Sarasota Memorial Health Care System Management Council February 10, 2010. Construction Milestone Schedule. Project Milestones – Surgery Vertical Expansion:. Preparation for Structural Steel Close Arlington Street Capture Site Set up Crane for Structural Steel Open Arlington Street.

EllenMixel
Download Presentation

Sarasota Memorial Health Care System Management Council February 10, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sarasota Memorial HealthCare SystemManagement Council February 10, 2010

  2. Construction Milestone Schedule

  3. Project Milestones – Surgery Vertical Expansion: • Preparation for Structural Steel • Close Arlington Street Capture Site Set up Crane for Structural Steel • Open Arlington Street Target Start – 2/22/10 Target Start – 4/12/10 Target Start - 12/31/10

  4. Site Phasing Diagram – Surgery Vertical Expansion Ambulance Access to be Maintained at All Times Construction Zone for Crane, Material Deliveries, etc.

  5. Project Milestones – New Bed Tower: • Wound Care Renovations • CEP Equipment Removal • Construct Temporary Waldemere Garage Entrance • After Garage Entrance is complete construct Interim Main Entrance • Old Central Energy Plant Structure Demolition • Construct Temporary ECC Canopy & Drop off • Open Temporary Canopy & Drop Off / Close Hawthorne in Front of ECC / Construct New ECC Drop Off • Install New & Relocate Site Utilities / Construct New Loop Road • Open New Loop Road / New Drop Offs / Close Hawthorne / Capture Site for Bed Tower Demolition / Construct Stair & Elevator Tower & Bridge Connector • New Bed Tower Construction Target Completion - 7/1/10 Target Start - 3/8/10 Target Start - 3/29/10 Target Start - 5/17/10 Target Start - 3/29/10 Target Start - 5/3/10 Target - 6/7/10 Target Start - 5/3/10 Target Start - 9/20/10 Target Start - 12/28/10

  6. Site Phasing Diagram - 1 Create Temporary Garage Entry/Exit onto Waldemere St Remove Equipment from CEP Demolish Old CEP Interim Moves for Surgery Support & Pathology

  7. Site Phasing Diagram - 2 Create Temporary ECC Entry Drop-Off Temporary ECC Entry Canopy

  8. Site Phasing Diagram - 3 Open New Entry/Exit at Waldemere Garage Build Temp Main Entrance Canopy, Drop-off & Vestibule Construct New Loop Road and Associated Utilities Close Hawthorne Street Open Temporary ECC Entry Canopy & Drop-off Construct New ECC Vestibule, Canopy & Drop-off Temporary Route to ECC

  9. Site Phasing Diagram - 4 Open New Loop Road Open Temporary Main Entry Canopy & Drop-off Open ECC Vestibule, Canopy & Drop-off Demolish Existing Main Entry Canopy Demolish Portion of Critical Care Tower for New Bridge Demolish Northeast Tower

  10. Site Phasing Diagram - 5 Construct New Bed Tower and Bridge