An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Market Trials Update NATF May 4, 2010 http://nodal.ercot.com 1

  2. Agenda • General Reminders / Updates • Phase 4 in Review • 90 Day Look Ahead http://nodal.ercot.com 2

  3. Market Trials 2010 Roadmap http://nodal.ercot.com 3

  4. General Updates / Reminders • Reminder: Weekly Friday Market Call Changes • ERCOT will be adjusting the agenda, effective 5/7/2010 • 09:00 AM-09:30 AM Outage Scheduling • 09:30 AM-10:00 AM Congestion Revenue Rights • 10:00 AM-11:00 AM Day Ahead Market / RUC / SASM • 11:00 AM-12:00 PM Real Time Market / LFC • 12:00 PM-01:00 PM Break • 01:00 PM-02:00 PM Settlements and Billing / COMs • The weekly Monday kick off meeting will remain in place, unchanged • Environment Availability for May 2010 • The Nodal Production Environment will be available Monday – Friday from 8am – 6pm for all systems except EMS / SCADA and SCED • EMS / SCADA and SCED will continue to be monitored, maintained and available 24x7 • ERCOT will continue to submit test transactions to verify and performance test systems • Additionally, ERCOT will also begin the process of testing fail-overs. • Initially, this will be during non-business hours • Once the process is matured, we will perform these during business hours • Test date / times will be communicated on Friday market calls so that MPs may also test their own failure process • Reminder: ERCOT is looking for suggestions for additional Operational Scenarios • Send these to markettrials@ercot.com • Deadline for submissions is 5/17/2010 http://nodal.ercot.com 4

  5. Phase 4 in Review • Day Ahead Market • Participation levels: • 169 / 265 QSEs actively participating in the Day Ahead Market >50% of the • 7 / 265 are newly registered and ramping up • 45 / 265 are participating under the 50% requirement • 44 / 265 are not participating • Cleared 9 Market-Facing Day Ahead Markets and ran DRUC, SASM and HRUC • Telemetry update • ERCOT continues to reach out to TSPs and QSEs on telemetry issues • 260 QSE telemetry points • Mostly due to incorrect ownership information • 145 of these will be corrected in the next model load • 357 TSP telemetry points • 288 of these are being worked by the TSPs • The remainder fall into the following categories: ERCOT investigating, considered “future” points and ownership issues • Expect resolution of most points by 5/10/2010 • Quality (ICCP server to server only) • TSP Quality currently has 1356 suspect points: 97.9% Good overall • QSE Quality currently has 871 suspect points: 94.9% Good overall http://nodal.ercot.com 5

  6. Phase 4 in Review • Real Time Market (continued) • Submissions • >95% of the expected TPOs are consistently submitted • Individual LFC tests • 23 tests conducted in MT4 • 10 additional tests are scheduled prior to the 5 / 7 timeline • Model / Data Update • Delayed the start of weekly updates (currently on bi-weekly updates) • Continue to work on registration data • CRR • Monthly Auction ran and invoiced as planned • Initiated Bid Window for Multi-Month Auction • Settlements Began on time for DAM / RTM Operating 4/21/2010 http://nodal.ercot.com 6

  7. Phase 4 in Review • Primary issues with DAM / RUC coming out of Phase 4 • Bid/Offer IDs with special characters • QSEs do not submit special characters until resolved • This will be included in 1.19L • ETA early June • MMS subroutines having issues with certain combinations of decimals in clearing process • The suspected root cause was that 2 QSEs had identical bids • Will be fixed in emergency patch from vendor in approx. 1 week • Circuit Breaker outages seen as always ‘Open’ • Fixed in MMS Patch 7 – ETA TBD • MMS numbers the main network incorrectly when integrated with outages (depends on combination of outages). • Included in the emergency patch in approx 1 week http://nodal.ercot.com 7

  8. 90 Day Outlook : May Market Activities Jan Feb Mar Apr May June July Aug Functional Area Targeted Activities for May 2010 • ERCOT ramps to DAM / DRUC 5x / weekly • 2hr LFC closed loop test executed • ERCOT complete Balance of Year auction • ERCOT executes June Monthly CRR Auction • ERCOT releases credit integration • SASM executed as needed • ERCOT executes limited HRUC • ERCOT ramps to reflect protocol timelines on a best effort basis • Real-Time Market • Congestion Revenue Rights • Day-Ahead Market • Reliability Unit Commitment • Outage Scheduler • COMS/Settlements • Network Modeling • Nodal Reports • Credit • Full Integration

  9. 90 Day Outlook : June Market Activities Jan Feb Mar Apr May June July Aug Functional Area Targeted Activities for June 2010 • Operational scenarios executed • 8hr LFC closed loop test executed • ERCOT executes July Monthly CRR Auction • DAM / DRUC Continues 5x / weekly • SASM executed as needed • ERCOT executes limited HRUC • Protocol timelines on a best effort basis • Real-Time Market • Congestion Revenue Rights • Day-Ahead Market • Reliability Unit Commitment • Outage Scheduler • COMS/Settlements • Network Modeling • Nodal Reports • Credit • Full Integration

  10. 90 Day Outlook : July Market Activities Jan Feb Mar Apr May June July Aug Functional Area Targeted Activities for July 2010 • Exercise ‘Normal State’ processes and procedures, including weekends • 48hr LFC closed loop test executed • DAM / DRUC executes 7x / weekly for two weeks • ERCOT executes HRUC 7x24 during 7 day weeks • Protocol timelines during 7 day weeks • ERCOT executes August Monthly CRR Auction • SASM executed as needed • Real-Time Market • Congestion Revenue Rights • Day-Ahead Market • Reliability Unit Commitment • Outage Scheduler • COMS/Settlements • Network Modeling • Nodal Reports • Credit • Full Integration

  11. Q&A Q&A / Open Forum http://nodal.ercot.com 11