1 / 21

Innovative Tools for Energy Savings

in Municipal WWTPs. Innovative Tools for Energy Savings. T. Allbaugh, P.E., S. J. Kang, Ph.D., P.E. , K. Williams, P.E., W. Kramer, P.E., G. Jones, P.E., K. P. Olmstead, Ph.D., P.E., L. Thomas, M. Jessee, S. Westover, P.E. Typical Energy Usage in U.S. Wastewater Treatment Plants.

zack
Download Presentation

Innovative Tools for Energy Savings

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. in Municipal WWTPs Innovative Tools forEnergy Savings T. Allbaugh, P.E., S. J. Kang, Ph.D., P.E. , K. Williams, P.E., W. Kramer, P.E., G. Jones, P.E., K. P. Olmstead, Ph.D., P.E., L. Thomas, M. Jessee, S. Westover, P.E.

  2. Typical Energy Usage in U.S.Wastewater Treatment Plants • Electricity at Average Plant: • 1500 kWh/Million Gallons (MG) treated for secondary treatment • Advanced Treatment Plant: 2000 to 3000 kWh/MG • Other Energy Use • External supply of Carbon; methanol; Micro-C • Natural gas

  3. Reasonable Expectations

  4. Typical Power Use Distribution

  5. Case History: Energy Optimization Study at 46 MGD Tertiary Treatment Plant • Energy Optimization Team: Operation, safety, maintenance, administration • Process optimization • Utility bill and energy use analysis • Develop alternatives and assess feasibility • Life-cycle costing • Priority ranking by team votes • Funding decisions

  6. YCUA WWTP • Recently expanded for 46 MGD average design flow • Tertiary treatment (biological P removal, filters, UV disinfection) • Belt presses and fluid bed incinerator • All flow is pumped to the site

  7. Base Line Energy Costs • $2.7 M at WWTP/year • $0.4 M at pump stations/year • Average 9 cents/KWH • Team Goal : Save 5% or more

  8. Average Power Use Before the Project3708 KW

  9. Average Power Use After Implementation2655 KW

  10. Aeration Blowers • A centrifugal blower system supplies air to aeration, filter backwash, and clear well • At current loadings, the power requirement could be reduced from 1,070 to 940 hp for one blower modification • COST: $76,000 • SAVINGS: $68,000 per year • Payback in 14 months

  11. Demand Anticipation • Demand Charge = Single highest 30-minute integrated reading of the demand meter during on-peak hours • In place for 12 months • $13.75 per kilowatt • Target decrease 300KW ($49,500/year) • Defined protocol for operator response

  12. Demand History

  13. HV Controls in Solids and PSST Building • Original HV equipment controls have been disconnected; system is presently being run manually • Upgrade controls to Direct Digital Controls (DDC) with METASIS system • COST: $240,000 • SAVINGS: $140,000 per year • Payback in < two years

  14. Intermittent Ventilation for Process Areas • Dewatering area, cake trucking area, and blower building not always occupied; continuous ventilation unnecessary • Install local controls, METASYS programming, and H2S/O2 alarm systems to only turn on HVAC when areas are occupied • COST: $40,000 • SAVINGS: $43,000 per year • Payback < one year

  15. Incinerator Room Heat Recovery • Space above fluid bed always HOT • Boiler combustion air un-tempered in winter • Adjacent dewatering area requires 12 air changes per hour • Project provides additional heated ventilation to dewatering, and pre-heated combustion air for boilers

  16. Building Lighting Philosophy • Original design incorporated highly efficient lights on 100% of the time in galleries and process areas • Changes incorporate slightly less efficient lights but provide immediate illumination

  17. Lighting System Retrofit • Fixtures are original, 1970s T12 fluorescent and metal halide High-Intensity Discharge (HID) lights • Replace all T12 with T8 lamps– Non-HID fluorescent tubes with electronic ballasts • COST: $265,000 • SAVINGS: $110,000 per year • Payback in < three years

  18. Intermittent Ventilation of Drywells at Four Pump Stations • Crews enter once per week for two hours • Engineering standards call for: • Six air changes per hour , or • Thirty air changes for ten minutes • Upgrade controls with SCADA • COST: $40,000 • SAVINGS: $21,000 per year • Payback in two years

  19. Adopted Plan • Optimization Study Cost: $59,000 • SRF Project Plan for $1.0M approved with 40% forgiveness of the loan principal, July 2009 • Design and construction underway, 2010-11 • Annual Cost Savings: $450,000, or 11% savings

  20. Summary of Selected Projects

  21. Questions?

More Related