An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRAINING OF CPT SPRAYINGMANDOR PERAWATAN Oleh : SafrudinWibowo (POD Manager TC PT. BWP)

  2. DEFINISI CPT SPRAYING • CPT spraying adalahpekerjaanpengendaliangulmakimiawidikebunsawit yang mencakup : 1. (C)ircleatauPiringan, 2. (P)athatauPasarPikul, dan 3. (T)PH atauTempatPengumpulanHasil • Pekerjaan CPT spraying (gabungan Circle, Path, dan TPH) iniadalahpekerjaan 1 paket yang tidakterpisahkan • Pekerjaaninimenggunakanracuntanaman (herbisida) yang bersifatsistemik

  3. YANG DISEMPROT DI CPT SPRAYING • Tidaksemuapermukaankebunsawit 1 ha disemprotdalampekerjaan CPT Spraying • Selain Circle, Path, dan TPH; tidakdisemprot 1. Gawangan (tidakikutdisemprot) 2. Lalang(tidakikutdisemprot) • Untukitu, harusdicariberapaluasmasing-masing Circle + Path + TPH

  4. YANG DISEMPROT DI CPT SPRAYING • Circle (Piringan) ada 148 piringansesuai SPH • Path (Pasarpikul) adasejumlah 2,18 PP/ha • TPH ada 2 TPH/Ha (Setiap 3 Path = 1 TPH)

  5. MENCARI LUAS SEMPROT CIRCLE • Dalam 1 ha ada 148 pokok = 148 Circle (Piringan) • Cara mencariluas circle (piringan) adalah 1. Mencariluas 1 circle (piringan) 2. SPH X luas 1 circel (piringan) • Rumuslingkaran (luas 1 circle/pokok) = ¶ x r2 atau 22/7 x (Jari-jari x Jari- jari) = 22/7 x (1,5 m x 1,5 m) = 3,14 x 2,25 m2 = 7,07 m2 • Luas total semuacircel (piringan) per ha = SPH x luas 1 circle = 148 pkk/ha x 7,07 m2 = 1.046,57 m2 • 1,5 m

  6. MENCARI LUAS SEMPROT PATH (PP) • Dalam 1 Path (PP) ada 2 baristanaman @ 34 pkksehingga, total pokok/path (PP) adalah = 2 BT x 34 pkk/BT = 68 pkk/path (PP) • Dalam 1 ha ada 148 pkk (SPH = 148 pkk/ha), sehinggajumlah Path (PP) adalah = SPH : Pkk/Path (PP) = 148 pkk/ha : 68 pkk/path = 2,18 Path/Haatau2,18 PP/Ha • Jikapanjang path (PP) = 300 m makaluas path/ha = Panjang Path x Lebar Path x Jumlah Path/Ha = 300 m x 1,5 m x 2,18 Path/ha = 979 m2

  7. MENCARI LUAS SEMPROT TPH • Setiap 3 Path (PP) ada 1 TPH. Karena 1 ha ada 2,18 Path (PP), makadalam 1 ha ada 2 TPH • Luas TPH/Haadalah = Panjang TPH x Lebar TPH x Jumlah TPH/Ha = 6 m x 4 m x 2 TPH/Ha = 24 m2 x 2 TPH/Ha = 48 m2

  8. TOTAL LUAS YANG DISEMPROT CPT • Jadi, dengandemikian, total luas yang disemprotdalampekerjaan CPT spraying adalah: 1. Luas Circle/Ha = 1.046 m2 2. Luas Path/Ha = 979 m2 3. Luas TPH/Ha = 48 m2 Total luas = 2.074 m2, atausetara = 0,21 ha

  9. ROTASI CPT SPRAYING • Setiap ha kebunsawitpunyarotasikerjamasing-masing • Untuk CPT Spraying, PT. BWP menganggarkan 3 rotasi/tahunatausetiap 4 bulan = 1 rotasi CPT • Contohblok A1 dilakukan CPT sesuaijadwalberikut: - Rotasi 1 = bulanJanuari 2011 - Rotasi 2 = bulan Mei 2011 - Rotasi 3 = bulan September 2011 • Artinya, Mandorharusmengaturrencana agar dalamwaktu 4 bulan (1 rotasi), seluruhblok yang adadidivisiharussudahdilakukan CPT Spraying • Antisipasikanharikering (haritidakhujan) dalam 1 rotasidengancara = 75% x (4 bln x 25 hr/bln) = 75 hr/rotasi (tidakhujan)

  10. RENCANA KERJA CPT SPRAYING

  11. CONTOH RENCANA KERJA CPT • MRE-3 memiliki 81 blok @ 30 ha = 2.430 ha. • Waktutersedia 1 rotasi = 4 bln (75 hariefektif). • TK Semprot yang ada = 40 TK. • Output TK = 0,4 Hk/Ha (2,5 Ha/Hk). Output TK Total/Hr : = 40 TK x 2,5 Ha/Hk = 100 ha/hr (3,3 blok). Untukmemudahkan, dibuat target 90 ha/hr (3 blok) dengan TK sebanyak = 90 ha/hr : 2,5 ha/hk = 36 TK RencanaKebutuhanWaktu (Alternatif 1): = 2.430 ha : 90 ha/hr = 27 hariefektif RencanaKebutuhanWaktu (Alternatif2): Target hanyadibuat 60 ha/hr (2 blok) dengan24 TK, maka = 2.430 ha : 60 ha/hr = 40,5 hariefektif 41 hariefektif

  12. LATIHAN 1: RENCANA KERJA CPT • MRE-3 memiliki 81 blok @ 30 ha = 2.430 ha. • Waktutersedia 1 rotasi = 4 bln (75 hariefektif). • TK Semprot yang ada = 40 TK. • Output TK = 0,4 Hk/Ha (2,5 Ha/Hk). Ditanya: Manajemen PT. BHL meminta agar 2.430 ha dikerjakandalam 50 hr. Beraparencana ha luas CPT/hr? Berapakebutuhan TK/hr ? Dijawab: Luas CPT/ha = 2.430 ha : 50 hr = 48,6 ha CPT/hr TK Dibutuhkan = 48,6 ha CPT/hr : 2,5 ha/hk = 19,44 HK

  13. LATIHAN 2: RENCANA KERJA CPT • MRE-3 memiliki 81 blok @ 30 ha = 2.430 ha. • Waktutersedia 1 rotasi = 4 bln (75 hariefektif). • Output TK = 0,4 Hk/Ha (2,5 Ha/Hk). Ditanya: Manajemen PT. BHL meminta agar 2.430 ha dikerjakandalam 75 hr. Beraparencana ha luas CPT/hr? Berapakebutuhan TK/hr ? Dijawab: Luas CPT/ha = 2.430 ha : 75 hr = 32,4 ha CPT/hr TK Dibutuhkan = 32,4 ha CPT/hr : 2,5 ha/hk = 12,96 HK/hr  13 HK

  14. KONDISI FISIK LAPANGAN • Secaraumum, dariawaltahun, kondisifisiklapanganuntukpekerjaan CPT Spraying adalah: - Rotasi1 = berat, - Rotasi 2 = sedang, dan - Rotasi 3 = ringan • Karenanya, maka Output TK CPT danpemakaianbahanjugamengikutikondisifisiklapangannya.

  15. PEMAKAIAN ALAT SEMPROT • Banyakalatsemprot yang bisadipakaiseperti RB, SA, Solo, Inter, CDA, dll • Alatapapun yang dipakai, perhatikankapasitastankidan volume semprot. Pastikan Nozzle benar. • Yang banyakdipakaiadalah Very Low Volume 200 ltr/ha. Hal iniuntukmenghemat air, mempercepatwaktukerja, danmeningkatkan output TK CPT. • Cara menghitung volume semprotadalah: (Flow Rate x 10.000) : (Lebarsemprot x mtr/mnt) = (900 ml/mnt x 10.000) : (1,5 mtr x 30 mtr/mnt) = 9.000.000 : 45 = 200.000 ml/ha = 200 ltr/ha

  16. JENIS-JENIS NOZZLE SPRAYER

  17. DOSIS DAN KONSENTRASI DOSIS adalahkebutuhanherbisida/ha untukdapatdiaplikasikansecarameratadalamsuatuluasantertentudengansatuan (ltr/ha atau kg/ha) KONSENTRASI adalahkebutuhanherbisida/liter larutanyang digunakanuntukmenyemprotdengansatuan (ml/ltr air atau mg/ltr air) atau %. Contohkonsentrasi CPT memakai Slash adalah 4%. Artinya, setiap cap = 15 ltr/cap X 4% Slash = 15000 ml x 4% = 60 cc/cap Slash atau = 60 cc : 15 ltr = 4 cc/ltr air. Jikadipakai Nozzle VLV (200 ltr/ha) makajumlah cap/ha dibutuhkan: = 200 ltr/ha : 15 ltr/cap = 13 cap/ha. Maka, jumlah Slash yang dibutuhkan: = 13 cap/ha x 60 cc/cap = 780 cc/ha atau 0,78 ltr/ha

  18. DOSIS DENGAN NOZZLE VLV (200 Ltr/Ha) • Jumlah cap/ha = 200 ltr/ha : 15 ltr/cap = 13,3 cap/ha. • Dosis/Ha (Slash) = 13,3 cap/ha x 60 cc/cap = 800 cc/haatau0,8 ltr/ha Latihan: MRE-4 akan CPT spraying di Blok A1, A2, B1, dan B2. Luaslahandi-CPT = 120 ha. Nozzle dipakai VLV 200 lt/ha. Kondisipiringandanpasarpikulsangatberatsekali. Rekomendasi EM memakai konsentrasi 6% Slash dan 0,027% Ally. Setiap HK dapat 1,5 ha. Hitunglah berapa : • Total air = 120 ha x 200 lt/ha = 24000 ltr. • Total cap = 24.000 ltr : 15 ltr/cap = 1600 cap • Total Slash = 1600 cap x (6% x 15 ltr/cap) = 1600 x 90 cc = 144.000 cc • Total Ally = 1600 cap x (0,027% x 15 ltr/cap) = 1600 x 4,05 gr = 6.480 gr • Total HK = 120 ha : 1,5 ha/hk = 80 hk

  19. DOSIS • Nozzle dipakaiadalah VLV atau volume 200 lt/ha. Artinya, untukmenyemprotblanket(seluruhpermukaan) 1 ha dibutuhkanlarutansebanyak 200 liter. • Sprayer dipakaiadalah Solo dengan volume 15 lt/cap. Jadi, dengan Nozzle VLV (200 lt/ha), jikadiubahke cap, jumlahkebutuhannyaadalah = 200 lt/ha : 15 lt/cap = 13,3 cap/ha