Regional Border Infrastructure Update SR 539 / Lynden-Aldergrove Port of Entry Improvements

Regional Border Infrastructure Update SR 539 / Lynden-Aldergrove Port of Entry Improvements. Todd Carlson Planning and Engineering Services. Canada-United States Transportation Border Working Group Spring Plenary Red Lion Inn - Seattle, Washington April 18, 2012.

aimee
Download Presentation

Regional Border Infrastructure Update SR 539 / Lynden-Aldergrove Port of Entry Improvements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Regional Border Infrastructure Update SR 539 / Lynden-Aldergrove Port of Entry Improvements Todd Carlson Planning and Engineering Services Canada-United States Transportation Border Working Group Spring Plenary Red Lion Inn - Seattle, Washington April 18, 2012

  2. Overview Lower Mainland BC / Northwest Washington 2

  3. Lynden/Aldergrove Border Crossing … a closer look… 3

  4. So what is the problem? 4

  5. A very under used roadway 5

  6. A little data … • In 2009, this vital port processed $496 million in Washington exports and $38 million in British Columbia exports • Second busiest U.S.- Canada commercial crossing in British Columbia (after Pacific Highway) Technical Assessment of the Aldergrove/Lynden Port of entry prepared by the Whatcom Council of Governments for the International Mobility and Trade Corridor Project (IMTC) 6

  7. Re-routing Impacts • Aldergrove-Lynden serves a distinct population of carriers and shippers • Without this crossing a significant amount of additional VMT and GHGs would be produced Technical Assessment of the Aldergrove/Lynden Port of entry - Whatcom Council of Governments 7

  8. Technical Assessment of the Aldergrove-Lynden Port of Entry Technical Assessment of the Aldergrove/Lynden Port of entry - Whatcom Council of Governments 8

  9. Technical Assessment of the Aldergrove-Lynden Port of Entry Technical Assessment of the Aldergrove/Lynden Port of entry - Whatcom Council of Governments 9

  10. WSDOT / CBSA Discussions • CBSA and WSDOT are close partners • CBSA’s POE built in 1972 – Over 40 years old • Meeting of WSDOT and CBSA March 2011 to discuss plans to rebuild the POE and the potential to add NEXUS • WSDOT allocates $250k to begin design process • CBSA and WSDOT begin design level coordination 10

  11. Scope of the Project • Add 2nd lane for NEXUS • Widen shoulder for trucks • Add truck spur • Potential for separate FAST lane Existing CBSA facility looking north 11

  12. SR 539 Project 12

  13. SR 539 Project 13

  14. SR 539 Project RISKS • Coordination with border agencies: CBP/ GSA & CBSA, could prolong important design decisions. • Limited Access Process – appeals could impact project schedule. • ROW acquisition – Unwilling seller. • Roadway Section – may need to construct the entire truck lane in PCCP concrete. Scoping estimate assumes HMA south of spur. 14

  15. For more information on (Topic of Presentation) Please contact: Todd Carlson (360) 757-5980 carlsot@wsdot.wa.gov 15