  • Uploaded on

Evaluation Alternatives Present Worth Analysis. Companies constantly evaluate whether or not to pursue projects. Mutually Exclusive Projects – several projects proposed to address the same need. Only one of the projects can be selected.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Evaluation Alternatives Present Worth Analysis' - Thomas


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
evaluation alternatives present worth analysis
Evaluation AlternativesPresent Worth Analysis

Companies constantly evaluate whether or not to pursue projects.

Mutually Exclusive Projects – several projects proposed to address the same need. Only one of the projects can be selected.

Independent Projects – projects that do not compete, and are selected merely on their economic value.

Do Nothing (DN) Option – projects are often compared to the option of taking no action.

present worth analysis
Present Worth Analysis

Project Types:

Revenue – each alternative project being evaluated generate costs and revenues. These alternatives usually involve the purchase of new systems and equipment in order to increase revenue. Both the cost streams and revenue streams vary by alternative.

Service – Each alternative has only cost cash flow estimates. These projects are typically for safety, or are government mandated projects.

present worth analysis equal life alternatives
Present Worth Analysis – Equal Life Alternatives

One alternative – Calculate the present worth (PW) at the MARR. If PW > 0, the requested MARR is met or exceeded and the alternative is financially viable.

Two or more alternatives – calculate the PW of each alternative at the MARR. Select the alternative with the PW value that is numerically largest. (If all PW are negative, and do nothing is an alternative, then do nothing.)

present worth analysis equal life alternatives1
Present Worth Analysis – Equal Life Alternatives

Revenue Example: You are evaluating the purchase of a two income properties. You expect a MARR of 15%. You have enough funds for both purchases.

$75K Home$37.5K Home

Purchase Price $15,000 $ 7,500

Annual Maint. $ 6,000 $ 4,000

Annual Income $ 7,500 $ 5,000

Resale (after

Expenses) $90,000 $40,000

Life, years 15 15

present worth analysis equal life alternatives2
Present Worth Analysis – Equal Life Alternatives

$75K Home

PW = _________________________________

$37.5K Home

PW = _________________________________

What if 8% MARR was used?

PW ($75K Home) = $26,207

PW ($37.5K Home) = $13,667

present worth analysis equal life alternatives3
Present Worth Analysis – Equal Life Alternatives

Service Example: You are evaluating the purchase of a new or used car that needs to last you for only 5 years.

New CarUsed Car

Purchase Price $20,000 $10,000

Annual Maint. $ 500 $ 1,000

Resale Value $ 8,000 $ 4,000

Life, years 5 5

present worth analysis equal life alternatives4
Present Worth Analysis – Equal Life Alternatives

Use 8% for i since 8% is the expected rate of return if money invested in stock market rather than purchasing a vehicle.

New Car

PW = _______________________________

Used Car

PW = ________________________________

present worth analysis different life alternatives
Present Worth Analysis – Different Life Alternatives

The Present Worth of alternatives must be compared over the same number of years.

If project alternative have different service lives, the equal service requirement can be satisfied by:

  • Compare the alternative over a period of time equal to the least common multiple (LCM) of their lives.
  • Compare the alternative using a study period of length n, which does not necessarily take into consideration the useful lives of the alternatives. This period n is called the planning horizon.
present worth analysis different life alternatives1
Present Worth Analysis – Different Life Alternatives

Revenue Example: You are evaluating the upgrade of some production equipment to increase productivity. You are considering two alternatives. Company policy dictates a MARR of 20%.

Alternative 1Alternative 2

Purchase Price $ 200,000 $100,000

Annual Maint. $ 5,000 $ 2,000

Productivity Imp.

(per year) $ 40,000 $ 20,000

Life, years 10 12

present worth analysis different life alternatives2
Present Worth Analysis – Different Life Alternatives

Revenue Example: Because life alternatives are different, you decide to use a 10 year planning horizon and estimate a resale value of alternative of $5000 for the remaining 2 year of life.

Alternative 1

PW = -$200,000 + $35,000(P/A,20%,10)

PW = -$53,262

Alternative 2

PW = -$100,000 + $18,000(P/A,20%,10) + 5000(P/F,20%,10)

PW = -$23,727

Which alternative should you choose? _________________

present worth analysis different life alternatives3
Present Worth Analysis – Different Life Alternatives

Service Example: You are evaluating the purchase of a new or used cars that needs to last you for 10 years.

New CarUsed Car

Purchase Price $20,000 $10,000

Annual Maint. $ 750 $ 1,000

Resale Value $ 4,000 $ 4,000

Life, years 10 5

present worth analysis different life alternatives4
Present Worth Analysis – Different Life Alternatives

Use 8% for i since 8% is the expected rate of return if money invested in stock market rather than purchasing a vehicle.

New Car

PW = -$20,000 - $750(P/A,8%,10) + $4000(P/F,8%,10)

PW = -$23,180

Used Car

Buy used car in year 0 Buy used car in year 5

Sell car in year 5

PW = -$10,000 + $4,000(P/F,8%,5) -$10,000(P/F,8%,5) + $4000(P/F,8%,10) -$1000(P/A,8%,10)

PW = -$18,941

future worth analysis
Future Worth Analysis

Future worth analysis is similar to present worth analysis, expect that all cash flows are normalized to some future point in time.

Future worth is often used if an asset is to be sold at some future point in time, but before its expected life is reached. The future worth would be an indicator of how much the asset could be sold for at that future point in time (of course this assumes the buyer expects the same cash flows you anticipate).

future worth analysis1
Future Worth Analysis

Example: A company is considering selling off its power generation plants in 5 years. The cash flow projection over the next 5 years for this power generation operation unit is depicted below. What sales price in year 5 (future worth)must be received to achieve the company’s ROR of 5% per year.

FW = -$60(F/P,5%,4) + $25(F/P,5%,3) + $50(F/P,5%,2) + $75(F/P,5%,1) + $50

FW = ?

$75

$50

$50

$25

0 1 2 3 4 5 6 7 8

$60

capitalized cost
Capitalized Cost

Capitalized cost (CC) is the present worth of an alternative that will last “forever”. Examples include University endowments, and large public sector projects (dams, bridges, tollroads, etc.).

CC is related to P/A formula, P = A(P/A,i%,∞)

As n approaches infinity, CC = _________________

For example, if an endowment was invested at 10% interest, and $1000 was to be withdrawn every year indefinitely, then

_______________________

must be the present amount in the endowment.

capitalized cost1
Capitalized Cost

The following examples demonstrates how to obtain the capitalized cost of an asset which contains both recurrent and non-recurrent cash flows.

A toll-road was just completed at a cost of $1.5 billion, with major maintenance expenditures of $500 million forecast every 10 years. Annual receipts minus maintenance results in a positive cash flow of $150 million. What is the present worth, assuming i = 5%?

$150

$150

0 1 2 3 4 5 6 7 8 9 10 11 … 20

$500

$1500

capitalized cost2
Capitalized Cost

$150

$150

$150

0 1 2 3 4 5 6 7 8 9 10 11 … 20 …..

1) Convert the $500 million every 10 years to an annual cost.

A1 = -$500(A/F, 5%,10) = ____________

Therefore AT = __________

2) CC = -$1,500 + 110.25/.05 = $705 million

$500

$1500

payback period analysis
Payback Period Analysis

The payback period, np, is the estimated time, usually in years, it will take for the estimated revenues and other economic benefits to recover the initial investment and a stated rate of return i.

In other words, find np that satisfies the following equation:

Or if all end of year cash flows are equal,

where NCF is the net cash flow in period t, and DP is the initial downpayment or cash flow at time 0

payback period analysis1
Payback Period Analysis

Example: A pharmaceutical company anticipates R&D cost of $1.5 Billion for the development of a new drug. In addition, production startup costs are estimated at $1.0 Billion. Annual marketing costs are expected to be $50 million, annual production costs are $100 million, and annual sales are expected to be $500 million. What is the payback period for an ROR of 10%?

DP = $2,500 Million

A = $350 million

$2,500 = $350(P/A, 10%,n)

(P/A,10%,n) = 7.14

n = ___________

payback period analysis2
Payback Period Analysis

Caution: Payback period does not necessarily indicate one alternative being preferable to another alternative.

Example: Using ROR of 15%

Machine 1 Machine 2

DP = $12,000 $8,000

Annual

NCF = $3000 $1000 (year 1-5)

$3000 (year 6-14)

Max Life 7 14

(years)

payback period analysis3
Payback Period Analysis

Example:

Machine 1 0 = -$12,000 + $3000(P/A,15%,np)

np = ___________

Machine 2 0 = -$8,000 + $1000(P/A,15%,5) +

$3,000(P/A,15%,np-5)(P/F,15%,5)

np = ______________

Using LCM of 14 years.

PW1 = _______________________________________

PW2 = _______________________________________

life cycle cost lcc
Life Cycle Cost (LCC)

LCC analysis is the present worth (PW) of an alternative at a stated MARR, covering all costs from the early stages of design through the final stages of phase-out and disposal.

Example: A pharmaceutical company anticipates R&D cost of $1.5 Billion for the development of a new drug. In addition, production startup costs are estimated at $1.0 Billion. Annual marketing costs are expected to be $50 million, annual production costs are $100 million, and annual sales are expected to be $500 million. At the end of production, the plant and equipment can be sold for $100 million. This drug is to be phased out after 20 years. What is the LCC assuming a 10% MARR.

life cycle cost lcc1
Life Cycle Cost (LCC)

Example: A pharmaceutical company anticipates R&D cost of $1.5 Billion for the development of a new drug (in years 1&2). In addition, production startup costs are estimated at $1.0 Billion (in year 3&4). Annual marketing costs are expected to be $50 million, annual production costs are $100 million (both starting in year 5). At the end of production, the plant and equipment can be sold for $100 million (year 24). This drug is to be phased out after 20 years of production. What is the LCC assuming a 10% MARR.

(in millions)

PW = ___________________________________________

present worth of bonds
Present Worth of Bonds

Bonds are financial instruments of raising capital. In other words, in order to finance major projects, the government or corporations issue bonds in return for cash.

The borrower (corporation) promises to pay the face value of the bond upon maturity (V), and agrees to pay interest or dividends (I) at periodic times (c). Expected dividend payments are quarterly or semi-annually (c = 4 or 2). The Interest is determined using the stated bond coupon rate (b).

present worth of bonds1
Present Worth of Bonds

Example: Find the interest payment on a $1000 US treasury bond stated as paying 5% quarterly.

V = $1000

b = 5%

c = 4

Therefore, I = ______________________________

present worth of bonds2
Present Worth of Bonds

How much should you purchase a bond for (PW)?

To find the present worth (to you) of a bond, perform the following:

  • Determine I, the interest per payment period.
  • Construct the cash flow diagram, including the dividend payments and the face value payment upon maturity.
  • Establish a MARR.
  • Calculate PW.
present worth of bonds3
Present Worth of Bonds

Example: Find the PW on a $1000 US treasury bond stated as paying 5% quarterly with a maturity date 10 years from now. Assume a MARR of 12%, compounded quarterly.

I = $1000(.05)/4 = $12.5 per quarter.

n = ___________________

i = ____________________

PW = ______________________________