Hampton Roads Transit Capital Investment Prioritization Scheme. ABOUT HRT. 2 nd largest transit operator in Virginia 370 square mile service area spread across six jurisdictions Operates bus, light rail (opened in 2011), and ferry service. WHY PRIORITIZE CAPITAL NEEDS?.

Download Presentation

Hampton Roads Transit Capital Investment Prioritization Scheme

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Hampton roads transit capital investment prioritization scheme

Hampton Roads Transit Capital Investment Prioritization Scheme


About hrt

ABOUT HRT

2nd largest transit operator in Virginia

370 square mile service area spread across six jurisdictions

Operates bus, light rail (opened in 2011), and ferry service

Foursquare ITP | HRT Capital Project Prioritization


Why prioritize capital needs

WHY PRIORITIZE CAPITAL NEEDS?

Guide agency’s first ever Capital Investment Plan (CIP)

Justify capital expenditures to stakeholders, especially local jurisdictions

Decide between various important projects competing for the limited funding available

Have a plan and become less reactive to capital needs

Foursquare ITP | HRT Capital Project Prioritization


Cip process

CIP PROCESS

Foursquare ITP | HRT Capital Project Prioritization


Project submissions

PROJECT SUBMISSIONS

  • Departments submitted 77 projects valued at almost $200 million dollars

  • Wide range of projects such as new buses, IT modernization, facility upgrades, and security enhancements

  • Each department responsible for filling out a project score sheet for every capital submittal

Foursquare ITP | HRT Capital Project Prioritization


Priotization scoring system

PRIOTIZATION SCORING SYSTEM

  • Based on responses on project score sheets:

    • 40% of score based on quantifiable benefits

    • 40% of score based on qualitative benefits

    • 20% of score based on adherence to agency strategic goals and objectives

  • Scoring automated through Access database

Foursquare ITP | HRT Capital Project Prioritization


Evaluation criteria

EVALUATION CRITERIA

  • Based on senior executive team strategic workshop

    • Focus on customers

    • Attend to state of good repair needs

    • Make HRT more financially independent

    • Develop and maintain highly qualified and effective workforce

    • Prioritize projects needed to complete existing investments

Foursquare ITP | HRT Capital Project Prioritization


Troubleshooting

TROUBLESHOOTING

  • Submitters provided varying levels of detail on capital projects

  • Departments unable to quantify benefits

  • Project submissions had to be re-scored by one party for greater consistency/neutrality

  • Scoring system revised multiple times to give proper weight to those projects deemed most important

Foursquare ITP | HRT Capital Project Prioritization


Key conclusions

KEY CONCLUSIONS

  • Involve decision makers from the start

  • Keep scoring metrics simple

  • Can’t rely on only quantitative measures

  • Need for balance between detail and simplicity