1 / 39

Presentation outline

Presentation outline. Presentation outline Organization PA plans and compliance PMP MIP/KIP planning Cleanliness ESD control Configuration Control CN, NCR and RFW status Problem areas. FPss PA plans/compliance. PA plans and compliance

Download Presentation

Presentation outline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation outline • Presentation outline • Organization • PA plans and compliance • PMP • MIP/KIP planning • Cleanliness • ESD control • Configuration Control • CN, NCR and RFW status • Problem areas FPss CDR 1/2/3 July 2003

  2. FPss PA plans/compliance • PA plans and compliance • Instead of one overall FPss PA plan separate plans for FCU, FPU and JPL: • FCU, SRON-U/FCU/PL/2000-001 • FPU, FPSS-00026 • JPL (MU bands 5, 6L and 6H, US part), JPL D-19161 • Other FPss consortium members through compliance matrices (HIFI PA plan): • Compliance status in section 6.1 of FPSS-00026 • Sufficient agreement between members and FPss PA • All need more or less support from FPss PA to fulfil these tasks • Subcontractors PA control through SoW’s or procurement specifications FPss CDR 1/2/3 July 2003

  3. PMP – EEE parts • EEE parts lists and procurement • All EEE parts lists established and reflecting current design status • All parts ordered at the CPPA or, if self procured, ordered at manufacturers/suppliers except Isolators • Isolator order waits finalization of PID but no delay expected • Go-ahead for housing production has been given and magnet materials procured • After approval of PID, probably shortly from now, go-ahead for production • Problems with CPPA expected delivery dates resolved for MU’s and IF amplifiers • Delivery of CPPA parts in progress and for the MU’s almost completed and for the other units expected to be on time • Parts list and procurement for IF Up-converter currently done by HIFI PA FPss CDR 1/2/3 July 2003

  4. PMP – EEE parts – PAD status • PAD Status (28) • FPU resistors and capacitors (24 PAD’s active, 2 withdrawn) • Most of them have initial Acceptance up to HIFI System; at ESA for acceptance (19) • Some under final definition - new items like 18nF capacitor (5) • Isolators • PAD needs update: batches and sample sizes, LAT program (PAMTECH/SRON tasks), number of cold thermal cycles • IF amplifier HEMT • Under definition by HIFI System PA • CSA temperature sensor Lake Shore DT670E-BR • Initial Acceptance up to HIFI System; at ESA for acceptance • FCU OP12B • Accepted by ESA, closed FPss CDR 1/2/3 July 2003

  5. PMP – EEE parts – PAD status • PAD’s FPU CAPACITORS AND RESISTORS • PAD’s for all capacitors and resistors because of use at cryogenic temperature • Qualification logic for these parts and applied interconnection techniques: • Parts mounted on evaluation boards of with envisaged materials and processes: • Aluminium oxide/solder/wire bond • Duroid/solder/wire bond • Duroid/conductive epoxy/wire bond • TMM/conductive epoxy/wire bond • Kapton flex print/solder • Evaluation boards cycled RT/LHe (dip stick) 100x • Destructive analysis of parts and interconnections • Boards defined, to be manufactured, cycled and evaluated, expected to be completed in October 2003 except for IF2 • JPL performs equivalent program on MU 5, 6L/6H hardware FPss CDR 1/2/3 July 2003

  6. PMP – EEE parts – PAD status • Alcatel IF1 evaluation board • Au plated aluminium/Duroid/conductive epoxy FPss CDR 1/2/3 July 2003

  7. PMP – EEE parts – PAD status • PAD FPU ISOLATORS • Two types of isolators that differ in outer dimensions only • PID for flight models almost completed • Two DM’s are cycled 30x at this moment; after that internal inspection and if necessary feedback into PID FM • Flight batch 100% inspection: • visual • performance at 4.2/15 Kelvin • From flight batch samples will be taken for LAT: • 2 of each type • Cycling 10x RT/LHe, 20x RT/LN2 • Extended bake out and warm cycling, 1x 144 hours at 85C + 4 cycles RT/85C • Cryogenic (80K) vibration, qualification level • Internal FPss CDR 1/2/3 July 2003

  8. PMP – EEE parts – PAD status • PAD CSA TEMPERATURE SENSOR • Lake Shore DT670E-BR bare diode • 100% visual inspection • LAT on 4 items, 1 control item: • Mounted on alumina together with DT670SD-4L for calibration check at 4.2 and 77 K • Irradiated 10krad/Si and calibration check thereafter • Thermal cycling 353/4.2 Kelvin, 100x followed by a calibration check, visual inspection, bond pull test, die shear test. • PAD FCU OP12B • Part from XMM-RGS project • Relife and hermetic seal testing and external visual inspection performed on 25 pieces FPss CDR 1/2/3 July 2003

  9. PMP – EEE parts – Other issues • Lake Shore Germanium thermistor GR200B • Lake Shore notified CPPA that they do not guarantee that part will survive launch vibration and does not change in calibration after bake out. • SRON performed vibration and bake out on commercially procured part • Bake out – 19 hours at 90, 145 hours at 80C • Vibration – together with console, in 11 steps from 2 upto 9 grms, 30 seconds each • No changes observed within our measuring accuracy of about 10 mKelvin • Results reported in FPSS-00402 • Proposed to CPPA to do LAT, by SRON, on 2 pieces from the FPU flight batch • Vibration at 80K, FPU qualification level • Extended bake out for 144 hours at 85C FPss CDR 1/2/3 July 2003

  10. PMP – EEE parts – Other issues • SMA Attenuators • Radiall type R413 6xx 650, 0 – 10 dB attenuation • Located on SMA input connectors of IF2 • No documented cryogenic history available • LAT on 2 pieces from flight batches • Thermal cycling RT/LN 10x and RT/LHe 6x • Vibration at 80K, FPU qualification level FPss CDR 1/2/3 July 2003

  11. PMP – Materials • Declared Materials Lists status • FPU – draft issue, to be updated • COA – established • DPB – in preparation • DRT – draft issue, to be updated and checked • MSA – draft issue, to be updated and checked • Console – draft issue, to be updated and checked • FPC – draft issue, to be updated and checked • CSA – draft issue, to be updated and checked • IF2 – not received yet (to be defined with selected Swiss company) • FCU – to be updated and checked • Draft issues are either based on draft or non-released production documents or on interviews FPss CDR 1/2/3 July 2003

  12. PMP – Processes • Declared Processes Lists status • FPU – draft issue, to be updated • COA – established • DPB – in preparation • DRT – draft issue, to be updated and checked • MSA – draft issue, to be updated and checked • Console – draft issue, to be updated and checked • FPC – draft issue, to be updated and checked • CSA – draft issue, to be updated and checked • IF2 – not received yet (to be defined with selected Swiss company) • FCU – to be updated and checked • Draft issues are either based on draft or non-released production documents or on interviews FPss CDR 1/2/3 July 2003

  13. PMP – Waveguide horns • Mixer unit waveguide horns electroforming process • Main problem with this process is fluid inclusion in corrugations, especially in the deep corrugations close to the waveguide transition • Status at RPG • RPG invested much time and in solving this problem • Optimization of electrolyte • Optimization of electroforming process • Development of an iterative process of copper growing and selective removal • Hiring a skilled and fully dedicated person for this process • Very recently they demonstrated that they were successful in producing an inclusion free MU 2 horn • No 100% guarantee that horns have no inclusions! FPss CDR 1/2/3 July 2003

  14. PMP – Waveguide horns MU 2 horn produced with “old” process MU 2 horn produced with optimized process FPss CDR 1/2/3 July 2003

  15. PMP – Waveguide horns Details of horn without inclusions Details of horn with inclusions FPss CDR 1/2/3 July 2003

  16. PMP – Waveguide horns • Status at RPG, continued • PID under review by SRON and KOSMA • Before delivery, horns are thermally cycled to reveal detrimental inclusions: • 150C for one hour • 2x between RT/LN2 • Visual inspection after each test • One horn from SRON flight batch will be cut • Contents of EIDP agreed, a.o. photographs of the corrugations at three stages of the electroforming process giving some evidence of inclusion free electroforming • Status at Thomas Keating Ltd • TK is producing horns with another type of process • Status on inclusions not known yet • Same LAT as for the horns from RPG FPss CDR 1/2/3 July 2003

  17. PMP – Riveting • Status COA riveting • HTS has riveted a COA precursor QM • External visual inspection of rivets showed that rivets are within NAS requirements • Results of micro sectioning of rivet samples were not acceptable to ETH/SRON • – probable cause is an inadequate DPA procedure of the riveting company – • HTS has produced new rivet samples that will be processed and inspected by a SRON contracted, independent, testhouse • Results expected at the end of the first week of July • If results are satisfying the go-ahead for riveting COA QM will be given • Pull strength test samples (NASM-1312-4) will be produced together with QM/FM FPss CDR 1/2/3 July 2003

  18. PMP – Pivots • Status C-Flex pivot manufacturing • Together with SRON C-Flex has developed processes for manufacturing the pivots for the Focal Plane Chopper and Diplexers • The development was focused on: • CuBe and Inconel 718 pivots • Base material condition • Plating process CuBe • Braze and EB weld schemes • Braze materials • Hardening heat treatments • Production flow • Batches of three types were recently produced for evaluation • CuBe, 100 m spring, brazed/welded • CuBe, 130 m spring, brazed/welded • Inconel 718, 90 m spring, brazed/brazed FPss CDR 1/2/3 July 2003

  19. PMP – Pivots • Status C-Flex pivot manufacturing, continued • Samples of all three types have been • Visually inspected • Static load tested • Vibration tested • Micro sectioned • All three types comply with the FPU requirements • Inconel 718 has been selected for use in the FPU because: • High strength • Relatively simple production flow and processes, reproducibility good • Fatigue strength acceptable • Torque rate within requirements • C-Flex PID defined and SRON procurement specification in preparation FPss CDR 1/2/3 July 2003

  20. PMP – Semi rigid cables • Status of semi rigid cables • Two types of semi rigid cable material • Stainless steel (between 1st and 2nd Isolators) • Aluminium (all others) • Reliability problem description • Creep of PTFE dielectric due stresses induced by bending and thermal cycling could cause breakage of solder joints at SMA connector • Problem widely recognized and occurs also in cables used in the normal temperature range • References: • ECSS-Q-70-18, section 4.1 • Barry. D. Dunn; Metallurgical assessment of spacecraft parts, materials and processes; p.421 FPss CDR 1/2/3 July 2003

  21. PMP – Semi rigid cables FPss CDR 1/2/3 July 2003

  22. PMP – Semi rigid cables • Remedy according to specification ECSS-Q-70-18 • Thermal cycling of the cut cable between RT/-45C/RT/85C/RT • Minimum number of cycles is 3, removal of the protruding dielectric after each cycle • Mounting of the connectors only after 24 hours at RT • Evaluation performed (test report FPSS-00420) • As ECSS-Q-70-18 is meant for cables to be used in the normal temperature range different preconditioning thermal cycles schemes were applied to a range of cable types and invest their behaviour when exposed to multiple cycles between RT and LHe, LN2 and bake out temperature • It appeared that creep of dielectric in assembled cables can be detected with reflection measurements • Preconditioning of the cables by cycling 3x between RT/-45C/RT/90C/RT seems to be sufficient for cables used at cryogenic temperature • SS cable type JS50085 and aluminium type AX50085 seem to be a good choice as baseline for the semi rigid cable qualification program FPss CDR 1/2/3 July 2003

  23. PMP – Semi rigid cables • Qualification program • Selection of cable manufacturers; two possible candidates: • SV Microwaves • Philips Natlab (R&D laboratories) • The manufacturer has to select the materials and processes and establish the manufacturing procedures according to the ECSS specification and possible amendments specified by SRON • SMA connectors are procured by SRON through the CPPA • A set of cables have to be produced according to that PID • Program • Extended bake out 144 hours at 85C and 5 cycles RT/85C • Thermal cycling 20x RT/LN2 and 10x RT/LHe • Vibration at 80K, FPU qualification level • Reflection measurements • DPA on connector samples to verify solder quality FPss CDR 1/2/3 July 2003

  24. PMP – Polarizing grids • Polarizing grids • Manufactured by QMC on SRON manufactured frames • Frame material Sanmac SS 304L frames • Mylar thickness 1.5 m • Grid material sputtered copper, photographically patterned • Copper thickness 0.4 m • Photoresist Microposit 1805 for copper protection • Mylar glued between two frames with Torr Seal • Evaluation performed on DM grids • Cold cycling had no effect on flatness, tensile stress loss of about 30% • Bake out no effect on flatness and a tensile stress loss of about 20% • Remaining tensile stress sufficient • Vibration at 80K did not show any effect on grids • Sufficient flatness for visible light alignment • Test report FPSS-00012 FPss CDR 1/2/3 July 2003

  25. PMP – Polarizing grids • Grid LAT program on flight batch • 100% visual inspection • 100% grid pitch and width • 100% flatness • Two samples from flight batch for: • Extended bake out 144 hours at 85C and 5 cycles RT/85C • Thermal cycling 20x RT/LN2 and 10x RT/LHe FPss CDR 1/2/3 July 2003

  26. PMP – Absorbing coating • Absorbing coating • Stycast 2850FT/24LV mixed with SiC grains (volume ratio – 3:1, weight ratio – 1:1) • Outgassing properties Stycast 2850FT/24LV (source: GSC outgassing data base) • TML – 0.5% - 1%, mean 0.6 • CVCM – 0.01% - 0.18%, mean 0.04% • Coating mass – 0.18 g/cm2 of which 0.9 g/cm2 Stycast • Total area of coating in FPU – 2520 cm2 • Total coating mass in FPU – 454 grams of which 227 grams Stycast • Estimated TML – 1.4 grams mean, 2.3 grams max • Estimated CVCM – 0.1 grams mean, 0.41 grams max • Outgassing properties of the absorbing coating may differ because of the large exposed surface area, variation in Stycast production lots, applied cure scheme • Outgassing properties will be verified in the near future FPss CDR 1/2/3 July 2003

  27. MIP/KIP planning • MIP/KIP • MIP’s currently not foreseen • KIP’s FPU and subunits thereof defined in FPss-00309 • COA, after machining mechanical parts and riveting • MU’s (except MU’s 5 and 6L/H, is JPL task) electrical boards before integration and internal electrical connections • IF amplifiers before closing boxes • CSA Warm source after assembly • FPC pivot manufacturing, before and after pivot integration, LVDT’s and Actuators, before closing • DRT’s before and after pivot integration, before closing Actuator • MSA’s before closing boxes • Consoles after full assembly • Grids before integration • KIP’s FCU and parts thereof planned in FCU PA plan, SRON-U/FCU/PL/2000-001 • Each board before conformal coating • After full assembly FPss CDR 1/2/3 July 2003

  28. Cleanliness control • Cleanliness Requirements • FPU • Particles – 300 ppm • Molecular– 4.10E-6 g/cm2 • FCU • Particles – 300 ppm • Control • One overall HIFI cleanliness control plan in cooperation with Subsystems down to the lowest level, no lower level control plans (SRON-U/HIFI/PL/2001-002) • Recording of exposure times to the different environment • On FPss level clean rooms and benches are validated to FED-STD-209 by an external company every year • Particle counter for on line monitoring in clean room • Molecular contamination monitoring periodically • Clean room garments – ESD safe – are regularly cleaned, dependent on use FPss CDR 1/2/3 July 2003

  29. Cleanliness control • Facilities • Available clean areas for FPU assembly and handling (requirement – class 1,000): • Clean room class 100 • Clean benches class 100 • Clean tent class TBD • Available clean areas for FCU assembly and handling (requirement – class 100,000): • Clean room class 100.000 • For FPU subunits clean benches and clean rooms of class <1000 available at the FPU consortium institutes and subcontractors • Clean room and facility monitoring • On FPss level clean rooms and benches are validated to FED-STD-209 by an external company every year • Initial determination of the molecular contamination potential during QM program of: • Clean room, clean benches • SRON MSA cryostat • CTH MSA cryostat (beam measurements) • FPU cryostat FPss CDR 1/2/3 July 2003

  30. Cleanliness control FPss CDR 1/2/3 July 2003

  31. ESD control • ESD plan SRON-G/FPU/PL/2001-001(FPSS-00183), issue2 • Four levels of ESD safe areas defined: • SIS/HEB/HEMT devices < 20V • MU’s/IF amplifiers/FPU/LOU < 100V • FCU/LSU/LCU < 1000V • Non ESD sensitivity hardware • (Sub)unit sensitivities in ESD plan are still estimates • (Sub)unit suppliers have to communicate sensitivities to the FPss; required for final classification and definition of protective measures • Integration/assembly/test locations and ESD measures for ESD sensitive hardware are defined with present sensitivity estimates as in ESD plan • ESD safe work locations available for all levels of ESD sensitivity, including for SIS, HEB and HEMT devices. • Guidelines for assembly and cable hook up FPss CDR 1/2/3 July 2003

  32. ESD control • Facilities evaluation and personnel training • Facilities evaluated by a JPL expert and found acceptable with minor recommendations. Recommendations are implemented. • Personnel at institutes and subcontractors, receiving US ESD sensitive hardware, were trained by JPL expert. All passed the exam FPss CDR 1/2/3 July 2003

  33. Configuration Control • Organization • Configuration Control performed at location of design responsible institute • FCU – SRON-U • FPU – SRON-G • DA, DRT, FPC, MSA’s – SRON-G • CSA – SRON-U • IF1L/H – YEBES/Alcatel • IF2 – ETH/Swiss industry • MU’s – MU institutes • Upconverter – TBD FPss CDR 1/2/3 July 2003

  34. Configuration Control – CIDL/PID FPss CDR 1/2/3 July 2003

  35. Configuration Control – CIDL/PID • Configuration Item Data List status • FCU – in DM phase; CIDL FM to be made soon • FPU QM – in preparation • COA QM – requirements and production documents part established • DA QM – production documents part established • DA FM – production documents part almost ready • DRT QM – production documents part established • MSA3V QM and FM – production documents part almost ready • MSA3H QM and FM – production documents part almost ready • FPss GSE’s – in preparation • CIDL’s of other subunits still have to be made • Process Identification Document status • MU’s and IF1H – almost established • IF1L – to be made but most of the contents the same as for IF1H • IF2 modules – to be made by to be selected Swiss industry FPss CDR 1/2/3 July 2003

  36. Configuration Control - CSL • Configuration Status • Change Notes • Total of 13 CN’s • 11 for FPU, 4 closed, status of some unclear or at least open • 2 for FCU, both closed • Main changes • Band 7 deleted • HEB change in band 6H • IF frequency change and Upconverter added • FPU mechanical interface with Optical Bench • FPC DM – QM/FM design change Problems • FPss Change register not well maintained • Insufficient communication and coordination between FPss CC and HIFI CC FPss CDR 1/2/3 July 2003

  37. Configuration Control - CSL • Requests for Waiver • 3 RFW’s for COA QM issued by the manufacturer, all closed, all level 4 • Two accepted – corner radii of COA parts • One rejected – Alodine 1500 instead of 1000 • NonConformance Reports • Total of 12 NCR’s. 1 open, 10 closed, 11 level 4, 1 level 2 • DRT QM • 1 NCR, level 4, open • Lack of Configuration Control, corrected • FPU mirrors • 2 NCR’s, level 4, closed • Insufficient production specification, corrected FPss CDR 1/2/3 July 2003

  38. Configuration Control - CSL • NonConformance Reports, continued • COA QM • 8 NCR’s, level 4, all closed • Mechanical parts production errors, some remanufactured, others acceptable and closed out as use as is • InP HEMT • One NCR, level 2 (processed by JPL/HIFI), open • Used in IF1L, IF1H and IF2 • Transistors from flight lot iher 1az1 wafer 4200-071 performed poor in test amplifier • Bad performance confirmed in IF1 and IF2 amplifiers • Some of the effects: • Higher noise (not good enough for bands 5 and 6) IF1 • Either worse input matching or gain of IF2 FPss CDR 1/2/3 July 2003

  39. Problems • Main problem • Evaluation, LAT and qualification programs • The evaluation, LAT and qualification programs to prevent parts and subunits with low quality and reliability being built into the FM cannot be done in a timely manner. • Hardly any or no feedback from these programs into the flight (sub)units • Possible solutions • More manpower and/or time • Limit the programs to an agreed and acceptable risk • Prioritize the items and accept the late completion of the last items FPss CDR 1/2/3 July 2003

More Related