Maintenance center albany
Download
1 / 8

MAINTENANCE CENTER ALBANY - PowerPoint PPT Presentation


  • 203 Views
  • Uploaded on

MAINTENANCE CENTER ALBANY. 2010 LRG Jim Clanton. MCA TEAM. Maintenance Center Albany MF Management Team. Project Lead: Jim Clanton MFP Coordinator: Bobby Farris Planner/Estimator: Rob Tyler MFP Liaison: SSgt Collins Project Section Supervisor: Blase Goodman

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MAINTENANCE CENTER ALBANY' - yin


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Maintenance center albany
MAINTENANCE CENTER ALBANY

2010 LRG

Jim Clanton


MCA TEAM

Maintenance Center Albany MF Management Team

  • Project Lead: Jim Clanton

  • MFP Coordinator: Bobby Farris

  • Planner/Estimator: Rob Tyler

  • MFP Liaison: SSgt Collins

  • Project Section Supervisor: Blase Goodman

  • Program Management Branch Head: Harold Eidson


Mobile facilities completed fy10

PRODUCTION

Mobile Facilities Completed FY10

BF-05, Qty 1.

BF-15 (Army), Qty 8.

CL-07, Qty 2.

FS-01, Qty 12.

HC-02, Qty 1.

HT-02A, Qty 2.

HT-01B, Qty 2.

JU-01, Qty 6.

KA-31, Qty 1.

MV-01B, Qty 1.

MV-02A, Qty 1.

TR-01, Qty 3.


Mobile facilities in process scheduled fy10

SCHEDULE

Mobile Facilities in Process/Scheduled FY10:

FS-01, Qty 7.

JU-01, Qty 6.

KA-31, Qty 9.

SU-12, Qty 1.

NB-03, Qty 1.


Tqg facility

TQG

TQG Facility

  • Construction in progress, ECD August/Sept 2010.


Tqg mmg 1a notes

TQG/MMG

TQG/MMG-1A Notes

  • 45 Each TQGs on hand:

    • MEP-807A, 7 each.

    • MEP-809A, 38 each.

  • 43 Each MMG-1A on hand.

    • 17 RFU

    • Prepping 3 for shipment.


Issues concerns
Issues/Concerns

  • Parts issues

    • FS-01 Disconnect Switch, ENF100X-3PB6-N.

      • Long lead time, built to order by Bussman.

      • 7 FS-01s completed ap this switch.