Managing Projects that are Destined to Fail

Managing Projects that are Destined to Fail . Lena Salim, PMP, Prince 2, PSM. About Me. Where I got my theories from ? PMP Prince 2 PSM MBIS ( Australian Nat Univ ) Managed projects ? Current status : Ready for the next challenge!. Agenda. Welcome drinks & nibbles

zeki
Download Presentation

Managing Projects that are Destined to Fail

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing Projectsthat are Destined to Fail Lena Salim, PMP, Prince 2, PSM

  2. About Me • Where I gotmytheoriesfrom? • PMP • Prince 2 • PSM • MBIS (Australian Nat Univ) • Managedprojects? • Currentstatus: Ready for the next challenge!

  3. Agenda • Welcome drinks & nibbles • Interactive discussions • PM Tooldemofrom Roll • Question & Answers

  4. Definition of Fail • Whatisa failingproject? • Objective data: cost, time, scope, quality • Subjective data: atmosphere • Case Study: ASB Classic

  5. Definition of Fail • Whoactually has the power to define the destiny of a project? • Always know your power & rights! • Whatsyourkpi? • Whatsyourlevel of authority? • What if point 1 & 2 dont match?

  6. Letssee….. Whatwecan do?

  7. Step 1: Look at the Project Plan • Project Plan (Estimation Based) : • Scope, Schedule, Budget • Quality, HR, Communication, Risk, Procurement • Anymissing info? • Case Study: 2 Existingproject plans  Whatdoesthismean?

  8. Step 2: Existing Project KPI • Easykpi: • % completion [calculatevelocity] • Vs. Remaining scope, budget and time • Advanced kpi- EVM (spi, cpi, BAC) • ASB Classic: no kpi. Look into PM Tools (Tasktracking, time tracking), incurred bills, etc

  9. Step 3: Stop Existing Damage • Find the leaks, mendit • Whathappenned in the pastis not yourfault (e.g. damagedfloor, chairs) • Make sure others know this • ASB Classic: • no kpi, • no communication plan, • no integration point, • unclearroles & responsilibilities • 15+ remotestakeholdersdumpedinto 1 email thread!!

  10. Step 4: Create a New Plan • Extra $$$, time, resources • New team rules • Adjustment in scope & quality plan • ASB Classic: • Lean equipment • No more helpingothers out • Regular communication, clear expectations, createsub threads

  11. Step 5: Image Repair • Anounce the changes underway • ASB Classic: • Call eachstakeholder (client & stakeholder) • Introducemyself, personaltouch • Hold a formal meeting (internal team) • Let them know the new plan, only the bits thatwilleffectthem

  12. Step 6: Monitoring & Controlling • Keeptrack on: • What?ongoingtasks • Who? Person in charge • Caution! blockers • ASB Classic: • Danny struggleswithstakeholders • Alan struggleswithworkloads

  13. Step 7: Removeimpediments • Set up a meeting withSubjectMatter Experts • Addresources • Re-prioritizetasks (put a task on hold) • ASB Classic: • Take over theirtasks • Coaching • FindInterns