LSC meeting – EDMS 1293605

  7. Monitoring method • Challenge: CF field-activities are composite and of different nature, depending on the project • Project preparation, ordering of material, documentation and other administrative activitiesdone by CF are not included Example of field-activities for coppercables De-cabling Mechanics cabletrays/racks Reworks Cablingcampaign (core) Cablepulling (60%) Connectors (30%) Test (10%) • variable • variable • variable • variable De-cabling Cablingcampaign (core) Reworks Reworks Cablepulling (60%) Connectors (30%) Test (10%) De-cabling Mechanics cabletrays/racks Cablingcampaign (core) Cablepulling (50%) Connectors (40%) Test (10%) • t3 • t1 • time • t2 D. RICCI – CERN, LSC meeting – EDMS 1293605

  8. Monitoring method • Heterogeneous monitoring toolsapply • Quick implementation to bereadyat the beginning of LS1 campaigns De-cabling (variable) Mechanics cabletrays/racks (variable) Reworks Cablingcampaign (core) Cablepulling (60%) Connectors (30%) Test (10%) • Cabledatabase (Cablothèque) • Fillingdata is part of the contractor’sobligations • Sotware data extraction (EDMS 1245912) • Weekly check fromeachconcerned Project Managers • Very important to get as accurate feedback as possible • Weeklyfeedback fromContractors • Fillingfollow-up sheets (for detailed cross checking) • Drawback: contractorsclaimingthisis not included in the contract and produce more work D. RICCI – CERN, LSC meeting – EDMS 1293605

  9. Monitoring: forecast • Forecastcurveisextractedfromscheduledactivities (MS-project planning) • Detailed summary of all activities of CF section • Updated weekly End of LS1 50% LS1 Beginning of LS1 D. RICCI – CERN, LSC meeting – EDMS 1293605

  10. Monitoring: forecast Simple rules • Each activity • Starting date  0% • Ending date  100% • Linear interpolation • Activity plans weekly updated • with the exception of the campaign already started D. RICCI – CERN, LSC meeting – EDMS 1293605

  11. Monitoring: forecast Simple rules • Each activity • Starting date  0% • Ending date  100% • Linear interpolation • Activity plans weekly updated • with the exception of the campaign already started D. RICCI – CERN, LSC meeting – EDMS 1293605

  12. Monitoring: progress • Progress curveisextractedfromheterogeneous monitoring tools • Very large stream of information to process Computed % of completion Input from contractors Phase 2 Phase 1 Phase N Phase 5 Phase 4 Phase 3 De-cabling Mechanics cabletrays/racks Reworks Cablingcampaign (core) D. RICCI – CERN, LSC meeting – EDMS 1293605 Cablepulling (60%) Connectors (30%) Test (10%)

  13. Monitoring plots D. RICCI – CERN, LSC meeting – EDMS 1293605

  14. Monitoring plots D. RICCI – CERN, LSC meeting – EDMS 1293605

  15. Monitoring plots D. RICCI – CERN, LSC meeting – EDMS 1293605

  16. Current performance Dashboard: http://lhcdashboard.web.cern.ch/lhcdashboard/ls1/ D. RICCI – CERN, LSC meeting – EDMS 1293605

  17. Monitoring methodimprovement Development of a new monitoring procedure based directly on GESMAR • All the information concerning the progress of the work is directly filled by contractors • Data extraction from GESMAR + elaboration/plotting by CF (to be included in GESMAR in the future) • First software implementation released to be taken over now by our contractors De-cabling (variable) Mechanics cabletrays/racks (variable) Reworks Cablingcampaign (core) Cablepulling (60%) Connectors (30%) Test (10%) Cablothèque (module of GESMAR) Integrationinto GESMAR Manythanks to Serge Oliger! (EN-EL-CD) D. RICCI – CERN, LSC meeting – EDMS 1293605

  18. Facing the challenges: where do we stand? • The technical challenges • CF working method is solid concerning cabling installations • Procurement of material: process well known, largely anticipated  not particular issues so far. • Recrudescence of theftsis worrisome. Consider securing more the sites! • Preparation/execution of projects and cabling campaigns is optimised • However, still very dependent on users timely feedback on final cabling requests! • Contract orders are issued timely and budget is in line with expectations • Coping with more resource needs than initially foreseen for safety and administrative tasks • Procurement and logistics for RP-related material (personal protection equipment, baskets, waste bags/bins, etc.) • Thousands of pieces • Find budget (~500 kCHF), manage purchases, deliveries, storage places, consumption levels, etc. • ALARA preparation and follow up • Lot of preparation: multiple iterations required with RP+contractors to achieve acceptable analysis • Workload on RSSOs is much more than estimated D. RICCI – CERN, LSC meeting – EDMS 1293605

  19. Facing the challenges: where do we stand? • The additional staff • As foreseen, the section management/coordination levels are extremely loaded (even overloaded) • Huge efforts to transfer the know-how to the newcomers • Huge efforts to train the project managers (aim is “autonomy”) • Workload for support functions is demanding taking into account the available manpower and skills  support priority being given to installation activities (e.g. planning, QA, access & safety) • Little and time-limited contingency to recover from (unforeseen) resource loss Manythanks to Fabio Formenti! (TE-HDO) Structure by project cells Support Function Unit with Support Manager D. RICCI – CERN, LSC meeting – EDMS 1293605

  20. Facing the challenges: where do we stand? • Challenge for contractors • Four installation contracts currently operational: • C209 (electrical), C210 (electrical), C202 (fibres), B1213 (WCC) • Contractors are increasing their staff. However, they need to: • be able to constantly find qualified personnel and to train them • cope with CERN planning (peaks and valleys) • cope with radiation rules: no temporary contracts + replace/rotate the personnel achieving the max. allowed dose in radiation areas D. RICCI – CERN, LSC meeting – EDMS 1293605

  21. Facing the challenges: where do we stand? • Challenge from contractors • One of the main electrical contractor is still struggling with their internal organisation and expertise level of their personnel • CERN has limited control on this (“delit de marchandage” always behind the corner!) • CF is currently working on contingency actions • Increasing at maximum the work supervision • Organizing more connector trainings/tests for the contractors • Working on a plan of actions in case of one contractor resigns (this will not be cost free…) • Strongly limited in “contract managers” • Even more overload on section coordination! D. RICCI – CERN, LSC meeting – EDMS 1293605

  22. Facing the challenges: where do we stand? • Planning challenge • Going well so far. Thanks also to joint effort with planning coordinators • Managed so far to have certain “agility” to smooth the curve peaks • Keep high level of attention to avoid “domino” effects • Attention on how to cope with new (unforeseen) projects • Last contingency slot in April 2014 was already filled by R2E-cryo • In case of more new projects, set new activity list with priorities! Manythanksto Katy Foraz’s team! D. RICCI – CERN, LSC meeting – EDMS 1293605

  23. An eyeon the field Flexwell (coax) cables in LHC P4 Replacement of WCC hoses in LHC P8-left D. RICCI – CERN, LSC meeting – EDMS 1293605

  24. An eye on the field Optical fibre cabling SPS & LHC CTRL cabling in the PSB D. RICCI – CERN, LSC meeting – EDMS 1293605

  25. Conclusion • 27 CF worksites currently ongoing CERN-wide with 4 main installation contractors • A tool for monitoringthe LS1 progress for CF isworking and availableonline • now developing a new version fully integrated in GESMAR • The working method is proved and work organisation is optimised around geographical campaigns.The forecast schedule is being kept so far • requires a lot of efforts and commitment from CF people! • Main challenges are: the overload of the section work-coordinators, the risks associated to the quality and (especially) the stability of the contractors • cabling activities are under control but still very sensitive to work plan perturbations • It is important to build-up contingency reserve (to cope with unforeseen circumstances) when activities are performed better than in the plan • attention to the new coming projects! Prioritize and schedule wisely… • The success of the LS1 cabling project is a real team effort! • Many thanks to all the CF colleagues which are making possible a smooth LS1! …and thanksfor everyone’s support! D. RICCI – CERN, LSC meeting – EDMS 1293605

More Related