Rivanna Water & Sewer Authority Community Water Supply Plan Update

Rivanna Water & Sewer Authority Community Water Supply Plan Update. Public Meeting Monticello High School September 21, 2004 7:00 pm. Presentation Agenda. 2002 Community Water Supply Strategy Need to Update Strategy Goal for Update Review of “Short List” Option Project Schedule.

adolph
Download Presentation

Rivanna Water & Sewer Authority Community Water Supply Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rivanna Water & Sewer Authority Community Water Supply Plan Update Public Meeting Monticello High School September 21, 2004 7:00 pm

  2. Presentation Agenda • 2002 Community Water Supply Strategy • Need to Update Strategy • Goal for Update • Review of “Short List” Option • Project Schedule

  3. 2002 CWS Strategy and Need to Update

  4. Basic Components of February 2002 Community Water Supply Strategy • Capital Improvements • Water Conservation • Watershed Protection • Environmental Protection

  5. 2002 Strategy – Capital Improvements • SFRR Four-Foot Crest • SFRR Dredging • Restore Mechums River PS and Increase Supply in Ragged Mountain 30-Year 50-Year • James River • Beaver Creek • Reservoir • Other Capital • Options

  6. The Need to Update • New “Drought of Record” in 2002 • Improved Modeling Information • Lower Yield for Four Foot Crest • Uncertain Costs and Yield for Dredging DECISION: Update the Capital Improvement Options in the Community Water Supply Plan Based on 50-Year Horizon

  7. Update - So Far • Existing Water Supply Adequate Until 2008 • Use of Beaver Creek in Drought Can Extend Adequacy to 2018 • Safe Yield Deficit in 2055 – 9.9 MGD

  8. Update – So Far • The “Short List” • James River • Ragged Mountain Expansion • SFRR Four-Foot Crest • SFRR Dredging • Beaver Creek Reservoir

  9. The Goal

  10. The Goal • Obtain a Federal Permit That ... –Will Achieve 9.9 MGD of Added Capacity Over 50 Years –Acceptable to State and Federal Regulators – Acceptance to Local Community – Issues are Complex and Cross the Jurisdiction of Multiple Agencies

  11. Federal and State Requirements To identify the least environmentally damaging, practicable alternative taking into account: overall project purposes, feasibility, logistics, and cost. • Water Quality • Wetland Impacts • Stream Impacts • Stream Flows for Expanded Reservoirs • Threatened and Endangered Species • Cultural Resources • Recreational Resources • Highway and Bridge Issues Specific Issues That Must Be Addressed:

  12. Federal and State Agencies • U.S. Army Corp of Engineers Norfolk District • U.S. Environmental Protection Agency Region III • U.S. Fish and Wildlife Service • Virginia Department of Environmental Quality • Virginia Department of Health • Virginia Department of Game and Inland Fisheries • Virginia Department of Conservation and Recreation Division of Planning and Recreation • Virginia Marine Resources Commission • Virginia Department of Historic Resources Division of Resource Services and Review • Virginia Department of Conservation and Recreation Division of Natural Heritage

  13. Local Agencies • Rivanna Water and Sewer Authority • Albemarle County • Albemarle County Service Authority • City of Charlottesville

  14. The “Short List”

  15. James River Option • Can Provide All 9.9 MGD Required • Could be Regional Project or RWSA Project • New Water Supply and Treatment Plant • Eventually Abandon Observatory WTP and Transfer from Sugar Hollow to Ragged Mountain • High Cost Among Options; Limited Project Phasing Capability

  16. Ragged Mountain Expansion • Can Provide All 9.9 MGD Required • Combines Dam Rehabilitation and Expansion • May Include Mechums Pump Station Restoration; Requires Pipe Replacement from Sugar Hollow • Requires VDOT Approval at I-64 • Lower End of Costs Among Options; Phasing Capability

  17. SFRR Expansion • Can Provide Only 2.9 MGD; Must Be Combined with Other Options • Four Foot Crest (Raise Dam by Four Feet) • May Require Bridge Replacements • Moderate Costs When Combined with Other Options; Phasing Capability • Measured Wetland and Stream Impacts Will Be Critical to Feasibility

  18. SFRR Dredging • Can Provide Maximum of Approx. 5 MGD; Must Be Combined with Other Options • Volume of Dredged Spoil is Significant; Will Require Large Disposal Site; Environmental Impacts Will Depend on Site • Quality of Spoil Material Not Yet Confirmed • Costs Not Yet Quantified • Long-Term Maintenance Required and Sustainability Uncertain

  19. Beaver Creek Reservoir • Crozet System Currently Uses 0.3 MGD; Master Plan Build-Out = Estimated 1.1 MGD Use in Future • Up to 2.6 MGD Available for Urban System; Must Be Combined With Other Options • Existing Reservoir; Low Cost to Implement • Lowers Costs when Combine with Other Options • May Be Used as an Interim Solution

  20. Project Schedule

  21. Project Schedule • January 2004 – Update Safe Yield Analysis • May 2004 – Identify Alternatives to Meet Future Safe Yield • July 2004 – Narrow alternatives to “Short List” using federal requirements • August 2004 – Initiate evaluation of “Short List” and discussions with regulators

  22. Project Schedule • September 2004 – Public Meeting • October/November 2004 – Additional Public Discussions • Winter 2005* - Propose Selected Alternative to RWSA Board of Directors • Winter 2005* - Public Meeting on Proposed Selected Alternative *Schedule Subject to Change Depending on Negotiations with Federal and State Regulators

  23. Project Schedule • Spring 2005* - Local Board Approvals of Selected Alternative • Spring 2005* – Make Application for Federal Permit for Selected Alternative *Schedule Subject to Change Depending on Negotiations with Federal and State Regulators