This document explores essential techniques in project management, focusing on Network Analysis, particularly the Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT). Developed in the 1950s, CPM emphasizes the balance between project cost and completion time, while PERT addresses uncertainties in activity timings. Useful for various types of projects, these techniques facilitate detailed planning, management, and control. Additionally, it covers Gantt charts, critical path determination, slack time, dependencies, and other vital project management terms.

alvin-solis
Download Presentation

Effective Project Management Approaches: CPM and PERT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROJECT MANAGEMENTApproaches By- Rahul Jain

  2. Plan your work first…..then work your plan

  3. Network analysis Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project: “A project is a temporary Endeavour undertaken to create a "unique" product or service”

  4. History • Developed in 1950’s • CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?) PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks).

  5. CPM - Critical Path Method • Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction • Single estimate of activity time • Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.

  6. PERT - Project Evaluation & Review Techniques • Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction • Multiple time estimates • Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

  7. Gantt chart Originated by H.L.Gantt in 1918 Advantages - Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place. • Limitations • Do not clearly indicate details regarding the progress of activities • Do not give a clear indication of interrelation ship between the separate activities

  8. Some keyterms • There are several key terms • Critical Path: The longest time path through the task network. The series of tasks (or even a single task) that dictates the calculated finish date of the project (That is, when the last task in the critical path is completed, the project is completed) The "longest" path (in terms of time) to the completion of a project. If shortened, it would shorten the time it takes to complete the project. Activities off the critical path would not affect completion time even if they were done more quickly. • Slack Time: The amount of time a task can be delayed before the project finish date is delayed. Total slack can be positive or negative. If total slack is a positive it indicates the amount of time that the task can be delayed without delaying the project finish date. If negative, it indicates the amount of time that must be saved so that the project finish date is not delayed. Total Slack = Latest Start - Earliest Start. By default and by definition, a task with 0 slack is considered a critical task. If a critical task is delayed, the project finish date is also delayed. (Also known as float time )

  9. Definitions • Yet more key PM terms: • Dependencies: Links between project tasks. There are 3 types of dependencies: • Causal, where 1 task must be completed before another can begin (have to bake bread before you can make a sandwich) • critical path schedules are based only on causal dependencies • Resource, where a task is limited by availability of resources (more bread can be baked by 2 bakers, but only 1 is available) • Discretionary, optional task sequence preferences that, though not required, may reflect organizational preferences • Milestone: A significant task which represents a key accomplishment within the project. Typically requires special attention and control.

  10. Definitions • More key PM terms: • Crashing: Shifting resources to reduce slack time so the critical path is as short as possible. Always raises project costs and is typically disruptive – a project should be crashed with caution.

  11. Project Management Definitions • Yet more key PM terms: • Duration: The time it takes for an activity to be completed, given the planned amount of material, labor and equipment. • Effort: The amount (not duration) of work required to complete a task. Duration may decrease by adding resources but the effort required will remain the same. • Scope: A specific definition of what the project does and does not entail. Critical to managing expectations of customers and workers alike.

  12. Planting trees with flowers and edging around them – tasks required to complete this project: Mark utilities Dig Holes Buy trees Buy flowers Plant trees Plant flowers Buy edging Install edging This list does not reflect time or money This list does not reflect task relationships This list is a simple sequence of logical events This list does not provide an easy project “snapshot” Hard to see conflicts An Example of a Logical SequenceMaking a simple list of tasks

  13. An Example of a Logical SequenceVisual - Using a PERT Chart (Network Diagram) Planting trees with flowers and edging around them Visual – task relationships are clear – good snapshot Created using RF Flow or Visio

  14. An Example of a Logical SequenceTabular – including time and cost data NOTE: Shaded areas are concurrent tasks that are completed along the timeline- they contribute to overall cost but not overall duration

  15. CPM/PERT These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique. • Overtime CPM and PERT became one technique • ADVANTAGES: • Precedence relationships • large projects • more efficient

  16. The Project Network • Use of nodes and arrows Arrows An arrow leads from tail to head directionally • Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish.

  17. Activity on Node - A completion of an activity is represented by a node Activity on Arrow - An arrow represents a task, while a node is the completion of a task - Arrows represent order of events Activity on Node & Activity on Arrow

  18. Activity Slack Each event has two important times associated with it : • Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times • Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project. • Difference between the latest time and the earliest time of an event is the slack time for that event Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion

  19. Critical Path • Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack • Longest path through a network • minimum project completion time

  20. Benefits of CPM/PERT • Useful at many stages of project management • Mathematically simple • Give critical path and slack time • Provide project documentation • Useful in monitoring costs

  21. Questions Answered by CPM & PERT • Completion date? • On Schedule? • Within Budget? • Critical Activities? • How can the project be finished early at the least cost?

  22. example Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?

  23. For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".

  24. Before starting any of the above activity, the questions asked would be • "What activities must be finished before this activity can start" • could we complete this project in 30 weeks? • could we complete this project in 2 weeks? One answer could be, if we first do activity 1, then activity 2, then activity 3, ...., then activity 10, then activity 11 and the project would then take the sum of the activity completion times, 30 weeks. “What is the minimum possible time in which we can complete this project ?“

  25. We shall see below how the network analysis diagram/picture we construct helps us to answer this question.

  26. CRITICAL PATH TAKES 24 WEEKS FOR THE COMPLETION OF THE PROJECT

  27. Limitations to CPM/PERT • Clearly defined, independent and stable activities • Specified precedence relationships • Over emphasis on critical paths

  28. Thank you