Mucool advanced m t f m i c e layouts
Download
1 / 14

MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS - PowerPoint PPT Presentation


  • 302 Views
  • Uploaded on

MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS. August 12-13, 2002 Edgar L. Black IIT. CURRENT EFFORTS FOR M.T.F. FINALIZE DETAILS OF FORCED COOLANT FLOW ABSORBER TO BE INSERTED INTO THE LAB G MAGNET. COORDINATE DESIGN OF THE CONVECTIVE TYPE ABSORBER FOR THE SAME LOCATION (KEK COLLABORATION).

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS' - adamdaniel


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Mucool advanced m t f m i c e layouts

MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS

August 12-13, 2002

Edgar L. Black

IIT

Edgar L. Black


Current efforts for m t f
CURRENT EFFORTS FOR M.T.F.

  • FINALIZE DETAILS OF FORCED COOLANT FLOW ABSORBER TO BE INSERTED INTO THE LAB G MAGNET.

  • COORDINATE DESIGN OF THE CONVECTIVE TYPE ABSORBER FOR THE SAME LOCATION (KEK COLLABORATION).

  • COMPLETE WINDOWS DESIGN WITH SHOP DRAWINGS FOR FABRICATION (TO BE SUBMITTED TO THE MISSISSIPPI COLLABORATION AT THE END OF THIS MEETING).

  • INITIATE THE INTERFACE RESOLUTION OF UP & DOWN SIDE VACUUM WINDOW DESIGN REQUIREMENTS, (INCLUDING IMMEDIATE AND FUTURE EXPERIMENT PROGRAMS)

  • START INSTRUMENTATION HARDWARE INTEGRATION DESIGN FOR THE IMMEDIATE TEST PLANS.

Edgar L. Black



Mtf absorber forced flow
MTF ABSORBER FORCED FLOW

Edgar L. Black


Window absorber seal detail section of the manifold
WINDOW/ ABSORBER SEAL DETAIL(SECTION OF THE MANIFOLD)

Edgar L. Black


Absorber window detail
ABSORBER WINDOW DETAIL

Edgar L. Black


Window test plate
WINDOW TEST PLATE

Edgar L. Black


Vacuum vessel window
VACUUM VESSEL WINDOW

Edgar L. Black


Current efforts for m i c e
CURRENT EFFORTS FOR M.I.C.E.

  • NEED MORE STUDIES TO INTEGRATE NEW M.GREEN MAGNET DESIGN INTO THE SFOFO1 CONFIGURATION (CONFLICT WITH THE RF FEEDS).

  • INITIATED PLANT LAYOUT COORDINATION FOR THE INSTALLATION AT RAL (COMMUNICATION WITH IOURY)

  • NEED MORE INFORMATION ON THE PLANT FACILITIES

Edgar L. Black



M i c e sfofo
M.I.C.E. SFOFO

Edgar L. Black


Location in question
LOCATION IN QUESTION

PARTIAL VIEW OF THE R.A.L. FACILITY

Edgar L. Black


Location enlarged
LOCATION ENLARGED

Edgar L. Black


Future activities with time durations hrs
FUTURE ACTIVITIES WITH TIME DURATIONS (HRS)

1- FABRICATION OF 21CM WINDOWS AND PRESSURE TEST PLATES. 480

3 OR 5 WINDOWS FOR EACH MATERIAL?

2 - RESOLVE VACUUM WINDOW ISSUES AND COMPLETE THE DESIGN FOR FABRICATION 80

3 -PERFORM PHOTOGRAMETRY MEASUREMENTS OF THE AS BUILT WINDOWS AT FERMILAB. 300

5 - SET UP FACILITY AT N.I.U. FOR WATER AND CRYO PRESSURE BURST TESTS AND TEST. 80

6 - PERFORM PHOTOGRAMETRY MEASUREMENTS DURING TEST AT N.I.U. 100

7 - FABRICATION OF MANIFOLD ASSEMBLY AND ACCEPTANCE TEST. 200

8 - COMPLETE INFRARED HEAT TRANSFER FLOW WITH THE 15 CM MANIFOLD ASSEMBLY. 60

9 - PROCURE (OR BORROW) VERTICAL CRYOSTAT FOR THE ABSORBERS FLOW TEST. 160 OR 60

10 - SETUP CRYO FLOW TEST SYSTEM (AT FERMILAB OR N.I.U.) AND PERFORM TESTS. 320

Edgar L. Black


ad