1 / 12

Progress Report on Physics Fill 1295 with 48 Bunches per Beam – August 20, 2023

On August 20, 2023, the LHC completed a successful physics fill with 48 bunches per beam, achieving an integrated luminosity of 240 nb⁻¹ after 16 hours of stable beams. The operation commenced with a filled beam containing 4.5 x 10¹² protons per beam. Emittance measurements showed average values of ex = 4.4 mm and ey = 4.9 mm. The day included tasks such as luminosity scans, orbit feedback tests, and addressing cryogenic problems. Upcoming issues involve CMS cooling and maintenance of ion pumps.

addo
Download Presentation

Progress Report on Physics Fill 1295 with 48 Bunches per Beam – August 20, 2023

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Friday 20.8. • Morning: First physics fill with 48 bunches per beam: • 20:30: Injection finished  4.5 1012 protons per beam in 48 bunches; ex1 = 2.9 mm; ey1 = 2.9 mm; ex2 = 3.3 mm; ey2 = 3.5 mm; • 21:00: Start ramp; • 21:40: End ramp; • 22:20: Start Squeeze Initial luminosity: L = 6.65 1030 cm-2 sec-1; • 23:30: Stable physics; L = 6.15 1030 cm-2 sec-1;  fitted average emittances for bunch current of Nb = 9 1010: • s= 4.05mm; with b* = 3.6m (average of three 1/b* measurement in IR5) integrated luminosity = 240 nb-1 after 16 hours; 8:30 meeting

  2. Firday 19.8. • 48 bunches in both beams: integrated Luminosity of more than 240 nb-1 8:30 meeting

  3. Thursday 19.8. • 48 bunches in both beam: beginning of the fill. 8:30 meeting

  4. Firday 19.8. • Beam 1 bunch distribution at end of fill: 8:30 meeting

  5. Firday 19.8. • Beam 1 bunch distribution at end of fill: 8:30 meeting

  6. Fill 1295 • 16 hours of stable beams • first 48 + 48 • IPs:1 5 2 8 - 1 58 - 1 5 2 • - 1 5 - 2 8-8 giulia papotti (BE/OP/LHC) giulia papotti (BE/OP/LHC)

  7. Fill 1295 1 LR in 2 (33m) 1 LR in 2 (33m) 1 LR in 8 (33m) 1 LR in 8 (33m) 1 LR in 2 (22m) 1 LR in 2 (22m) no Long Range interactions with Long Range • IPs:1 5 2 8-1 58-1 5 2-1 5 -2 8- 8 giulia papotti (BE/OP/LHC) giulia papotti (BE/OP/LHC)

  8. Firday 19.8. • Very clean dump by operator switch: 8:30 meeting

  9. Friday 20.8. • End of Fill studies: • Luminosity scans in all IPs (large scan in IP1); • Damper studies; • Orbit feedback test for radial loop correctio; • 16:15: Beam dump; very clean & without any unusual losses 8:30 meeting

  10. Firday 19.8. • Lumi scans in IR1: • average beam emittances: ex = 4.4mm ey = 4.9mm • growth of 10% to 20% over the fill! 8:30 meeting

  11. Saturday 21.8. • Morning until noon: • Recovery from cryo problem in Pt6. • Afternoon and over night: • New physics fill with 48 on 48 bunches. • Sunday to Monday: • Physics Fills with 48 bunches per beam. 8:30 meeting

  12. Week 33 • Open Issues for next Technical Stop: • CMS cooling for central tracker. • Ion pumps in dump line MKB (B2 only 4 out of 8 pumps working; few days intervention). • BLM racks (in buildings SR1 and SR5 and both at position BY02): would like to correct the way the power cable for the multi-plug arrives inside the rack. • QPS boards: several boards had to switch from channel A to B. • Access team to replace oxydized connectors for PAD-PX24 (3 hours). • CV needs to replace a motorization of the water valve of the sector 56 (3h). • RCBH18.R7B2 – Miguel CerqueiraBastos. 8:30 meeting

More Related