Ssr1 cryomodule design and fabrication schedule
Download
1 / 5

SSR1 Cryomodule Design and Fabrication Schedule - PowerPoint PPT Presentation


  • 337 Views
  • Uploaded on

SSR1 Cryomodule Design and Fabrication Schedule. Tom Nicol - Fermilab. Design and Fabrication Schedule From July 2011. Front End Test Facility Planning SSR0 prototype cryomodule development/fabrication branch Possible schedule Systems integrated in the cryomodule Cryosystem SRF cavity

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'SSR1 Cryomodule Design and Fabrication Schedule' - albany


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Ssr1 cryomodule design and fabrication schedule

SSR1 Cryomodule Design and Fabrication Schedule

Tom Nicol - Fermilab


Design and fabrication schedule from july 2011
Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

Front End Test Facility Planning

SSR0 prototype cryomodule development/fabrication branch

Possible schedule

Systems integrated in the cryomodule

Cryosystem

SRF cavity

Power coupler

Tuner

Focusing lens

Alignment

TNicol

Assume: Dressed cavities are available as-needed.

2 identical cryomodules with 9-10 cavities each.

Engineering, design, drafting, and production resources available

as-needed.

October 2016 Production cryomodules ready for installation and testing.

October 2014 Production cryomodule parts in-house (not including cavities).

October 2013 Production cryomodule parts ordered.

June 2013 Production cryomodule design complete.

May 2017 Prototype cryomodule is ready for installation in the beamline.

Nov. 2015 Cryovessel is delivered to FNAL. Cryomodule assembly components are in house. Cryomodule assembly starts.

Feb. 2014 Cryovessel order is placed.

Oct. 2013 Cryovessel design is complete.


Design and fabrication schedule from july 20111
Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

November 2016 10 SSR0 ready for cryomodule assembly

November 2015 SSR0 jacketed cavity tests start in cryostat

August 2015 SSR0 Jacketing starts

June 2015 SSR0 VTS testing starts

March 2015 SSR0 processing starts

Dec 2014 SSR0 order is received

April 2014 SSR0 Production order is placed (~12 cavities)

January 2014 Prototype SSR0 cavity is jacketed and is tested in cryostat. Design modification period starts.

June 2013 SSR0 prototype cavity is processed / VTS-tested.

Dec 2012 SSR0 Prototype cavity is received

Dec. 2011 SSR0 prototype cavity order is placed.

June. 2016 Couplers are ready for installation

Dec. 2015 Production couples test and processing start

Dec. 2014 Order is placed for SSR0 production coupler fabrication

Dec. 2013 Prototype coupler is tested. Design modification period starts.

Nov. 2012 Prototype coupler is ordered

Dec. 2011 Power coupler design is complete


Design and fabrication schedule from july 20112
Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

January 2015 Production tuners are ready for installation

March 2014 Production tuner order is placed

Dec. 2013 Prototype tuner is tested with a prototype cavity

Nov . 2011 Tuner concept is finalized

Dec. 2014 Focusing lens assemblies delivered to the cryomodule assembly site.

March 2014 Order is placed for production focusing lens fabrication

Nov. 2013 Prototype focusing lens is tested. Design modification period starts.

July 2013 Prototype SSR0 lens is tested. Design modifications start.

May 2013 Prototype lens fabrication starts.

Oct. 2012 SSR0 lens design is complete

Sept. 2012 Focusing lens design is complete

May 2012 Lens concept is proposed

March 2012 Lens fringe magnetic field requirement is finalized

Dec. 2011 Lens cooling scheme is finalized

Oct. 2011 Quench protection solution is found

Dec 2014 Alignment procedures and techniques are finalized. Equipment procurement starts

June 2013 Long base alignment test is made; Alignment system design starts

Nov. 2011 Alignment study for the SSR0 cryomodule is complete


Design and fabrication schedule
Design and Fabrication Schedule

PXIE Cryomodule Design Meeting

  • Assume:

    • Dressed cavities are available as-needed.

    • 1 SSR1 cryomodule with 8 cavities, 4 solenoids.

    • Engineering, design, drafting, and production resources availableas-needed.

  • June 2013 Production cryomodule design complete.

  • October 2013 Production cryomodule parts ordered.

  • October 2014 Production cryomodule parts in-house (not including cavities).

  • October 2016 Production cryomodules ready for installation and testing.