tank 85 foundation l.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Tank 85 Foundation PowerPoint Presentation
Download Presentation
Tank 85 Foundation

Loading in 2 Seconds...

play fullscreen
1 / 16

Tank 85 Foundation - PowerPoint PPT Presentation


  • 208 Views
  • Uploaded on

Tank 85 Foundation . View of poured auger pile. Setting up for next pile. This process repeated itself 310. Tank 85 Foundation. Tying the cages for the poured piling. Auger pile boring in progress. New cage ready to place when gout is poured. Tank 85 Foundation.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Tank 85 Foundation' - Ava


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
tank 85 foundation
Tank 85 Foundation
  • View of poured auger pile.
  • Setting up for next pile.
  • This process repeated itself 310.
tank 85 foundation2
Tank 85 Foundation
  • Tying the cages for the poured piling.
  • Auger pile boring in progress.
  • New cage ready to place when gout is poured.
tank 85 foundation3
Tank 85 Foundation
  • The grout in some piling settled and was repaired. Grout was chipped to a clean surface and re-poured.
  • Pouring the repair.
tank 85 foundation4
Tank 85 Foundation
  • Excavating to sub-grade for the mud slab.
  • Excavating continues while the mud slab is being poured.
tank 85 foundation5
Tank 85 Foundation
  • Mud slab complete and form setting in progress. Laying out support bars for re-bar work to begin.
  • Form setting for the slab well under way.
tank 85 foundation6
Tank 85 Foundation
  • First mat of re-bar placed Oct. 24/25,06
  • Placing top mat Oct. 26/27,06
tank 85 foundation7
Tank 85 Foundation
  • Re-bar is complete and ready for concrete pour Oct. 28, 06.
tank 85 foundation8
Tank 85 Foundation
  • Tying wall dowels and support dowels Oct 27, 06.
  • Water-stop placed so it can be repositioned while the concrete is being poured
tank 85 foundation9
Tank 85 Foundation
  • 5AM Oct 28,06. First two loads of concrete.
  • Pouring with two pump trucks
tank 85 foundation10
Tank 85 Foundation
  • 5:45 AM, pour well under way.
tank 85 foundation11
Tank 85 Foundation
  • Grading in progress prior to setting panels Nov. 2,06.
  • Preparing to set inner ring wall.
tank 85 foundation12
Tank 85 Foundation
  • 7AM Sat. anchor bolts set and checked, re-bar complete, ready to pour.
  • Pour approximately 40 % at 9:30 AM
tank 85 foundation13
Tank 85 Foundation
  • Ring wall completely poured.
  • Ring wall stripped and grading for tank contractor started
tank 85 foundation14
Tank 85 Foundation
  • Liner installation well under way.
  • Liner nearly completed.
tank 85 foundation15
Tank 85 Foundation
  • Ramp in place for placing of sand and entrance of crane and materials. 11-13-06
  • First of many loads of sand, 11-14-06
tank 85 foundation16
Tank 85 Foundation
  • Sand fill covered for the night. 11-15-06
  • Compacting first lift of sand. Tested at 105-108.