Janet6 Update. Neil Shewry Project Manager. Agenda. Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the future. Background. SuperJanet5: 2006 to 2013. Janet6: Project to replace the UK wide Janet backbone, SuperJanet5.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Janet6 Update' - alyssa-edwards


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
janet6 update

Janet6 Update

Neil Shewry

Project Manager

agenda

Agenda

  • Background
  • Procurement
  • What we’re building
  • How we’re getting on
  • Strategic Research Facilities
  • Plans for the future
background

Background

SuperJanet5: 2006 to 2013

  • Janet6: Project to replace the UK wide Janet backbone, SuperJanet5
procurement

Procurement

  • Fibre infrastructure contract signed: 31st July 2012
                • Scottish & Southern Energy Telecoms (SSET)
                • 4 year framework
                • 10 (+5) year contract
                • £30M
  • Optical transmission contract signed: 6th September 2012
      • Ciena Inc.
      • 7 year framework
      • Order for supply and 5 years support
      • £12.8M
what we re building

What we’re building

  • 5 delivery phases
  • Core
  • 4 Regional
  • RNs connect at multiples of 10G
  • Most are getting an upgrade
what we re building1

What we’re building

I could go into more detail…

…but how good is your eyesight?

what we re building points of presence

What we’re building - Points of Presence

  • Vacating the Verizon Business PoPs
    • Except for small presence in Glasgow and Reading
  • Existing Provider-Neutral PoPs
    • Telehouse North, Telecity Harbour Exchange
    • Telecity Manchester, Scolocate
  • New Provider-Neutral PoPs
    • Telecity Powergate, Telehouse West, Leeds (aql)
  • SSET Core PoPs
    • Bradley Stoke, Erdington, Lowdham, Glasgow
  • SSET Transmission PoPs
    • Multiplex circuits from regional fibres onto the backbone
  • SSET In-Line Amplifier PoPs
    • Single rack, small amplifier shelf
  • RNEPs
what we re building lightpath

What we’re building - Lightpath

  • Increase bandwidth between backbone nodes to 100GE
  • Topology reflects what is currently required
how we re getting on fibre

How we’re getting on – fibre

  • Acceptance of core infrastructure February 2013
  • Acceptance of regional infrastructure March 2013
how we re getting on dwdm equipment

How we’re getting on – DWDM equipment

  • Ciena 6500 platform
  • All kit is in the country
    • 40% on site
    • 60% in staging
  • Deployment began in January
    • Staging
    • Delivery
    • Installation
    • Commissioning
  • Completion end April 2013
how we re getting on ip routing equipment

How we’re getting on – IP routing equipment

  • Upgrade: Juniper T1600 Juniper T4000
  • Professional Services
how we re getting on other stuff

How we’re getting on – other stuff

  • Regional Network Readiness
    • Space & power
    • RNEP router capability
  • Transition Planning
  • Operational Readiness
    • PoP Control
    • Fault Management
    • Network Management
  • Service Management
    • SSET
    • Ciena
  • Decommissioning
strategic research facilities

Strategic Research Facilities

  • Government e-Infrastructure initiative
    • £26m funding to Janet
      • £10m for Janet6 backbone
      • £12m for phase 1 (below)
      • £4m for ‘industrial connectivity’
  • Phase 1
    • Met Office, Exeter
    • Norwich Research Park
    • Hinxton Campus, Cambridge
    • (Francis Crick Institute, St Pancras)
plans for the future

Plans for the future

  • LOTS of bandwidth
    • 100Gbit/s x 88 channels = 8.8Tbit/s
    • 400Gbit/s?
  • Strategic Research Facilities – possible phase 2
  • Thames Valley Network
  • South Region (formerly LeNSE)
  • Other regional networks?
  • Individual customers?