Los Angeles County Metropolitan Transportation Authority. Item: #12. SR-138 Capacity Enhancements. Measure R Project Delivery Committee June 17, 2010. SR-138 Capacity Enhancements. 26-mile rural highway extending from SR-14 to SR-18

Download Presentation

SR-138 Capacity Enhancements

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Sr 138 capacity enhancements

Los Angeles County

Metropolitan Transportation Authority

Item: #12

SR-138 Capacity Enhancements

Measure R Project Delivery Committee

June 17, 2010


Sr 138 capacity enhancements1

SR-138 Capacity Enhancements

  • 26-mile rural highway extending from SR-14 to SR-18

  • Roadway widening from 2 to 4 lanes with turn pockets at critical intersections

  • Measure R: $200 million


Status

Status

Phase I:

  • Six Segments:

    • Four constructed

    • Remaining two scheduled for advertisement:

      • September 2010 and January 2011


Status cont

Status (Cont.)

Phase II:

  • Eight Segments:

    • Environmentally cleared

    • Begin design in Summer 2010


Next steps

Next Steps

  • Execute Funding Agreement with Caltrans to initiate design